RIGHT-OF-WAY CLEARANCE US-62: FROM 3.4 MILES EAST OF THE SH -82 JUNCTION, EXTEND EAST NEAR TAHLEQUAH . PROJECT LENGTH = 2.47 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .
- Let date
- Thursday, November 14, 2019
- Contract
- 190343
- J/P numbers
- 27111(09)
- District
- Division 1
- County
- Cherokee
- Highway
- Limits
- RIGHT-OF-WAY CLEARANCE US-62: FROM 3.4 MILES EAST OF THE SH -82 JUNCTION, EXTEND EAST NEAR TAHLEQUAH . PROJECT LENGTH = 2.47 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .
- Project number
- SSP-211B(040)RW
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Robin Hausner Demolition, LLC Low bidder | $60,010 | ||
| 2 | RMR DEMOLITION, LLC | $87,400 | +45.6% | |
| 3 | J.E. DIRT WURX, LLC | $94,760 | +57.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Robin Hausner D… | #2 RMR DEMOLITION,… | #3 J.E. DIRT WURX,… |
|---|---|---|---|---|---|---|---|---|
| 1 | 233(A) 2817 | VEGETATIVE MULCHING | 1 | AC | $5,000.00 | $200.00 | $1,000.00 | $3,000.00 |
| 2 | 619(G) 0094 | RIGHT-OF-WAY CLEARANCE | 1 | LSUM | $111,400.00 | $58,010.00 | $77,400.00 | $87,260.00 |
| 3 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $5,000.00 | $500.00 | $1,000.00 | $1,500.00 |
| 4 | 641 1552 | MOBILIZATION | 1 | LSUM | $5,000.00 | $1,300.00 | $8,000.00 | $3,000.00 |