22-00018-00-BR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | County Contractors, Inc. Low bidder | $1,285,105 | ||
| 2 | Sangamo Construction Company | $1,333,513 | +3.8% | |
| 3 | Freesen, a div of UCM, Inc. | $1,473,639 | +14.7% | |
| 4 | William Charles Construction Company, LLC | $1,577,000 | +22.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 County Contract… | #2 Sangamo Constru… | #3 Freesen, a div … | #4 William Charles… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.4 | ACRE | $17,500.00 | $9,470.65 | $9,397.50 | $8,950.00 | |
| 2 | X2810208 | STONE RIPRAP CL A4 SP | 331 | TON | $88.00 | $79.56 | $156.60 | $120.00 | |
| 3 | X6650202 | WOV W FENCE REMOV | 213 | FOOT | $20.00 | $8.86 | $9.88 | $12.00 | |
| 4 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $6,000.00 | $8,530.07 | $4,200.00 | $8,961.80 | |
| 5 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 6 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 7 | 20100110 | TREE REMOV 6-15 | 116 | UNIT | $210.00 | $53.29 | $47.25 | $100.00 | |
| 8 | 20100210 | TREE REMOV OVER 15 | 30 | UNIT | $500.00 | $87.93 | $68.25 | $150.00 | |
| 9 | 20100500 | TREE REMOV ACRES | 0.2 | ACRE | $110,000.00 | $61,993.15 | $52,500.00 | $35,000.00 | |
| 10 | 20101100 | TREE TRUNK PROTECTION | 9 | EACH | $210.00 | $380.58 | $157.50 | $200.00 | |
| 11 | 20200100 | EARTH EXCAVATION | 255 | CU YD | $40.00 | $56.49 | $47.33 | $100.00 | |
| 12 | 20300100 | CHANNEL EXCAVATION | 541 | CU YD | $20.00 | $44.60 | $28.08 | $50.00 | |
| 13 | 20400800 | FURNISHED EXCAVATION | 838 | CU YD | $35.00 | $83.75 | $76.94 | $40.00 | |
| 14 | 25100630 | EROSION CONTR BLANKET | 1,074 | SQ YD | $4.75 | $2.01 | $2.00 | $1.90 | |
| 15 | 25100635 | HD EROS CONTR BLANKET | 535 | SQ YD | $5.50 | $2.28 | $2.26 | $2.15 | |
| 16 | 28000250 | TEMP EROS CONTR SEED | 110 | POUND | $1.00 | $8.81 | $4.20 | $5.00 | |
| 17 | 28000305 | TEMP DITCH CHECKS | 119 | FOOT | $8.00 | $22.91 | $38.32 | $16.00 | |
| 18 | 28000400 | PERIMETER EROS BAR | 509 | FOOT | $2.50 | $7.12 | $11.19 | $4.00 | |
| 19 | 28100105 | STONE RIPRAP CL A3 | 121 | SQ YD | $35.00 | $77.62 | $101.99 | $100.00 | |
| 20 | 31100700 | SUB GRAN MAT A 8 | 971 | SQ YD | $24.00 | $21.73 | $25.89 | $25.00 | |
| 21 | 40600275 | BIT MATLS PR CT | 2,002 | POUND | $1.50 | $1.52 | $1.27 | $0.8500 | |
| 22 | 40600290 | BIT MATLS TACK CT | 201 | POUND | $10.00 | $9.92 | $7.03 | $0.8600 | |
| 23 | 40603080 | HMA BC IL-19.0 N50 | 179 | TON | $201.00 | $201.25 | $176.35 | $176.26 | |
| 24 | 40604050 | HMA SC IL-9.5 C N50 | 121 | TON | $204.00 | $204.46 | $221.50 | $215.59 | |
| 25 | 44000100 | PAVEMENT REM | 864 | SQ YD | $26.00 | $4.19 | $17.62 | $30.00 | |
