RESURFACE (ASPHALT ) COUNTY ROAD (SHAY ROAD ): 2.8 MILES NORTH OF THE TEXAS STATE LINE NEAR WILLIS. PROJECT LENGTH = 3.500 MILES

Let date
Thursday, January 17, 2019
Contract
190010
J/P numbers
29988(04)
District
Division 2
County
Marshall
Highway
Limits
RESURFACE (ASPHALT ) COUNTY ROAD (SHAY ROAD ): 2.8 MILES NORTH OF THE TEXAS STATE LINE NEAR WILLIS. PROJECT LENGTH = 3.500 MILES
Project number
CIRB-248D(040)RB

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$833,379
1 OVERLAND CORPORATION Low bidder $793,297 -4.8%
2 THE CUMMINS CONSTRUCTION CO., INC. $829,095 -0.5% +4.5%
3 Silver Star Construction Company, Inc. $1,044,850 +25.4% +31.7%

Bid tab: unit prices 10 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 OVERLAND CORPOR…#2 THE CUMMINS CON…#3 Silver Star Con…
1402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E2,826TON $27.58 $23.90 $28.50 $36.20
2407(B) 0250 TACK COAT7,228GAL $2.05 $0.0100 $2.00 $2.50
3411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)7,962TON $67.49 $73.60 $75.80 $88.40
4411(H) 6210 SUPERPAVE, TYPE S3(PATCH)(PG64-22OK)400TON $85.35 $135.00 $97.50 $152.80
5412 5267 COLD MILLING PAVEMENT367SY $6.00 $13.15 $11.00 $12.50
6850(A) 8110 SHEET ALUMINUM SIGNS330SF $22.50 $22.00 $22.00 $23.50
7851(C) 8324 2" SQUARE TUBE POST299LF $7.75 $12.45 $12.00 $12.80
8856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)73,920LF $1.00 $0.3500 $0.3300 $0.3500
9880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $7,500.00 $35,000.00 $2,300.00 $57,500.00
10641 1399 MOBILIZATION1LSUM $75,761.00 $9,000.00 $50,000.00 $59,976.30