21-00070-00-SW
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | McCarthy Improvement Company Low bidder | $1,645,985 | ||
| 2 | Kinney Contractors, Inc. | $1,787,605 | +8.6% | |
| 3 | Mayer Landscaping, Inc. | $1,880,274 | +14.2% | |
| 4 | Baxmeyer Construction, Inc. | $1,996,040 | +21.3% | |
| 5 | Samron Midwest Contracting, Inc. | $2,074,876 | +26.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 McCarthy Improv… | #2 Kinney Contract… | #3 Mayer Landscapi… | #4 Baxmeyer Constr… | #5 Samron Midwest … |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0327301 | RELOCATE EX MAILBOX | 1 | EACH | $400.00 | $750.00 | $441.20 | $636.99 | $350.00 | |
| 2 | X2500900 | SEEDING CL 1 SPL | 2 | ACRE | $7,725.00 | $7,000.00 | $28,579.55 | $32,489.61 | $15,000.00 | |
| 3 | X2600012 | REM & REL SN P&P ASSY | 7 | EACH | $400.00 | $700.00 | $440.65 | $591.67 | $300.00 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $74,300.00 | $30,750.00 | $130,266.60 | $26,192.99 | $25,000.00 | |
| 5 | X8760200 | ACCESSIBLE PED SIGNAL | 2 | EACH | $4,290.00 | $4,650.00 | $4,905.90 | $2,410.90 | $5,000.00 | |
| 6 | 20100210 | TREE REMOV OVER 15 | 94 | UNIT | $150.00 | $127.50 | $61.45 | $157.66 | $150.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 1,326 | CU YD | $78.00 | $49.00 | $163.50 | $185.49 | $50.00 | |
| 8 | 20400800 | FURNISHED EXCAVATION | 999 | CU YD | $73.00 | $48.00 | $59.50 | $249.91 | $100.00 | |
| 9 | 20800150 | TRENCH BACKFILL | 5 | CU YD | $106.00 | $175.00 | $142.60 | $91.91 | $100.00 | |
| 10 | 35400300 | PCC BASE CSE W 8 | 104 | SQ YD | $131.00 | $172.00 | $251.60 | $261.73 | $150.00 | |
| 11 | 42300200 | PCC DRIVEWAY PAVT 6 | 925 | SQ YD | $108.00 | $155.50 | $167.05 | $184.08 | $120.00 | |
| 12 | 42400100 | PC CONC SIDEWALK 4 | 74,971 | SQ FT | $10.75 | $12.75 | $9.10 | $9.32 | $15.00 | |
| 13 | 42400300 | PC CONC SIDEWALK 6 | 7,055 | SQ FT | $11.00 | $13.75 | $16.95 | $9.54 | $15.00 | |
| 14 | 42400410 | PC CONC SIDEWALK 8 | 345 | SQ FT | $13.75 | $17.00 | $24.90 | $12.37 | $15.00 | |
| 15 | 42400800 | DETECTABLE WARNINGS | 596 | SQ FT | $42.00 | $45.00 | $83.05 | $47.05 | $35.00 | |
| 16 | 44000100 | PAVEMENT REM | 80 | SQ YD | $20.50 | $60.00 | $74.60 | $206.56 | $45.00 | |
| 17 | 44000200 | DRIVE PAVEMENT REM | 1,167 | SQ YD | $19.25 | $26.00 | $17.40 | $57.30 | $20.00 | |
| 18 | 44000500 | COMB CURB GUTTER REM | 613 | FOOT | $11.00 | $22.00 | $16.75 | $39.19 | $25.00 | |
| 19 | 44000600 | SIDEWALK REM | 9,054 | SQ FT | $1.75 | $2.50 | $1.00 | $3.48 | $4.00 | |
| 20 | 50901760 | PIPE HANDRAIL | 180 | FOOT | $200.00 | $150.00 | $148.65 | $137.60 | $150.00 | |
