17-00111-00-BT
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Baxmeyer Construction, Inc. Low bidder | $253,072 | ||
| 2 | Keller Construction, Inc. | $274,000 | +8.3% | |
| 3 | RCS Construction, Inc. | $316,829 | +25.2% | |
| 4 | Kinney Contractors, Inc. | $321,851 | +27.2% | |
| 5 | Stutz Excavating, Inc. | $434,522 | +71.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Baxmeyer Constr… | #2 Keller Construc… | #3 RCS Constructio… | #4 Kinney Contract… | #5 Stutz Excavatin… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0322936 | REMOV EX FLAR END SEC | 2 | EACH | $142.00 | $115.00 | $500.00 | $325.00 | $150.00 | |
| 2 | X1200050 | BOX CULVERT REMOVAL | 30 | FOOT | $279.16 | $265.00 | $80.00 | $350.00 | $330.00 | |
| 3 | X2500920 | SEEDING CL 1A SPL | 0.5 | ACRE | $8,399.70 | $8,080.00 | $10,000.00 | $8,300.00 | $8,325.00 | |
| 4 | X5091725 | BICYCLE RAILING SPL | 86 | FOOT | $227.88 | $255.00 | $260.00 | $225.00 | $415.00 | |
| 5 | X7240600 | REM RE-ERECT EX SIGN | 3 | EACH | $270.27 | $260.00 | $300.00 | $295.00 | $267.00 | |
| 6 | Z0004002 | BOLLARDS | 2 | EACH | $1,351.37 | $1,300.00 | $1,500.00 | $1,400.00 | $1,525.00 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $4,676.33 | $3,600.00 | $12,000.00 | $4,500.00 | $6,000.00 | |
| 8 | Z0016702 | DETOUR SIGNING | 1 | L SUM | $4,432.47 | $1,250.00 | $3,500.00 | $3,250.00 | $3,050.00 | |
| 9 | Z0046304 | P UNDR FOR STRUCT 4 | 90 | FOOT | $17.76 | $21.00 | $4.50 | $23.40 | $18.50 | |
| 10 | 20100500 | TREE REMOV ACRES | 0.25 | ACRE | $3,143.60 | $14,600.00 | $6,250.00 | $20,500.00 | $20,800.00 | |
| 11 | 20200100 | EARTH EXCAVATION | 445 | CU YD | $28.46 | $26.25 | $15.00 | $29.00 | $28.50 | |
| 12 | 20201200 | REM & DISP UNS MATL | 100 | CU YD | $34.09 | $19.15 | $0.0100 | $26.50 | $23.50 | |
| 13 | 20400800 | FURNISHED EXCAVATION | 410 | CU YD | $19.29 | $27.50 | $58.00 | $32.00 | $56.00 | |
| 14 | 20800150 | TRENCH BACKFILL | 10 | CU YD | $67.67 | $67.65 | $38.00 | $59.00 | $45.00 | |
| 15 | 21001000 | GEOTECH FAB F/GR STAB | 1,267 | SQ YD | $1.82 | $1.15 | $1.00 | $1.75 | $1.10 | |
| 16 | 21101805 | COMPOST F & P 2 | 2,560 | SQ YD | $4.72 | $4.54 | $3.75 | $5.00 | $4.65 | |
| 17 | 25100630 | EROSION CONTR BLANKET | 1,660 | SQ YD | $1.48 | $1.42 | $1.75 | $1.50 | $1.50 | |
| 18 | 28000250 | TEMP EROS CONTR SEED | 100 | POUND | $2.71 | $2.55 | $0.0100 | $5.00 | $2.00 | |
| 19 | 28000305 | TEMP DITCH CHECKS | 102 | FOOT | $9.36 | $15.95 | $3.00 | $11.50 | $6.50 | |
| 20 | 28000400 | PERIMETER EROS BAR | 100 | FOOT | $5.88 | $13.00 | $15.00 | $17.50 | $13.40 | |
| 21 | 28000500 | INLET & PIPE PROTECT | 3 | EACH | $114.84 | $77.85 | $115.00 | $305.00 | $150.00 | |
| 22 | 28100107 | STONE RIPRAP CL A4 | 52 | SQ YD | $35.97 | $62.56 | $45.00 | $71.00 | $60.00 | |
| 23 | 28200200 | FILTER FABRIC | 52 | SQ YD | $3.51 | $6.75 | $7.00 | $6.00 | $2.00 | |
| 24 | 35100300 | AGG BASE CSE A 4 | 84 | SQ YD | $14.61 | $17.32 | $9.75 | $11.00 | $10.00 | |
| 25 | 35100500 | AGG BASE CSE A 6 | 1,420 | SQ YD | $9.56 | $8.45 | $10.00 | $13.00 | $10.00 | |
| 26 | 40201000 | AGGREGATE-TEMP ACCESS | 30 | TON | $0.0100 | $30.00 | $0.0100 | $45.00 | $30.00 | |
