RIGHT-OF-WAY CLEARANCE US-77: FROM 2.0 MILES SOUTH OF I-35, EXTEND NORTH NEAR THACKERVILLE . PROJECT LENGTH = 1.780 MILES
- Let date
- Thursday, July 23, 2020
- Contract
- 200253
- J/P numbers
- 28803(08)
- District
- Division 7
- County
- Love
- Highway
- Limits
- RIGHT-OF-WAY CLEARANCE US-77: FROM 2.0 MILES SOUTH OF I-35, EXTEND NORTH NEAR THACKERVILLE . PROJECT LENGTH = 1.780 MILES
- Project number
- STP-243C(038)RW
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $150,000 | ||
| 1 | RMR DEMOLITION, LLC Low bidder | $84,300 | -43.8% | |
| 2 | JACKSON WRECKING & DEMOLITION | $97,000 | -35.3% | +15.1% |
| 3 | Robin Hausner Demolition, LLC | $98,113 | -34.6% | +16.4% |
| 4 | B & H CONSTRUCTION, LLC. | $687,135 | +358.1% | +715.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 RMR DEMOLITION,… | #2 JACKSON WRECKIN… | #3 Robin Hausner D… | #4 B & H CONSTRUCT… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 233(A) 2817 | VEGETATIVE MULCHING | 1 | AC | $1,000.00 | $250.00 | $3,000.00 | $100.00 | $135.00 |
| 2 | 619(G) 0094 | RIGHT-OF-WAY CLEARANCE | 1 | LSUM | $141,000.00 | $72,050.00 | $90,000.00 | $96,513.00 | $205,890.00 |
| 3 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $2,000.00 | $2,000.00 | $1,000.00 | $500.00 | $68,250.00 |
| 4 | 641 1552 | MOBILIZATION | 1 | LSUM | $6,000.00 | $10,000.00 | $3,000.00 | $1,000.00 | $412,860.00 |