17-00042-02-RS
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stutz Excavating, Inc. Low bidder | $533,207 | ||
| 2 | Hank's Excavating & Landscaping, Inc. | $551,620 | +3.5% | |
| 3 | DMS Contracting, Inc. | $558,501 | +4.7% | |
| 4 | Baxmeyer Construction, Inc. | $570,818 | +7.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stutz Excavatin… | #2 Hank's Excavati… | #3 DMS Contracting… | #4 Baxmeyer Constr… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0350810 | BOLLARD REMOVAL | 2 | EACH | $275.00 | $140.00 | $646.00 | $293.00 | |
| 2 | X6060505 | CONC CURB SPL | 234 | FOOT | $58.00 | $98.00 | $66.00 | $103.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $13,500.00 | $12,600.00 | $10,400.00 | $9,200.00 | |
| 4 | Z0036200 | PAINT CURB | 82 | FOOT | $22.25 | $21.00 | $21.00 | $21.00 | |
| 5 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 6 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 320 | CU YD | $35.00 | $95.00 | $72.00 | $61.00 | |
| 8 | 20201200 | REM & DISP UNS MATL | 100 | CU YD | $65.00 | $28.00 | $50.00 | $35.50 | |
| 9 | 28000250 | TEMP EROS CONTR SEED | 76 | POUND | $5.00 | $9.00 | $17.00 | $0.0100 | |
| 10 | 28000500 | INLET & PIPE PROTECT | 10 | EACH | $35.00 | $275.00 | $260.00 | $0.0100 | |
| 11 | 35101600 | AGG BASE CSE B 4 | 409 | SQ YD | $13.50 | $11.50 | $13.00 | $18.00 | |
| 12 | 35102400 | AGG BASE CSE B 12 | 443 | SQ YD | $40.00 | $24.50 | $43.00 | $37.00 | |
| 13 | 40201000 | AGGREGATE-TEMP ACCESS | 200 | TON | $35.00 | $38.00 | $43.00 | $14.50 | |
| 14 | 42000301 | PCC PVT 8 JOINTED | 213 | SQ YD | $71.00 | $115.00 | $97.00 | $98.00 | |
| 15 | 42300400 | PCC DRIVEWAY PAVT 8 | 372 | SQ YD | $141.00 | $110.00 | $134.00 | $145.00 | |
| 16 | 42400100 | PC CONC SIDEWALK 4 | 3,534 | SQ FT | $16.50 | $9.00 | $16.00 | $10.50 | |
| 17 | 42400800 | DETECTABLE WARNINGS | 60 | SQ FT | $147.00 | $45.00 | $140.00 | $35.00 | |
| 18 | 44000100 | PAVEMENT REM | 52 | SQ YD | $18.50 | $55.00 | $103.00 | $59.00 | |
| 19 | 44000200 | DRIVE PAVEMENT REM | 445 | SQ YD | $26.00 | $20.00 | $14.00 | $21.60 | |
| 20 | 44000500 | COMB CURB GUTTER REM | 979 | FOOT | $18.50 | $13.00 | $9.00 | $14.00 | |
| 21 | 44200929 | CL B PATCH T1 8 | 8 | SQ YD | $245.00 | $430.00 | $328.00 | $308.00 | |
| 22 | 44200934 | CL B PATCH T2 8 | 60 | SQ YD | $232.00 | $320.00 | $228.00 | $193.00 | |
| 23 | 44200942 | CL B PATCH T3 8 | 116 | SQ YD | $220.00 | $250.00 | $233.00 | $193.00 | |
| 24 | 44200944 | CL B PATCH T4 8 | 280 | SQ YD | $214.00 | $190.00 | $232.00 | $193.00 | |
| 25 | 44201298 | DOWEL BARS 1 1/4 | 525 | EACH | $13.50 | $25.00 | $7.00 | $20.00 | |
| 26 | 44213200 | SAW CUTS | 2,367 | FOOT | $7.30 | $6.00 | $8.00 | $9.15 | |
| 27 | 44213204 | TIE BARS 3/4 | 572 | EACH | $8.50 | $22.00 | $4.00 | $18.00 | |
| 28 | 542C0213 | P CUL CL C 1 8 | 24 | FOOT | $98.50 | $70.00 | $66.00 | $47.00 | |
| 29 | 54262708 | METAL FL END SEC 8" | 4 | EACH | $870.00 | $390.00 | $515.00 | $320.00 | |
| 30 | 56109210 | WATER VALVES ADJUST | 4 | EACH | $200.00 | $235.00 | $400.00 | $603.00 | |
| 31 | 56500300 | DOM MET VLTS ADJ | 2 | EACH | $325.00 | $725.00 | $743.00 | $604.00 | |
| 32 | 60218500 | MAN TA 4 DIA T3F&G | 1 | EACH | $4,275.00 | $5,900.00 | $5,000.00 | $4,350.00 | |
| 33 | 60255500 | MAN ADJUST | 1 | EACH | $500.00 | $1,300.00 | $1,370.00 | $550.00 | |
| 34 | 60260400 | INLETS ADJ NEW T1F CL | 1 | EACH | $950.00 | $1,800.00 | $1,835.00 | $984.00 | |
| 35 | 60500060 | REMOV INLETS | 1 | EACH | $875.00 | $825.00 | $448.00 | $390.00 | |
| 36 | 60604400 | COMB CC&G TB6.18 | 880 | FOOT | $67.25 | $45.00 | $89.00 | $57.00 | |
| 37 | 67100100 | MOBILIZATION | 1 | L SUM | $21,800.00 | $22,000.00 | $21,000.00 | $46,002.59 | |
| 38 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $11,300.00 | $3,300.00 | $1.00 | $0.0100 | |
| 39 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $9,700.00 | $60,000.00 | $15,000.00 | $62,000.00 | |
| 40 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 54.4 | SQ FT | $22.25 | $21.00 | $21.00 | $21.25 | |
| 41 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 1,753 | FOOT | $2.25 | $2.10 | $2.10 | $2.15 | |
| 42 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 99 | FOOT | $22.25 | $21.00 | $21.20 | $21.25 | |
| 43 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 63 | FOOT | $28.00 | $26.25 | $26.50 | $26.50 | |
| 44 | 72000100 | SIGN PANEL T1 | 21.6 | SQ FT | $40.50 | $37.80 | $94.00 | $38.00 | |
| 45 | 72800100 | TELES STL SIN SUPPORT | 50 | FOOT | $39.75 | $37.25 | $31.00 | $38.00 | |
| 46 | 78009000 | MOD URETH PM LTR-SYM | 54.4 | SQ FT | $44.50 | $42.00 | $43.00 | $42.40 | |
| 47 | 78009004 | MOD URETH PM LINE 4 | 1,753 | FOOT | $4.50 | $4.20 | $4.25 | $4.25 | |
| 48 | 78009012 | MOD URETH PM LINE 12 | 99 | FOOT | $44.50 | $42.00 | $42.40 | $42.40 | |
| 49 | 78009024 | MOD URETH PM LINE 24 | 63 | FOOT | $111.25 | $105.00 | $106.00 | $106.00 | |
| 50 | 78200020 | CURB REFLECTORS | 15 | EACH | $20.00 | $262.50 | $265.00 | $25.75 | |
| 51 | 78300202 | PVT MKG REM WTR BLAST | 1,226 | SQ FT | $1.15 | $1.05 | $1.05 | $1.10 |