Bid codeDescriptionUnitJobs ▼QuantityAvg low bidAvg all bidsAvg estimateLow rangeLast let
202(A)2200UNCLASSIFIED EXCAVATIONCY 150 $25.75$46.81$25.00 $25.75 – $25.75Oct 22, 2026
202(D)2500UNCLASSIFIED BORROWCY 1100 $36.05$52.38$29.00 $36.05 – $36.05Oct 22, 2026
205(A)6200TYPE A-SALVAGED TOPSOILLSUM 11 $7,725.00$12,925.45$5,000.00 $7,725.00 – $7,725.00Oct 22, 2026
221(B)2300TEMPORARY SILT FENCELF 11,200 $6.17$5.79$5.00 $6.17 – $6.17Oct 22, 2026
230(A)7200SOLID SLAB SODDINGSY 14,000 $5.15$6.27$6.00 $5.15 – $5.15Oct 22, 2026
310(B)5300SUBGRADE, METHOD BSY 11,667 $5.15$8.59$4.70 $5.15 – $5.15Oct 22, 2026
408 8100PRIME COATGAL 11,239 $8.47$7.31$10.00 $8.47 – $8.47Oct 22, 2026
411(B)1330SUPERPAVE, TYPE S3(PG 64-22 OK)TON 193 $276.04$416.83$175.00 $276.04 – $276.04Oct 22, 2026
414(A)5200P.C.CONCRETE PAVEMENT(PLACEMENT)SY 11,667 $37.08$49.77$41.00 $37.08 – $37.08Oct 22, 2026
414(G)5800P.C. CONCRETE FOR PAVEMENTCY 1417 $252.79$298.80$250.00 $252.79 – $252.79Oct 22, 2026
501(G)1800CLSM BACKFILLCY 1222 $316.47$317.04$225.00 $316.47 – $316.47Oct 22, 2026
504(A)5200APPROACH SLABSY 1731.2 $303.52$314.74$320.00 $303.52 – $303.52Oct 22, 2026
504(B)5300SAW-CUT GROOVINGSY 11,637.3 $4.94$5.60$5.50 $4.94 – $4.94Oct 22, 2026
504(E)552042" F-SHAPED PARAPETLF 1355 $132.53$173.05$125.00 $132.53 – $132.53Oct 22, 2026
506(A)7225STRUCTURAL STEEL M270 GRADE 50WLB 1348,460 $2.83$3.11$2.75 $2.83 – $2.83Oct 22, 2026
507(A)8210WEATHERING STEEL FIXED BEARING ASSEMBLYEA 112 $1,758.64$2,098.63$2,000.00 $1,758.64 – $1,758.64Oct 22, 2026
507(B)8310WEATHERING STL EXP. BEARING ASSEMBLYEA 112 $1,758.64$2,098.63$2,000.00 $1,758.64 – $1,758.64Oct 22, 2026
509(A)0210CLASS AA CONCRETECY 1222.7 $998.66$1,227.73$880.00 $998.66 – $998.66Oct 22, 2026
509(D)0510CLASS C CONCRETECY 110 $811.71$970.75$850.00 $811.71 – $811.71Oct 22, 2026
511(B)2310EPOXY COATED REINFORCING STEELLB 151,990 $1.95$1.91$1.70 $1.95 – $1.95Oct 22, 2026
513(B)4300CLASS B BRIDGE DECK REPAIRSY 115 $638.60$542.73$400.00 $638.60 – $638.60Oct 22, 2026
513(C)4400CLASS C BRIDGE DECK REPAIRSY 15 $1,030.00$838.58$700.00 $1,030.00 – $1,030.00Oct 22, 2026
515(A)7200WATER REPELLENT (VISUALLY INSPECTED)SY 12,076 $5.15$5.81$5.50 $5.15 – $5.15Oct 22, 2026
517 9110ELASTOMERIC COATINGSF 1666 $32.96$26.04$25.00 $32.96 – $32.96Oct 22, 2026
518(B)0310EXPANSION JOINT SYSTEMLF 185 $206.00$171.28$150.00 $206.00 – $206.00Oct 22, 2026
520(A)1200PREPARATION OF CRACKS, ABOVE WATERLF 179 $41.20$43.78$35.00 $41.20 – $41.20Oct 22, 2026
520(C)1400EPOXY RESIN, ABOVE WATERGAL 16.4 $82.40$133.82$125.00 $82.40 – $82.40Oct 22, 2026
521(A)2200PNEUMATICALLY PLACED MORTARSY 15.2 $1,030.00$1,124.17$825.00 $1,030.00 – $1,030.00Oct 22, 2026
523(A)3200SEALER CRACK PREPARATIONLF 1188 $4.12$4.86$4.50 $4.12 – $4.12Oct 22, 2026
523(B)3300SEALER RESINGAL 12.2 $190.55$193.89$70.00 $190.55 – $190.55Oct 22, 2026
535 7100CORROSION INHIBITOR(SURFACE APPLIED)SY 18.2 $53.56$52.04$60.00 $53.56 – $53.56Oct 22, 2026
619(B)6304REMOVAL OF BRIDGE ITEMSLSUM 11 $97,595.07$153,536.25$100,000.00 $97,595.07 – $97,595.07Oct 22, 2026
619(B)6352REMOVAL OF FENCELF 1225 $5.15$7.73$1.80 $5.15 – $5.15Oct 22, 2026
619(B)6360REMOVAL OF CONCRETE PAVEMENTSY 11,948 $16.48$18.56$15.00 $16.48 – $16.48Oct 22, 2026
