21-00080-00-SW
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Rees Construction Company of Quincy Low bidder | $857,080 | ||
| 2 | Laverdiere Construction, Inc. | $878,218 | +2.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Rees Constructi… | #2 Laverdiere Cons… |
|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 1 | ACRE | $9,500.00 | $14,300.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $15,690.00 | $18,000.00 | |
| 3 | Z0004002 | BOLLARDS | 8 | EACH | $929.25 | $1,000.00 | |
| 4 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $20,350.00 | $10,000.00 | |
| 5 | Z0056608 | STORM SEW WM REQ 12 | 140 | FOOT | $94.00 | $145.00 | |
| 6 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | |
| 7 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 8 | 20200100 | EARTH EXCAVATION | 1,455 | CU YD | $26.00 | $30.00 | |
| 9 | 20800150 | TRENCH BACKFILL | 51 | CU YD | $74.00 | $129.00 | |
| 10 | 28000250 | TEMP EROS CONTR SEED | 93 | POUND | $0.0100 | $10.00 | |
| 11 | 28000400 | PERIMETER EROS BAR | 8,149 | FOOT | $1.89 | $7.00 | |
| 12 | 28000500 | INLET & PIPE PROTECT | 7 | EACH | $78.75 | $260.00 | |
| 13 | 31100300 | SUB GRAN MAT A 4 | 446 | SQ YD | $24.00 | $25.00 | |
| 14 | 35102000 | AGG BASE CSE B 8 | 4,108 | SQ YD | $27.15 | $20.00 | |
| 15 | 40600275 | BIT MATLS PR CT | 9,242 | POUND | $1.03 | $1.43 | |
| 16 | 40600290 | BIT MATLS TACK CT | 925 | POUND | $2.79 | $0.9500 | |
| 17 | 40602978 | HMA BC IL-9.5 N50 | 358 | TON | $179.64 | $254.00 | |
| 18 | 40604050 | HMA SC IL-9.5 C N50 | 350 | TON | $179.64 | $257.00 | |
| 19 | 42300400 | PCC DRIVEWAY PAVT 8 | 128 | SQ YD | $160.00 | $180.00 | |
| 20 | 42400300 | PC CONC SIDEWALK 6 | 10,216 | SQ FT | $18.00 | $13.50 | |
| 21 | 42400800 | DETECTABLE WARNINGS | 369 | SQ FT | $52.00 | $50.00 | |
| 22 | 44000100 | PAVEMENT REM | 308 | SQ YD | $20.00 | $38.00 | |
| 23 | 44000200 | DRIVE PAVEMENT REM | 187 | SQ YD | $18.00 | $29.00 | |
| 24 | 44000500 | COMB CURB GUTTER REM | 402 | FOOT | $15.00 | $16.00 | |
| 25 | 44000600 | SIDEWALK REM | 2,496 | SQ FT | $3.00 | $2.00 | |
| 26 | 44201329 | CL C PATCH T2 8 | 20 | SQ YD | $165.00 | $282.00 | |
| 27 | 44201333 | CL C PATCH T3 8 | 57 | SQ YD | $165.00 | $200.00 | |
| 28 | 55100300 | STORM SEWER REM 8 | 99 | FOOT | $35.00 | $28.00 | |
| 29 | 55100400 | STORM SEWER REM 10 | 32 | FOOT | $35.00 | $43.00 | |
| 30 | 60234200 | INLETS TA T1F OL | 1 | EACH | $2,100.00 | $2,300.00 | |
| 31 | 60236700 | INLETS TA T10F&G | 1 | EACH | $2,200.00 | $2,400.00 | |
| 32 | 60236800 | INLETS TA T11F&G | 3 | EACH | $2,200.00 | $2,400.00 | |
| 33 | 60240305 | INLETS TB T10F&G | 1 | EACH | $3,000.00 | $3,000.00 | |
| 34 | 60257900 | MAN RECONST | 2 | EACH | $7,800.00 | $3,500.00 | |
| 35 | 60500060 | REMOV INLETS | 6 | EACH | $900.00 | $800.00 | |
| 36 | 60603800 | COMB CC&G TB6.12 | 2,004 | FOOT | $52.00 | $46.00 | |
| 37 | 67100100 | MOBILIZATION | 1 | L SUM | $32,614.00 | $24,500.00 | |
| 38 | 72000100 | SIGN PANEL T1 | 236 | SQ FT | $29.40 | $45.00 | |
| 39 | 72800100 | TELES STL SIN SUPPORT | 352 | FOOT | $23.88 | $26.00 | |
| 40 | 78001130 | PAINT PVT MK LINE 6 | 559 | FOOT | $8.92 | $5.00 | |
| 41 | 78001150 | PAINT PVT MK LINE 12 | 467 | FOOT | $14.30 | $11.00 | |
| 42 | 78001180 | PAINT PVT MK LINE 24 | 56 | FOOT | $24.04 | $21.00 |