21-00056-01-SC
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | K. E. Vas Company Low bidder | $369,091 | ||
| 2 | Illinois Valley Paving, a div of UCM, Inc. | $391,568 | +6.1% | |
| 3 | Rees Construction Company of Quincy | $416,533 | +12.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K. E. Vas Compa… | #2 Illinois Valley… | #3 Rees Constructi… |
|---|---|---|---|---|---|---|---|---|
| 1 | LR403200 | BIT MATL PR CT | 6 | TON | $1,325.00 | $1,321.95 | $1,388.04 | |
| 2 | LR403400 | BIT MATLS C&S CT | 23 | TON | $1,015.00 | $1,011.66 | $1,062.24 | |
| 3 | LR403500 | COVER COAT AGG | 136 | TON | $45.00 | $40.79 | $42.82 | |
| 4 | LR403600 | SEAL COAT AGG | 68 | TON | $65.00 | $64.40 | $67.62 | |
| 5 | X2501000 | SEEDING CL 2 SPL | 2 | ACRE | $6,000.00 | $6,163.50 | $6,850.00 | |
| 6 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $10,000.00 | $5,670.00 | $8,500.00 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,000.00 | $2,928.62 | $5,200.00 | |
| 8 | 20200100 | EARTH EXCAVATION | 1,214 | CU YD | $20.00 | $22.20 | $32.00 | |
| 9 | 20400800 | FURNISHED EXCAVATION | 2,437 | CU YD | $28.00 | $30.73 | $34.00 | |
| 10 | 20800150 | TRENCH BACKFILL | 108 | CU YD | $40.00 | $99.02 | $74.00 | |
| 11 | 28000250 | TEMP EROS CONTR SEED | 178 | POUND | $5.00 | $4.73 | $5.18 | |
| 12 | 28000305 | TEMP DITCH CHECKS | 220 | FOOT | $10.00 | $9.71 | $10.64 | |
| 13 | 28000400 | PERIMETER EROS BAR | 130 | FOOT | $5.00 | $4.46 | $4.89 | |
| 14 | 28000500 | INLET & PIPE PROTECT | 4 | EACH | $100.00 | $94.50 | $105.00 | |
| 15 | 35100900 | AGG BASE CSE A 10 | 5,438 | SQ YD | $18.00 | $18.85 | $17.00 | |
| 16 | 40200700 | AGG SURF CSE A 8 | 20 | SQ YD | $20.00 | $49.95 | $52.00 | |
| 17 | 48100500 | AGGREGATE SHLDS A 6 | 1,914 | SQ YD | $12.00 | $10.06 | $15.00 | |
| 18 | 50105220 | PIPE CULVERT REMOV | 98 | FOOT | $10.00 | $37.14 | $22.00 | |
| 19 | 542A0229 | P CUL CL A 1 24 | 148 | FOOT | $154.00 | $246.50 | $120.00 | |
| 20 | 542A1069 | P CUL CL A 2 24 | 64 | FOOT | $154.00 | $174.09 | $132.00 | |
| 21 | 54213669 | PRC FLAR END SEC 24 | 8 | EACH | $1,800.00 | $2,870.64 | $2,600.00 | |
| 22 | 67100100 | MOBILIZATION | 1 | L SUM | $25,000.00 | $16,056.72 | $40,575.00 |