AURORA MUNICIPAL

Let date
Friday, November 6, 2020
Contract
AU069
District
District 1
County
Kane
Highway

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 A Lamp Concrete Contractors, Inc. Low bidder $499,302
2 D. Construction, Inc. $557,334 +11.6%
3 R. W. Dunteman Company $559,156 +12.0%
4 Martam Construction Incorporated $586,906 +17.5%
5 K-Five Construction Corporation $640,093 +28.2%
6 Builders Paving, LLC $888,000 +77.8%

Bid tab: unit prices 38 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 A Lamp Concrete…#2 D. Construction…#3 R. W. Dunteman …#4 Martam Construc…#5 K-Five Construc…#6 Builders Paving…
1AR150510 ENGINEER'S FIELD OFFICE1L.S. $1,500.00 $15,750.00 $30,126.80 $49,543.54 $3,300.00 $21,508.00
2AR152410 UNCLASSIFIED EXCAVATION900C.Y. $49.00 $32.00 $52.67 $65.00 $42.00 $100.00
3AR152540 SOIL STABILIZATION FABRIC1,715S.Y. $2.00 $3.75 $9.02 $6.98 $4.00 $7.00
4AR156520 INLET PROTECTION4EACH $150.00 $275.00 $200.00 $233.20 $282.56 $300.00
5AR208515 POROUS GRANULAR EMBANKMENT565C.Y. $50.00 $63.00 $58.53 $101.92 $51.00 $115.00
6AR209608 CRUSHED AGG. BASE COURSE - 8"325S.Y. $28.00 $17.00 $20.71 $23.25 $8.00 $47.00
7AR209613 CRUSHED AGG. BASE COURSE - 13"1,520S.Y. $32.00 $25.00 $21.59 $24.00 $18.00 $45.50
8AR401613 BIT. SURF. CSE.-METHOD I, SUPERPAVE708TON $104.00 $113.00 $132.06 $96.46 $205.00 $165.00
9AR401650 BITUMINOUS PAVEMENT MILLING4,654S.Y. $3.75 $6.75 $4.20 $4.51 $11.25 $8.00
10AR401900 REMOVE BITUMINOUS PAVEMENT1,500S.Y. $20.00 $12.50 $30.92 $14.61 $25.00 $44.50
11AR401916 REM & REP BIT PAVEMENT - TYPE B100S.Y. $75.00 $106.00 $152.30 $173.61 $65.00 $315.00
12AR403613 BIT. BASE CSE.-METHOD I, SUPERPAVE175TON $100.00 $112.00 $119.00 $95.40 $200.00 $150.00
13AR501509 9" PCC PAVEMENT110S.Y. $180.00 $100.00 $217.50 $129.00 $230.00 $210.00
14AR501511 11" PCC PAVEMENT380S.Y. $225.00 $115.00 $157.21 $139.00 $240.00 $250.00
15AR501530 PCC TEST BATCH1EACH $12,500.00 $8,125.00 $2,500.00 $3,393.59 $4,500.00 $3,500.00
16AR501900 REMOVE PCC PAVEMENT575S.Y. $20.00 $18.75 $62.44 $30.46 $75.00 $165.00
17AR602510 BITUMINOUS PRIME COAT760GAL. $5.00 $0.0100 $3.35 $0.0100 $0.0100 $5.00
18AR603510 BITUMINOUS TACK COAT926GAL. $5.00 $0.0100 $2.80 $0.0100 $0.0100 $5.00
19AR620520 PAVEMENT MARKING-WATERBORNE4,000S.F. $2.65 $2.48 $2.40 $2.54 $2.40 $2.60
20AR620525 PAVEMENT MARKING-BLACK BORDER2,700S.F. $2.65 $2.48 $2.40 $2.54 $2.40 $2.60
21AR620900 PAVEMENT MARKING REMOVAL200S.F. $11.00 $3.30 $10.00 $10.60 $10.00 $10.75
22AR705506 6" PERFORATED UNDERDRAIN380L.F. $57.25 $33.00 $52.00 $27.72 $52.00 $60.00
23AR751980 RECONSTRUCT INLET8EACH $1,085.00 $12,000.00 $985.00 $5,053.52 $985.00 $1,100.00
24AR751995 RECONSTRUCT UTILITY STRUCTURE5EACH $1,575.00 $10,000.00 $1,425.00 $5,000.10 $1,425.00 $1,550.00
25AR800009 PCC SPALL REPAIR100S.F. $10.00 $67.00 $84.65 $267.72 $300.00 $310.00
26AR800159 SEEDING1,025S.Y. $5.50 $1.57 $1.43 $1.52 $1.43 $12.00
27AR800162 MULCHING1,025S.Y. $5.50 $1.93 $1.75 $1.86 $1.75 $2.00
28AR905530 TOPSOILING1,025S.Y. $9.10 $5.89 $5.35 $5.67 $5.35 $6.00
29AS501509 9" PCC PAVEMENT410S.Y. $180.00 $80.00 $135.89 $129.00 $170.00 $220.00
30AS501900 REMOVE PCC PAVEMENT410S.Y. $20.00 $18.75 $47.36 $36.43 $60.00 $135.00
31AS510510 TIE DOWN1EACH $3,000.00 $1,600.00 $2,000.00 $1,551.87 $750.00 $550.00
32AS620520 PAVEMENT MARKING-WATERBORNE124S.F. $20.50 $2.48 $18.50 $19.61 $18.50 $20.00
33AS620525 PAVEMENT MARKING-BLACK BORDER145S.F. $20.50 $2.48 $18.50 $19.61 $18.50 $20.00
34AT501509 9" PCC PAVEMENT315S.Y. $180.00 $82.00 $135.73 $129.00 $170.00 $210.00
35AT501900 REMOVE PCC PAVEMENT315S.Y. $20.00 $18.75 $47.48 $34.89 $60.00 $115.00
36AT510510 TIE DOWN4EACH $3,000.00 $1,600.00 $2,000.00 $1,551.87 $650.00 $550.00
37AT620520 PAVEMENT MARKING-WATERBORNE100S.F. $20.50 $2.48 $18.50 $19.61 $18.50 $20.00
38AT620525 PAVEMENT MARKING-BLACK BORDER100S.F. $20.35 $2.48 $18.50 $19.61 $18.50 $20.00