19-00158-00-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $411,217 | ||
| 2 | Southern Illinois Asphalt Co., Inc. | $484,886 | +17.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Southern Illino… |
|---|---|---|---|---|---|---|---|
| 1 | X4401198 | HMA SURF REM VAR DP | 15,164 | SQ YD | $3.12 | $2.53 | |
| 2 | X5539000 | SS CLEANED 60 | 50 | FOOT | $89.39 | $164.50 | |
| 3 | X6020084 | MANHOLE SPECIAL | 2 | EACH | $5,241.86 | $10,909.48 | |
| 4 | X6024240 | INLETS SPL | 6 | EACH | $4,870.02 | $6,181.09 | |
| 5 | X6026800 | INLETS RECONST SPL | 1 | EACH | $3,928.60 | $6,181.09 | |
| 6 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $18,034.31 | $11,312.16 | |
| 7 | 20800150 | TRENCH BACKFILL | 30 | CU YD | $46.41 | $267.90 | |
| 8 | 28100105 | STONE RIPRAP CL A3 | 3 | SQ YD | $321.27 | $117.50 | |
| 9 | 28200200 | FILTER FABRIC | 3 | SQ YD | $52.78 | $29.38 | |
| 10 | 40600275 | BIT MATLS PR CT | 360 | POUND | $0.00 | $0.00 | |
| 11 | 40600290 | BIT MATLS TACK CT | 10,235 | POUND | $0.00 | $0.00 | |
| 12 | 40600990 | TEMPORARY RAMP | 183 | SQ YD | $19.35 | $15.18 | |
| 13 | 40602978 | HMA BC IL-9.5 N50 | 1,274 | TON | $71.53 | $84.18 | |
| 14 | 40604050 | HMA SC IL-9.5 C N50 | 1,274 | TON | $71.53 | $84.18 | |
| 15 | 42300200 | PCC DRIVEWAY PAVT 6 | 22 | SQ YD | $216.92 | $168.91 | |
| 16 | 44000200 | DRIVE PAVEMENT REM | 21 | SQ YD | $82.54 | $30.84 | |
| 17 | 44000500 | COMB CURB GUTTER REM | 283 | FOOT | $6.12 | $26.68 | |
| 18 | 44201717 | CL D PATCH T2 6 | 10 | SQ YD | $125.00 | $308.43 | |
| 19 | 44201723 | CL D PATCH T4 6 | 155 | SQ YD | $98.65 | $79.60 | |
| 20 | 550A0050 | STORM SEW CL A 1 12 | 163 | FOOT | $83.11 | $105.60 | |
| 21 | 550A0090 | STORM SEW CL A 1 18 | 66 | FOOT | $117.83 | $345.97 | |
| 22 | 55100700 | STORM SEWER REM 15 | 38 | FOOT | $45.61 | $22.28 | |
| 23 | 60108104 | PIPE UNDERDR T 1 4 | 215 | FOOT | $9.15 | $9.69 | |
| 24 | 60300305 | FR & LIDS ADJUST | 1 | EACH | $1,488.16 | $352.50 | |
| 25 | 60500060 | REMOV INLETS | 2 | EACH | $642.33 | $587.50 | |
| 26 | 60609800 | COMB CC&G TM6.18 | 283 | FOOT | $48.39 | $77.95 | |
| 27 | 67100100 | MOBILIZATION | 1 | L SUM | $34,224.61 | $33,545.62 | |
| 28 | 70300100 | SHORT TERM PAVT MKING | 496 | FOOT | $6.01 | $4.06 | |
| 29 | 78000200 | THPL PVT MK LINE 4 | 1,240 | FOOT | $4.20 | $4.70 | |
| 30 | 78000650 | THPL PVT MK LINE 24 | 42 | FOOT | $18.38 | $20.56 |