Bid code 648(C)6450

GAS LINE RELOCATION · per LSUM

‹ All bid codes

$496,270.13Avg low bid / LSUM
$426,689.41Avg of all bids
$507,488.20Avg engineer's estimate
3Jobs · 5 LSUM

Average low bid by year

YearJobsQuantityAvg lowAvg all
202612$417,500.00$407,456.34
202523$548,783.55$444,174.01

Recent low bids

ExcelCSV
Let dateContractCounty / DistrictQuantityUnit priceLow bidder
Jan 15, 2026250273 KingfisherDivision 41 LSUM $195,000.00Silver Star Construction Company, Inc.
Jan 15, 2026250273 KingfisherDivision 41 LSUM $640,000.00Silver Star Construction Company, Inc.
Nov 20, 2025250273 KingfisherDivision 41 LSUM $195,000.00Silver Star Construction Company, Inc.
Nov 20, 2025250273 KingfisherDivision 41 LSUM $640,000.00Silver Star Construction Company, Inc.
Oct 9, 2025250153 CherokeeDivision 11 LSUM $811,350.66SHERWOOD CONSTRUCTION CO., INC.