RIGHT-OF-WAY CLEARANCE US 277: BEGIN 0.04 MILES EAST OF US -62, EXTEND EAST. PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .
- Let date
- Thursday, May 17, 2012
- Contract
- 120180
- J/P numbers
- 21717(08)
- District
- Division 7
- County
- Comanche
- Highway
- Limits
- RIGHT-OF-WAY CLEARANCE US 277: BEGIN 0.04 MILES EAST OF US -62, EXTEND EAST. PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .
- Project number
- STPY-216C(006)RW
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $91,700 | ||
| 1 | M & M WRECKING, INC. Low bidder | $68,058 | -25.8% | |
| 2 | MIDWEST WRECKING, INC. | $76,510 | -16.6% | +12.4% |
| 3 | T & G CONSTRUCTION, INC. | $77,875 | -15.1% | +14.4% |
| 4 | K & M DIRT SERVICES, LLC | $86,960 | -5.2% | +27.8% |
| 5 | Robin Hausner Demolition, LLC | $88,291 | -3.7% | +29.7% |
| 6 | SCHIRALLI CONSTRUCTION CORP. | $114,420 | +24.8% | +68.1% |
| 7 | CP3 ENTERPRISES, INC. | $170,995 | +86.5% | +151.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 M & M WRECKING,… | #2 MIDWEST WRECKIN… | #3 T & G CONSTRUCT… | #4 K & M DIRT SERV… | #5 Robin Hausner D… | #6 SCHIRALLI CONST… | #7 CP3 ENTERPRISES… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 619(G) 0094 | RIGHT-OF-WAY CLEARANCE | 1 | LSUM | $91,700.00 | $68,058.00 | $76,510.00 | $77,875.00 | $86,960.00 | $88,291.00 | $114,420.00 | $170,995.17 |