| 26 | 48101500 | AGGREGATE SHLDS B 6 | 324 | SQ YD | $30.00 | $28.30 | $55.13 | $35.00 | |
| 27 | 50100100 | REM EXIST STRUCT | 1 | EACH | $55,000.00 | $44,833.23 | $103,838.29 | $40,000.00 | |
| 28 | 50200100 | STRUCTURE EXCAVATION | 148 | CU YD | $19.00 | $46.39 | $28.88 | $30.00 | |
| 29 | 50200300 | COFFERDAM EXCAVATION | 96 | CU YD | $88.00 | $80.83 | $163.33 | $120.00 | |
| 30 | 50201121 | COFFERDAM TYP 2 LOC 1 | 1 | EACH | $57,500.00 | $97,090.02 | $73,955.51 | $100,000.00 | |
| 31 | 50201122 | COFFERDAM TYP 2 LOC 2 | 1 | EACH | $57,500.00 | $85,421.78 | $73,955.51 | $100,000.00 | |
| 32 | 50300225 | CONC STRUCT | 145.1 | CU YD | $1,100.00 | $1,273.52 | $1,636.17 | $1,750.00 | |
| 33 | 50300265 | SEAL COAT CONC | 51.8 | CU YD | $350.00 | $364.10 | $674.80 | $450.00 | |
| 34 | 50300280 | CONCRETE ENCASEMENT | 3.4 | CU YD | $2,150.00 | $1,125.35 | $2,991.95 | $3,500.00 | |
| 35 | 50400405 | P P CONC DK BM 21 DP | 3,078 | SQ FT | $105.00 | $102.23 | $104.67 | $125.00 | |
| 36 | 50800205 | REINF BARS, EPOXY CTD | 11,670 | POUND | $2.50 | $1.98 | $2.84 | $3.00 | |
| 37 | 50901050 | STEEL RAILING TY SM | 221 | FOOT | $224.00 | $224.86 | $217.04 | $206.70 | |
| 38 | 51201400 | FUR STL PILE HP10X42 | 1,021 | FOOT | $74.00 | $58.04 | $60.28 | $55.00 | |
| 39 | 51202305 | DRIVING PILES | 1,021 | FOOT | $0.1000 | $0.0200 | $0.0100 | $0.0100 | |
| 40 | 51203400 | TEST PILE ST HP10X42 | 2 | EACH | $5,900.00 | $4,499.12 | $14,772.91 | $15,000.00 | |
| 41 | 51204650 | PILE SHOES | 22 | EACH | $210.00 | $135.85 | $122.31 | $175.00 | |
| 42 | 51500100 | NAME PLATES | 1 | EACH | $750.00 | $720.26 | $843.72 | $1,000.00 | |
| 43 | 58300100 | PC MORTAR FAIRING CSE | 661 | FOOT | $1.00 | $0.5000 | $0.0100 | $9.00 | |
| 44 | 58700300 | CONCRETE SEALER | 835 | SQ FT | $3.00 | $2.55 | $4.10 | $5.50 | |
| 45 | 59300100 | CONTR LOW-STRENG MATL | 46 | CU YD | $300.00 | $290.45 | $207.86 | $325.00 | |
| 46 | 63100087 | TRAF BAR TERM T6A | 2 | EACH | $5,333.00 | $5,343.78 | $4,935.00 | $4,700.00 | |
| 47 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $3,988.00 | $3,994.61 | $4,032.00 | $3,840.00 | |
| 48 | 63500105 | DELINEATORS | 4 | EACH | $65.00 | $64.81 | $237.98 | $226.65 | |
| 49 | 66500105 | WOV W FENCE 4 | 213 | FOOT | $27.00 | $26.98 | $26.78 | $92.85 | |
| 50 | 67100100 | MOBILIZATION | 1 | L SUM | $75,000.00 | $78,677.26 | $52,113.37 | $94,500.00 | |
| 51 | 72501000 | TERMINAL MARKER - DA | 2 | EACH | $43.00 | $43.39 | $52.50 | $50.00 | |
| 52 | 78001110 | PAINT PVT MK LINE 4 | 1,071 | FOOT | $3.40 | $3.44 | $3.41 | $2.80 | |
| 53 | 78200005 | GRDRAIL REF TYPE A | 8 | EACH | $11.00 | $10.85 | $10.50 | $10.00 |