RIGHT-OF-WAY CLEARANCE SH-10/SH-10C: FROM THE MISSOURI STATE LINE , EXTEND WEST. PROJECT LENGTH = 4.559 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .
- Let date
- Thursday, May 14, 2020
- Contract
- 200206
- J/P numbers
- 24277(10)
- District
- Division 8
- County
- Ottawa
- Highway
- Limits
- RIGHT-OF-WAY CLEARANCE SH-10/SH-10C: FROM THE MISSOURI STATE LINE , EXTEND WEST. PROJECT LENGTH = 4.559 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .
- Project number
- STP-258C(070)RW
Bidders 8
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $133,743 | ||
| 1 | H & G Paving Contractors Inc. Low bidder | $65,000 | -51.4% | |
| 2 | Robin Hausner Demolition, LLC | $66,511 | -50.3% | +2.3% |
| 3 | D T SPECIALIZED SERVICES, INC. | $75,475 | -43.6% | +16.1% |
| 4 | JACKSON WRECKING & DEMOLITION | $78,800 | -41.1% | +21.2% |
| 5 | M & M WRECKING, INC. | $94,742 | -29.2% | +45.8% |
| 6 | MJM CONSTRUCTION & APPLICATION, LLC | $98,142 | -26.6% | +51.0% |
| 7 | RMR DEMOLITION, LLC | $129,000 | -3.5% | +98.5% |
| 8 | GROUND LEVEL, LLC | $224,150 | +67.6% | +244.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 H & G Paving Co… | #2 Robin Hausner D… | #3 D T SPECIALIZED… | #4 JACKSON WRECKIN… | #5 M & M WRECKING,… | #6 MJM CONSTRUCTIO… | #7 RMR DEMOLITION,… | #8 GROUND LEVEL, L… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 233(A) 2817 | VEGETATIVE MULCHING | 1 | AC | $5,000.00 | $1,000.00 | $100.00 | $2,500.00 | $3,000.00 | $13,068.00 | $3,500.00 | $1,500.00 | $12,500.00 |
| 2 | 619(G) 0094 | RIGHT-OF-WAY CLEARANCE | 1 | LSUM | $122,243.00 | $58,000.00 | $64,411.29 | $65,975.00 | $71,800.00 | $74,374.00 | $79,642.00 | $106,500.00 | $184,150.00 |
| 3 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $1,500.00 | $1,000.00 | $500.00 | $0.00 | $1,000.00 | $0.00 | $5,000.00 | $1,000.00 | $7,500.00 |
| 4 | 641 1552 | MOBILIZATION | 1 | LSUM | $5,000.00 | $5,000.00 | $1,500.00 | $7,000.00 | $3,000.00 | $7,300.00 | $10,000.00 | $20,000.00 | $20,000.00 |