14-00130-00-FP
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $1,772,157 | ||
| 2 | Samron Midwest Contracting, Inc. | $1,856,682 | +4.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | X2500900 | SEEDING CL 1 SPL | 0.7 | ACRE | $6,926.76 | $7,100.00 | |
| 2 | X4404400 | PAVT REMOVAL SPL | 13,123 | SQ YD | $9.75 | $10.00 | |
| 3 | X5012502 | CONC REM SPEC | 6.6 | CU YD | $133.44 | $250.00 | |
| 4 | X5030225 | CONC STRUCT SPL | 6.6 | CU YD | $1,579.84 | $1,200.00 | |
| 5 | X6024242 | INLETS SPL N1 | 19 | EACH | $2,857.43 | $2,250.00 | |
| 6 | X6024244 | INLETS SPL N2 | 3 | EACH | $2,748.37 | $2,150.00 | |
| 7 | X6024246 | INLETS SPL N3 | 1 | EACH | $3,100.18 | $2,700.00 | |
| 8 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $24,735.85 | $11,250.00 | |
| 9 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $45,404.19 | $12,000.00 | |
| 10 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | |
| 11 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | |
| 12 | 20800150 | TRENCH BACKFILL | 1,090 | CU YD | $43.35 | $15.00 | |
| 13 | 21101615 | TOPSOIL F & P 4 | 3,388 | SQ YD | $13.39 | $14.00 | |
| 14 | 28000400 | PERIMETER EROS BAR | 626 | FOOT | $5.55 | $5.00 | |
| 15 | 28000500 | INLET & PIPE PROTECT | 29 | EACH | $129.57 | $50.00 | |
| 16 | 42300200 | PCC DRIVEWAY PAVT 6 | 777 | SQ YD | $125.15 | $90.00 | |
| 17 | 42400100 | PC CONC SIDEWALK 4 | 21,446 | SQ FT | $7.87 | $7.00 | |
| 18 | 42400800 | DETECTABLE WARNINGS | 325 | SQ FT | $30.90 | $25.00 | |
| 19 | 44000200 | DRIVE PAVEMENT REM | 849 | SQ YD | $32.03 | $20.00 | |
| 20 | 44000600 | SIDEWALK REM | 21,217 | SQ FT | $2.38 | $2.00 | |
| 21 | 54213657 | PRC FLAR END SEC 12 | 4 | EACH | $628.46 | $750.00 | |
| 22 | 550B0050 | STORM SEW CL B 1 12 | 901 | FOOT | $40.53 | $48.00 | |
| 23 | 550B0070 | STORM SEW CL B 1 15 | 987 | FOOT | $46.90 | $51.00 | |
| 24 | 550B0090 | STORM SEW CL B 1 18 | 348 | FOOT | $50.78 | $54.00 | |
| 25 | 550B0120 | STORM SEW CL B 1 24 | 264 | FOOT | $63.24 | $65.00 | |
| 26 | 550B0140 | STORM SEW CL B 1 30 | 88 | FOOT | $102.86 | $79.00 | |
| 27 | 550B0160 | STORM SEW CL B 1 36 | 79 | FOOT | $119.12 | $82.00 | |
| 28 | 55100200 | STORM SEWER REM 6 | 7 | FOOT | $4.99 | $10.00 | |
| 29 | 55100500 | STORM SEWER REM 12 | 1,134 | FOOT | $7.40 | $10.00 | |
| 30 | 55100700 | STORM SEWER REM 15 | 1,091 | FOOT | $7.68 | $10.00 | |
| 31 | 55100900 | STORM SEWER REM 18 | 46 | FOOT | $7.59 | $10.00 | |
| 32 | 55101200 | STORM SEWER REM 24 | 267 | FOOT | $7.85 | $10.00 | |
| 33 | 55101400 | STORM SEWER REM 30 | 86 | FOOT | $16.24 | $10.00 | |
| 34 | 55101600 | STORM SEWER REM 36 | 81 | FOOT | $17.24 | $10.00 | |
| 35 | 56500300 | DOM MET VLTS ADJ | 38 | EACH | $376.58 | $20.00 | |
| 36 | 60218400 | MAN TA 4 DIA T1F CL | 3 | EACH | $2,309.79 | $2,000.00 | |
| 37 | 60237000 | INLETS TA T15F&L | 2 | EACH | $1,571.21 | $1,500.00 | |
| 38 | 60266600 | VALVE BOX ADJ | 18 | EACH | $147.62 | $20.00 | |
| 39 | 60300305 | FR & LIDS ADJUST | 13 | EACH | $236.12 | $275.00 | |
| 40 | 60500040 | REMOV MANHOLES | 4 | EACH | $847.54 | $275.00 | |
| 41 | 60500060 | REMOV INLETS | 21 | EACH | $565.03 | $275.00 | |
| 42 | 60603800 | COMB CC&G TB6.12 | 6,425 | FOOT | $27.47 | $25.00 | |
| 43 | 60604400 | COMB CC&G TB6.18 | 97 | FOOT | $50.20 | $30.00 | |
| 44 | 67100100 | MOBILIZATION | 1 | L SUM | $13,204.91 | $134,000.00 | |
| 45 | 78009000 | MOD URETH PM LTR-SYM | 1,200 | SQ FT | $6.18 | $6.30 | |
| 46 | 78009004 | MOD URETH PM LINE 4 | 6,700 | FOOT | $1.70 | $1.70 | |
| 47 | 78009006 | MOD URETH PM LINE 6 | 1,231 | FOOT | $2.78 | $2.90 | |
| 48 | 78009024 | MOD URETH PM LINE 24 | 90 | FOOT | $10.30 | $11.00 | |
| 49 | 35100300 | AGG BASE CSE A 4 | 11,987 | SQ YD | $6.89 | $4.00 | |
| 50 | 42000300 | PCC PVT 8 | 11,987 | SQ YD | $43.13 | $58.50 | |
| 51 | 42001300 | PROTECTIVE COAT | 11,987 | SQ YD | $0.00 | $0.0100 |