23-00143-00-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $387,947 | ||
| 2 | Samron Midwest Contracting, Inc. | $457,623 | +18.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $28,780.61 | $23,400.00 | |
| 2 | 40200800 | AGG SURF COURSE TY B | 150 | TON | $34.50 | $32.00 | |
| 3 | 40600290 | BIT MATLS TACK CT | 9,964 | POUND | $0.0100 | $0.0100 | |
| 4 | 40600982 | HMA SURF REM BUTT JT | 86 | SQ YD | $49.17 | $15.00 | |
| 5 | 40600990 | TEMPORARY RAMP | 64 | SQ YD | $35.22 | $25.00 | |
| 6 | 40604052 | HMA SC IL-9.5 C N70 | 2,805 | TON | $85.39 | $108.00 | |
| 7 | 44000157 | HMA SURF REM 2 | 22,142 | SQ YD | $1.99 | $2.25 | |
| 8 | 48101200 | AGGREGATE SHLDS B | 614 | TON | $50.95 | $55.00 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $18,057.26 | $25,000.00 | |
| 10 | 70300100 | SHORT TERM PAVT MKING | 2,076 | FOOT | $0.0100 | $2.00 | |
| 11 | 70300150 | SHRT TRM PAVT MK REM | 2,076 | SQ FT | $0.0100 | $0.0100 | |
| 12 | 78000200 | THPL PVT MK LINE 4 | 20,636 | FOOT | $0.7000 | $0.5200 |