Bid tab 97880

Let Jan 16, 2026 · District 8 · Monroe

‹ Jan 2026 results

23-00057-01-BT

Let date
Friday, January 16, 2026
Contract
97880 · job page
District
District 8
County
Monroe
Highway
Limits
Construction of an HMA multi-use path and pedestrian bridge from GMandO Heritage Trail to Rueck road in Columbia. Includes; concrete curb, driveway, sidewalks, box culvert extension, and storm sewer.
Classification
·
Project number

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 DMS Contracting, Inc. Low bidder $928,457
2 Baxmeyer Construction, Inc. $1,010,738 +8.9%
3 Keller Construction, Inc. $1,160,914 +25.0%

Bid tab: unit prices 65 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 DMS Contracting…#2 Baxmeyer Constr…#3 Keller Construc…
1X0322508 PED TRUSS SUPERSTR1,223SQ FT $202.10 $180.50 $288.00
2X0327423 CONNECT EXIST CULVERT1EACH $1,470.00 $3,925.00 $1,750.00
3X0350805 FOLD DOWN BOLLARDS1EACH $2,300.00 $2,375.00 $2,285.00
4X1400326 R R FL BEACON A COMP2EACH $7,700.00 $7,900.00 $7,613.00
5X2810844 REMOVE EXIST RIPRAP278SQ YD $22.50 $20.00 $15.20
6X3110102 COARSE AGR BACKFIL SPL34CU YD $125.00 $128.00 $161.85
7X5010520 REM C BOX CUL END SEC1EACH $6,000.00 $2,675.00 $2,700.00
8X5090810 PEDESTRIAN RAIL SPL142FOOT $76.55 $78.50 $75.60
9X5510012 PRO SS CONN TO EX SS1EACH $779.50 $1,850.00 $1,900.00
10X6640634 WOOD RAIL SPL48FOOT $114.00 $117.00 $112.90
11X7010216 TRAF CONT & PROT SPL1L SUM $44,000.00 $9,800.00 $6,300.00
12Z0013798 CONSTRUCTION LAYOUT1L SUM $16,400.00 $23,000.00 $9,950.00
13Z0076600 TRAINEES500HOUR $0.8000 $0.8000 $0.8000
14Z0076604 TRAINEES TPG500HOUR $15.00 $15.00 $15.00
1520100500 TREE REMOV ACRES0.25ACRE $35,000.00 $64,825.00 $55,500.00
1620101100 TREE TRUNK PROTECTION3EACH $250.00 $475.00 $760.00
1720200100 EARTH EXCAVATION1,870CU YD $14.25 $38.25 $25.75
1820700220 POROUS GRAN EMBANK10CU YD $330.00 $111.50 $240.00
1920800150 TRENCH BACKFILL49CU YD $59.50 $32.00 $45.00
2025000200 SEEDING CL 21.5ACRE $3,800.00 $4,725.00 $3,150.00
2125000400 NITROGEN FERT NUTR135POUND $4.50 $10.25 $9.00
2225000500 PHOSPHORUS FERT NUTR135POUND $4.50 $10.25 $9.00
2325000600 POTASSIUM FERT NUTR135POUND $4.50 $10.25 $9.00
2425100115 MULCH METHOD 21.5ACRE $5,000.00 $8,225.00 $4,500.00
2525100630 EROSION CONTR BLANKET1,304SQ YD $3.65 $3.75 $2.80
2628000250 TEMP EROS CONTR SEED150POUND $12.40 $11.00 $7.75
2728000305 TEMP DITCH CHECKS64FOOT $29.50 $30.00 $21.00
2828000400 PERIMETER EROS BAR3,500FOOT $2.50 $4.65 $5.00
2928000500 INLET & PIPE PROTECT5EACH $400.00 $295.00 $175.00
3028100107 STONE RIPRAP CL A4625SQ YD $47.70 $85.75 $64.00
3128200200 FILTER FABRIC625SQ YD $4.60 $6.65 $8.10
3235100300 AGG BASE CSE A 4422SQ YD $10.75 $24.65 $27.85
3335100500 AGG BASE CSE A 62,412SQ YD $15.00 $14.20 $11.20
3435200420 PROC SOIL-CEM BC 122,412SQ YD $3.65 $6.25 $3.90
3535200500 CEMENT421100 WT $16.50 $36.00 $15.80
3640201000 AGGREGATE-TEMP ACCESS100TON $45.25 $0.0100 $63.85
3740600275 BIT MATLS PR CT5,428POUND $2.60 $2.30 $2.55
3840604050 HMA SC IL-9.5 C N50270TON $170.00 $191.60 $167.70
3942000100 PCC PVT 6163SQ YD $98.25 $181.00 $175.56
4042400100 PC CONC SIDEWALK 42,329SQ FT $8.25 $14.00 $19.80
4142400800 DETECTABLE WARNINGS68SQ FT $90.00 $41.75 $45.20
4244000100 PAVEMENT REM105SQ YD $34.00 $33.00 $29.30
4344000500 COMB CURB GUTTER REM5FOOT $230.00 $120.00 $307.70
4444000600 SIDEWALK REM150SQ FT $19.00 $5.00 $13.00
4550200100 STRUCTURE EXCAVATION10CU YD $146.50 $150.00 $175.00
4650300225 CONC STRUCT21.2CU YD $2,695.00 $2,760.00 $3,120.00
4750800105 REINFORCEMENT BARS2,200POUND $6.50 $8.50 $3.00
4851201600 FUR STL PILE HP12X53124FOOT $316.00 $323.50 $208.15
4951202305 DRIVING PILES124FOOT $0.0100 $0.0100 $0.0100
5051204650 PILE SHOES4EACH $239.25 $245.00 $183.00
5154001001 BOX CUL END SEC C11EACH $35,800.00 $56,450.00 $29,500.00
5254010807 PCBC 8X724FOOT $1,220.00 $0.0100 $1,225.00
5354213657 PRC FLAR END SEC 121EACH $2,710.00 $1,475.00 $2,341.00
5454213663 PRC FLAR END SEC 181EACH $2,865.00 $1,865.00 $2,747.00
55550A0340 STORM SEW CL A 2 12196FOOT $58.50 $61.00 $77.00
56550A0380 STORM SEW CL A 2 1823FOOT $107.00 $77.50 $98.70
5755100900 STORM SEWER REM 1818FOOT $50.00 $37.40 $41.50
5860219540 MAN TA 4 DIA T24F&G1EACH $4,250.00 $3,960.00 $6,550.00
5960236200 INLETS TA T8G1EACH $2,920.00 $2,070.00 $3,925.00
6060240301 INLETS TB T8G1EACH $3,330.00 $2,420.00 $4,325.00
6160605200 COMB CC&G TB6.24 DOW56FOOT $127.00 $322.00 $114.50
6263200310 GUARDRAIL REMOV90FOOT $56.15 $21.00 $43.50
6367100100 MOBILIZATION1L SUM $56,000.00 $62,913.19 $164,500.00
6478001130 PAINT PVT MK LINE 6210FOOT $8.75 $5.85 $8.66
6578001180 PAINT PVT MK LINE 24118FOOT $16.20 $10.35 $16.00