| 21 | 542C0217 | P CUL CL C 1 12 | 40 | FOOT | $60.00 | $280.00 | $170.35 | $68.95 | $150.00 | |
| 22 | 542C0229 | P CUL CL C 1 24 | 16 | FOOT | $101.00 | $300.00 | $405.15 | $66.31 | $175.00 | |
| 23 | 550A2320 | SS RG CL A 1 12 | 30 | FOOT | $59.00 | $202.00 | $212.20 | $75.78 | $150.00 | |
| 24 | 56500300 | DOM MET VLTS ADJ | 6 | EACH | $1,150.00 | $500.00 | $469.80 | $643.26 | $500.00 | |
| 25 | 60236200 | INLETS TA T8G | 1 | EACH | $6,375.00 | $3,200.00 | $6,522.45 | $2,055.01 | $5,000.00 | |
| 26 | 60260100 | INLETS ADJUST | 3 | EACH | $2,200.00 | $1,250.00 | $2,199.90 | $891.37 | $500.00 | |
| 27 | 60265700 | VV ADJUST | 2 | EACH | $735.00 | $600.00 | $957.00 | $643.26 | $100.00 | |
| 28 | 60605100 | COMB CC&G TB6.24 AEP | 547 | FOOT | $83.00 | $105.00 | $112.35 | $176.61 | $100.00 | |
| 29 | 63200310 | GUARDRAIL REMOV | 91 | FOOT | $15.00 | $12.00 | $26.65 | $26.55 | $15.00 | |
| 30 | 63301210 | REM RE-E SPBGR TY A | 8 | FOOT | $400.00 | $400.00 | $731.45 | $296.38 | $325.00 | |
| 31 | 66900200 | NON SPL WASTE DISPOSL | 85 | CU YD | $166.00 | $49.00 | $187.00 | $0.0100 | $175.00 | |
| 32 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,400.00 | $1,700.00 | $1,601.00 | $1,905.29 | $2,500.00 | |
| 33 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,200.00 | $2,700.00 | $2,515.85 | $3,175.49 | $3,500.00 | |
| 34 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,200.00 | $2,700.00 | $2,515.85 | $1,058.50 | $1,500.00 | |
| 35 | 66901006 | REG SUB MON | 4 | CAL DA | $1,175.00 | $1,450.00 | $1,343.70 | $1,164.35 | $1,500.00 | |
| 36 | 67100100 | MOBILIZATION | 1 | L SUM | $99,100.00 | $95,500.00 | $99,362.50 | $57,031.40 | $185,000.00 | |
| 37 | 81028350 | UNDRGRD C PVC 2 | 67 | FOOT | $84.50 | $100.00 | $96.65 | $73.81 | $90.00 | |
| 38 | 87301215 | ELCBL C SIGNAL 14 2C | 228 | FOOT | $7.25 | $8.50 | $8.30 | $2.63 | $5.00 | |
| 39 | 87301235 | ELCBL C SIGNAL 14 4C | 241 | FOOT | $8.50 | $9.00 | $9.70 | $2.95 | $10.00 | |
| 40 | 87502460 | TS POST GALVS 12 | 2 | EACH | $3,950.00 | $4,250.00 | $4,517.10 | $4,228.73 | $4,500.00 | |
| 41 | 87600100 | PED PUSH-BUT POST T1 | 2 | EACH | $4,600.00 | $5,250.00 | $5,260.40 | $3,661.47 | $4,500.00 | |
| 42 | 87800100 | CONC FDN TY A | 6 | FOOT | $1,150.00 | $1,400.00 | $1,315.10 | $792.89 | $1,000.00 | |
| 43 | 87900200 | DRILL EX HANDHOLE | 2 | EACH | $1,675.00 | $1,900.00 | $1,915.45 | $1,501.98 | $1,000.00 | |
| 44 | 88102825 | PED SH P LED 1F BM CT | 2 | EACH | $1,695.00 | $1,850.00 | $1,938.35 | $2,191.72 | $2,500.00 | |
| 45 | 89502200 | MOD EX CONTR | 1 | EACH | $3,025.00 | $3,350.00 | $3,459.30 | $5,466.42 | $2,500.00 |