BRIDGE PAINTING SH -48/OAK STREET: SH-48, OVER LONG GEORGE CREEK 8.9 MILES N OF US-270. OAK STREET, OVER SH-1, IN THE CITY OF ADA.
- Let date
- Thursday, April 15, 2010
- Contract
- 100303
- J/P numbers
- 20981(04)
- District
- County
- Hughes, Pontotoc
- Highway
- Limits
- BRIDGE PAINTING SH -48/OAK STREET: SH-48, OVER LONG GEORGE CREEK 8.9 MILES N OF US-270. OAK STREET, OVER SH-1, IN THE CITY OF ADA.
- Project number
- BRFY-NBIP(424)
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $256,580 | ||
| 1 | Euro Paint, LLC Low bidder | $186,410 | -27.3% | |
| 2 | POSEIDON CONSTRUCTION, INC. | $227,977 | -11.1% | +22.3% |
| 3 | Panther Industrial Painting, LLC | $323,467 | +26.1% | +73.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Euro Paint, LLC | #2 POSEIDON CONSTR… | #3 Panther Industr… |
|---|---|---|---|---|---|---|---|---|
| 1 | 512 6280 | CLEANING AND PAINTING BRIDGE METAL RAIL | 331.33 | LF | $15.00 | $45.00 | $10.00 | $50.00 |
| 2 | 512(A) 1323 | PAINTING EXISTING STRUCTURES | 1 | LSUM | $124,800.00 | $92,000.00 | $130,771.00 | $133,000.00 |
| 3 | 512(B) 6303 | COLLECTION & HANDLING OF WASTE | 1 | LSUM | $32,000.00 | $3,000.00 | $3,000.00 | $2,000.00 |
| 4 | 512(A) 1323 | PAINTING EXISTING STRUCTURES | 1 | LSUM | $58,560.00 | $40,000.00 | $55,643.00 | $111,000.00 |
| 5 | 512(B) 6303 | COLLECTION & HANDLING OF WASTE | 1 | LSUM | $15,000.00 | $1,500.00 | $3,000.00 | $2,000.00 |
| 6 | 876(C) 8482 | (PL)TRUCK MOUNTED ATTENUATOR | 30 | SD | $22.00 | $8.00 | $25.00 | $10.00 |
| 7 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $3,750.00 | $14,400.00 | $10,000.00 | $20,000.00 |
| 8 | 882(B) 8306 | PORT.CHANGEABLE MESSAGE SIGN | 60 | SD | $20.00 | $6.00 | $25.00 | $10.00 |
| 9 | 641 1399 | MOBILIZATION | 1 | LSUM | $15,640.00 | $20,000.00 | $20,000.00 | $38,000.00 |