| 27 | 42400100 | PC CONC SIDEWALK 4 | 589 | SQ FT | $6.93 | $7.00 | $9.00 | $9.00 | $6.10 | |
| 28 | 42400200 | PC CONC SIDEWALK 5 | 10,048 | SQ FT | $4.49 | $4.35 | $5.00 | $4.85 | $4.50 | |
| 29 | 42400800 | DETECTABLE WARNINGS | 60 | SQ FT | $26.92 | $55.00 | $42.00 | $49.00 | $59.00 | |
| 30 | 44000400 | GUTTER REM | 40 | FOOT | $24.53 | $23.75 | $10.50 | $24.00 | $50.00 | |
| 31 | 44000600 | SIDEWALK REM | 340 | SQ FT | $3.27 | $2.20 | $1.50 | $3.50 | $2.15 | |
| 32 | 50105220 | PIPE CULVERT REMOV | 25 | FOOT | $30.66 | $10.80 | $15.00 | $31.00 | $15.00 | |
| 33 | 54001001 | BOX CUL END SEC C1 | 1 | EACH | $37,678.70 | $37,488.78 | $35,000.00 | $54,250.00 | $39,800.00 | |
| 34 | 542A0220 | P CUL CL A 1 15 | 53 | FOOT | $42.81 | $66.40 | $110.00 | $81.00 | $924.00 | |
| 35 | 542A0229 | P CUL CL A 1 24 | 22 | FOOT | $77.59 | $87.00 | $140.00 | $94.00 | $1,070.00 | |
| 36 | 542A0235 | P CUL CL A 1 30 | 24 | FOOT | $87.76 | $102.50 | $150.00 | $110.00 | $1,635.00 | |
| 37 | 54213660 | PRC FLAR END SEC 15 | 1 | EACH | $566.16 | $795.00 | $600.00 | $950.00 | $51.50 | |
| 38 | 54213669 | PRC FLAR END SEC 24 | 1 | EACH | $714.54 | $1,190.00 | $750.00 | $1,115.00 | $69.00 | |
| 39 | 54213675 | PRC FLAR END SEC 30 | 2 | EACH | $942.02 | $1,450.00 | $1,000.00 | $1,550.00 | $106.00 | |
| 40 | 59100100 | GEOCOMPOSITE WALL DR | 45 | SQ YD | $16.15 | $21.25 | $10.00 | $30.00 | $16.00 | |
| 41 | 60240305 | INLETS TB T10F&G | 1 | EACH | $1,676.18 | $1,530.00 | $2,200.00 | $1,830.00 | $1,930.00 | |
| 42 | 60602800 | CONC GUTTER TB | 640 | FOOT | $25.75 | $19.50 | $28.50 | $32.50 | $30.40 | |
| 43 | 66900200 | NON SPL WASTE DISPOSL | 30 | CU YD | $0.0100 | $145.00 | $200.00 | $125.00 | $300.00 | |
| 44 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $2,692.14 | $985.00 | $1,110.00 | $1,100.00 | $1,260.00 | |
| 45 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,225.79 | $2,140.00 | $2,875.00 | $2,400.00 | $2,650.00 | |
| 46 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $2,225.79 | $2,140.00 | $2,875.00 | $2,400.00 | $1,950.00 | |
| 47 | 66901006 | REG SUB MON | 2 | CAL DA | $794.93 | $765.00 | $1,500.00 | $800.00 | $950.00 | |
| 48 | 67100100 | MOBILIZATION | 1 | L SUM | $6,007.27 | $22,600.00 | $22,500.00 | $14,500.95 | $28,800.00 | |
| 49 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $3,762.64 | $2,805.00 | $23,000.00 | $4,500.00 | $3,750.00 | |
| 50 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $211.98 | $571.20 | $250.00 | $250.00 | $500.00 | |
| 51 | 72000100 | SIGN PANEL T1 | 53.2 | SQ FT | $25.44 | $24.48 | $27.50 | $25.00 | $25.00 | |
| 52 | 72800100 | TELES STL SIN SUPPORT | 183 | FOOT | $16.16 | $24.48 | $17.50 | $17.00 | $16.00 | |
| 53 | 78001110 | PAINT PVT MK LINE 4 | 500 | FOOT | $1.06 | $1.02 | $1.15 | $4.00 | $3.75 | |
| 54 | 78001150 | PAINT PVT MK LINE 12 | 35 | FOOT | $5.30 | $5.10 | $5.75 | $14.00 | $12.75 | |
| 55 | 78001180 | PAINT PVT MK LINE 24 | 120 | FOOT | $6.89 | $6.63 | $7.50 | $18.00 | $17.35 | |
| 56 | 89500400 | RELOC EX PED PUSH-BUT | 2 | EACH | $520.41 | $500.82 | $575.00 | $400.00 | $370.00 |