$103.41Avg low bid / TON
$110.09Avg of all bids
$103.21Avg engineer's estimate
13Jobs · 124,067.2 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 1 | 7,500 | $110.25 | $117.63 |
| 2020 | 5 | 50,517 | $114.77 | $117.32 |
| 2019 | 4 | 33,466.2 | $101.98 | $110.70 |
| 2018 | 3 | 32,584 | $85.69 | $98.52 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Mar 18, 2021 | 210073 | CanadianDivision 4 | 7,500 TON | $110.25 | HASKELL LEMON CONSTRUCTION CO. |
| May 14, 2020 | 200219 | Kiowa, Washita | 12,833 TON | $101.00 | CORNELL CONSTRUCTION COMPANY, INC. |
| May 14, 2020 | 200208 | PittsburgDivision 2 | 6,077 TON | $95.34 | DUIT CONSTRUCTION COMPANY, INC. |
| Apr 16, 2020 | 200186 | ClevelandDivision 3 | 795 TON | $225.50 | HASKELL LEMON CONSTRUCTION CO. |
| Mar 19, 2020 | 200121 | Nhppi-4000(096)3p | 15,170 TON | $119.50 | HASKELL LEMON CONSTRUCTION CO. |
| Mar 19, 2020 | 200121 | Nhppi-4000(096)3p | 12,972 TON | $121.00 | HASKELL LEMON CONSTRUCTION CO. |
| Feb 20, 2020 | 190268 | PittsburgDivision 2 | 2,670 TON | $135.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Sep 19, 2019 | 190278 | CusterDivision 5 | 8,098 TON | $75.19 | CASWELL CONSTRUCTION, INC. |
| Jun 20, 2019 | 190190 | AtokaDivision 2 | 3,590 TON | $130.95 | APAC-CENTRAL, INC. |
| Jun 20, 2019 | 190231 | Ssr-225c(084)sr | 6,295.71 TON | $112.30 | OVERLAND CORPORATION |
| Jun 20, 2019 | 190231 | Ssr-225c(084)sr | 5,182.49 TON | $112.30 | OVERLAND CORPORATION |
| Mar 14, 2019 | 190070 | BryanDivision 2 | 10,300 TON | $101.45 | OVERLAND CORPORATION |
| May 17, 2018 | 180198 | KiowaDivision 5 | 15,224 TON | $99.50 | CORNELL CONSTRUCTION COMPANY, INC. |
| Apr 19, 2018 | 180157 | ClevelandDivision 3 | 10,360 TON | $67.90 | MARKWELL PAVING COMPANY, INC. |
| Jan 18, 2018 | 180029 | Ssr-264n(059)sr | 3,500 TON | $82.00 | GLOVER & ASSOCIATES, INC. |
| Jan 18, 2018 | 180029 | Ssr-264n(059)sr | 3,500 TON | $82.00 | GLOVER & ASSOCIATES, INC. |