Bid tab 180228

Let Jun 14, 2018 · Division 8 · Tulsa Sign up free

‹ Jun 2018 results

RIGHT-OF-WAY CLEARANCE SH-20: FROM 0.09 MILES EAST OF US -75, EXTEND EAST NEAR COLLINSVILLE. PROJECT LENGTH = 3.723 MILES

Let date
Thursday, June 14, 2018
Contract
180228
J/P numbers
24346(10)
District
Division 8
County
Tulsa
Highway
Limits
RIGHT-OF-WAY CLEARANCE SH-20: FROM 0.09 MILES EAST OF US -75, EXTEND EAST NEAR COLLINSVILLE. PROJECT LENGTH = 3.723 MILES
Project number
STP-272B(251)RW

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$638,439
1 MJM CONSTRUCTION & APPLICATION, LLC Low bidder $135,500 -78.8%
2 J.E. DIRT WURX, LLC $147,500 -76.9% +8.9%
3 ARK WRECKING OF OK., INC. $155,930 -75.6% +15.1%
4 Robin Hausner Demolition, LLC $248,777 -61.0% +83.6%
5 BECCO CONTRACTORS, INC. $754,000 +18.1% +456.5%

Bid tab: unit prices 4 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 MJM CONSTRUCTIO…#2 J.E. DIRT WURX,…#3 ARK WRECKING OF…#4 Robin Hausner D…#5 BECCO CONTRACTO…
1233(A) 2817 VEGETATIVE MULCHING1AC $8,974.00 $2,500.00 $1,500.00 $5,220.00 $13,000.00 $7,500.00
2619(G) 0094 RIGHT-OF-WAY CLEARANCE1LSUM $609,465.00 $115,000.00 $127,000.00 $142,910.00 $228,777.00 $629,000.00
3880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $10,000.00 $10,000.00 $4,000.00 $6,600.00 $6,000.00 $55,000.00
4641 1552 MOBILIZATION1LSUM $10,000.00 $8,000.00 $15,000.00 $1,200.00 $1,000.00 $62,500.00