RESURFACE (ASPHALT ) COUNTY ROAD (BOGGY DEPOT ROAD ): FROM 8.0 MILES WEST OF THE US-69 JUNCTION, EXTEND EAST NEAR TUSHKA . PROJECT LENGTH = 7.138 MILES
- Let date
- Thursday, January 17, 2019
- Contract
- 190002
- J/P numbers
- 31192(04)
- District
- Division 2
- County
- Atoka
- Highway
- Limits
- RESURFACE (ASPHALT ) COUNTY ROAD (BOGGY DEPOT ROAD ): FROM 8.0 MILES WEST OF THE US-69 JUNCTION, EXTEND EAST NEAR TUSHKA . PROJECT LENGTH = 7.138 MILES
- Project number
- CIRB-203C(068)RB
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,836,207 | ||
| 1 | THE CUMMINS CONSTRUCTION CO., INC. Low bidder | $1,624,247 | -11.5% | |
| 2 | OVERLAND CORPORATION | $1,876,820 | +2.2% | +15.6% |
| 3 | APAC-CENTRAL, INC. | $2,358,193 | +28.4% | +45.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 THE CUMMINS CON… | #2 OVERLAND CORPOR… | #3 APAC-CENTRAL, I… |
|---|---|---|---|---|---|---|---|---|
| 1 | 402(E) 0225 | TRAFFIC BOUND SURFACE COURSE TYPE E | 2,174 | TON | $41.68 | $21.60 | $20.40 | $25.50 |
| 2 | 407(B) 0250 | TACK COAT | 13,828 | GAL | $2.48 | $2.05 | $0.0100 | $2.50 |
| 3 | 411(B) 5945 | SUPERPAVE, TYPE S3(PG 64-22 OK) | 12,899 | TON | $64.00 | $55.25 | $67.70 | $89.85 |
| 4 | 411(C) 5960 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 10,395 | TON | $65.17 | $66.70 | $76.70 | $91.20 |
| 5 | 411(I) 6310 | SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 500 | TON | $102.86 | $87.30 | $115.00 | $138.00 |
| 6 | 412 5267 | COLD MILLING PAVEMENT | 1,527 | SY | $6.00 | $5.50 | $6.35 | $15.20 |
| 7 | 854(A) 8800 | TRAFFIC STRIPE(PAINT)(4" WIDE) | 150,765 | LF | $0.1300 | $0.1000 | $0.1000 | $0.1000 |
| 8 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $7,500.00 | $3,800.00 | $30,000.00 | $33,300.00 |
| 9 | 641 1552 | MOBILIZATION | 1 | LSUM | $120,632.00 | $72,000.00 | $49,500.00 | $20,600.00 |