Bid tab 190321

Let Oct 17, 2019 · Division 2 · Mccurtain Sign up free

‹ Oct 2019 results

RIGHT-OF-WAY CLEARANCE US-259: FROM 2.0 MILES NORTH OF THE TEXAS STATE LINE , EXTEND NORTH NEAR IDABEL . PROJECT LENGTH = 13.44 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .

Let date
Thursday, October 17, 2019
Contract
190321
J/P numbers
24404(07)
District
Division 2
County
Mccurtain
Highway
Limits
RIGHT-OF-WAY CLEARANCE US-259: FROM 2.0 MILES NORTH OF THE TEXAS STATE LINE , EXTEND NORTH NEAR IDABEL . PROJECT LENGTH = 13.44 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .
Project number
SSP-245N(058)RW

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$85,300
1 RMR DEMOLITION, LLC Low bidder $67,700 -20.6%
2 Robin Hausner Demolition, LLC $67,777 -20.5% +0.1%
3 Built Right Construction, LLC $77,500 -9.1% +14.5%
4 B & B CONSTRUCTION SERVICE J.T., INC. $166,000 +94.6% +145.2%

Bid tab: unit prices 4 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 RMR DEMOLITION,…#2 Robin Hausner D…#3 Built Right Con…#4 B & B CONSTRUCT…
1233(A) 2817 VEGETATIVE MULCHING1AC $1,000.00 $1,000.00 $100.00 $2,500.00 $6,000.00
2619(G) 0094 RIGHT-OF-WAY CLEARANCE1LSUM $76,300.00 $57,200.00 $66,677.00 $65,000.00 $140,000.00
3880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $4,000.00 $1,500.00 $500.00 $5,000.00 $5,000.00
4641 1552 MOBILIZATION1LSUM $4,000.00 $8,000.00 $500.00 $5,000.00 $15,000.00