619(B)6396REMOVAL OF GUARDRAILLF 1530 $8.64$8.97$6.80 $8.64 – $8.64Oct 22, 2026
619(B)6432REMOVAL OF CABLE BARRIERLF 12,427 $19.05$21.22$28.00 $19.05 – $19.05Oct 22, 2026
619(B)6436REMOVAL OF CONCRETE DITCH LINERLF 1181 $15.45$21.15$7.00 $15.45 – $15.45Oct 22, 2026
619(C)6600SAWING PAVEMENTLF 12,000 $5.15$6.27$5.30 $5.15 – $5.15Oct 22, 2026
623(A)1200BEAM GUARDRAIL W-BEAM SINGLELF 1475 $28.71$31.23$30.00 $28.71 – $28.71Oct 22, 2026
623(G)1820GUARDRAIL END TREATMENT (31")EA 12 $4,017.00$4,405.67$4,000.00 $4,017.00 – $4,017.00Oct 22, 2026
623(I)2050GUARDRAIL BRIDGE CONN-THRIE BEAM (31")EA 12 $3,914.00$4,332.17$3,500.00 $3,914.00 – $3,914.00Oct 22, 2026
624(C)3400FENCE-STYLE SWF (4 BARBED WIRE)LF 1230 $23.17$23.95$8.50 $23.17 – $23.17Oct 22, 2026
628(B)7300HIGH-TENSION CABLE BARRIER(TL-4)LF 12,370 $20.08$26.86$39.00 $20.08 – $20.08Oct 22, 2026
628(C)7400END ANCHORSEA 14 $6,180.00$7,576.67$7,100.00 $6,180.00 – $6,180.00Oct 22, 2026
641 2100MOBILIZATIONLSUM 11 $173,903.90$195,048.89$155,974.98 $173,903.90 – $173,903.90Oct 22, 2026
642(B)3300CONSTRUCTION STAKING LEVEL IILSUM 11 $6,180.00$13,826.67$20,000.00 $6,180.00 – $6,180.00Oct 22, 2026
805(D)3528(PL)REMOVE & RESET EXISTING SIGNSEA 12 $1,133.00$1,243.50$350.00 $1,133.00 – $1,133.00Oct 22, 2026
853 5170GUARDRAIL DELINEATORS(TYPE 1, CODE 1)EA 113 $12.35$13.63$25.00 $12.35 – $12.35Oct 22, 2026
856(A)8207(SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(6" WIDE)LF 125,200 $0.6700$0.7417$1.30 $0.6700 – $0.6700Oct 22, 2026
857(C)9400REMOVABLE PAVEMENT MARKING TAPE(4" WIDE)LF 131,420 $1.68$1.83$1.40 $1.68 – $1.68Oct 22, 2026
857(F)9700PAVEMENT MRKNG.REMOVAL(TRAF.STRP)LF 125,200 $0.3100$0.3533$0.5000 $0.3100 – $0.3100Oct 22, 2026
858(A)0224PAVE.MARKERS CLASS A TYPE 2-CEA 1469 $6.69$7.26$11.00 $6.69 – $6.69Oct 22, 2026
858(A)0228PAVE.MARKERS CLASS A TYPE 2-DEA 11,039 $6.69$7.27$8.50 $6.69 – $6.69Oct 22, 2026
871(B)2300CONST.ZONE IMPACT ATTEN.SD 140 $46.35$48.62$18.00 $46.35 – $46.35Oct 22, 2026
877(B)4300DELIVER PORTABLE LONGITUDINAL BARRIERLF 12,900 $16.89$19.87$29.00 $16.89 – $16.89Oct 22, 2026
877(C)4400RELOCATION OF PORT. LONGITUDINAL BARRIERLF 12,000 $2.62$3.15$5.00 $2.62 – $2.62Oct 22, 2026
880(B)6300CONSTRUCTION SIGNS 0 TO 6.25 SFSD 11,850 $2.06$2.79$0.3000 $2.06 – $2.06Oct 22, 2026
880(B)6310CONSTRUCTION SIGNS 6.26 SF TO 15.99 SFSD 12,390 $0.3000$0.3283$0.6000 $0.3000 – $0.3000Oct 22, 2026
880(B)6320CONSTRUCTION SIGNS 16.0 SF TO 32.99 SFSD 14,010 $0.2000$0.2233$1.00 $0.2000 – $0.2000Oct 22, 2026
880(C)6410CONSTRUCTION BARRICADES(TYPE III)SD 1940 $0.5100$0.5400$1.00 $0.5100 – $0.5100Oct 22, 2026
880(E)6607WARNING LIGHTS(TYPE B)SD 13,700 $0.1400$4.79$0.8000 $0.1400 – $0.1400Oct 22, 2026
880(E)6610WARNING LIGHTS(TYPE C)SD 114,880 $4.63$0.9067$0.1000 $4.63 – $4.63Oct 22, 2026
880(F)6700DRUMSSD 116,730 $0.0200$0.0383$0.2000 $0.0200 – $0.0200Oct 22, 2026
880(G)6810TUBE CHANNELIZERSEA 1326 $64.81$72.27$21.00 $64.81 – $64.81Oct 22, 2026
880(L)7310(SP) TRAFFIC SURVEILLANCE, OHP (NON-BID)HOUR 1740 $77.00$77.00$77.00 $77.00 – $77.00Oct 22, 2026
882(A)8210PORT.CHANGEABLE MESSAGE SIGNSD 1398 $6.18$6.57$16.00 $6.18 – $6.18Oct 22, 2026