22-P4003-00-BT
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stark Excavating, Inc. Low bidder | $430,250 | ||
| 2 | Duce Construction Company | $529,670 | +23.1% | |
| 3 | White Construction LLC | $905,000 | +110.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stark Excavatin… | #2 Duce Constructi… | #3 White Construct… |
|---|---|---|---|---|---|---|---|---|
| 1 | K1004572 | PRAIRIE SEEDING SPL | 0.25 | ACRE | $6,550.00 | $10,000.00 | $6,550.00 | |
| 2 | X0322508 | PED TRUSS SUPERSTR | 918 | SQ FT | $107.50 | $111.00 | $320.00 | |
| 3 | X2500910 | SEEDING CL 1 MOD | 0.5 | ACRE | $6,250.00 | $5,000.00 | $6,250.00 | |
| 4 | X2502024 | SEEDING CL 4B MOD | 0.25 | ACRE | $6,750.00 | $5,000.00 | $6,750.00 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $3,900.00 | $50,000.00 | $55,000.00 | |
| 6 | Z0013797 | STAB CONSTR ENTRANCE | 71 | SQ YD | $14.00 | $42.00 | $80.00 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $5,035.00 | $7,200.00 | $19,556.95 | |
| 8 | 20100500 | TREE REMOV ACRES | 0.25 | ACRE | $38,800.00 | $44,000.00 | $50,000.00 | |
| 9 | 20101000 | TEMPORARY FENCE | 487 | FOOT | $6.50 | $7.00 | $14.00 | |
| 10 | 20101200 | TREE ROOT PRUNING | 5 | EACH | $250.00 | $350.00 | $500.00 | |
| 11 | 20101350 | TREE PRUN OVER 10 | 10 | EACH | $165.00 | $500.00 | $500.00 | |
| 12 | 20101400 | NITROGEN FERT NUTR | 5 | POUND | $1.60 | $5.00 | $1.60 | |
| 13 | 20101500 | PHOSPHORUS FERT NUTR | 5 | POUND | $1.60 | $5.00 | $1.60 | |
| 14 | 20101600 | POTASSIUM FERT NUTR | 5 | POUND | $1.60 | $5.00 | $1.60 | |
| 15 | 20101700 | SUPPLE WATERING | 1 | UNIT | $1,850.00 | $299.00 | $1,850.00 | |
| 16 | 20200100 | EARTH EXCAVATION | 51 | CU YD | $49.00 | $77.00 | $125.00 | |
| 17 | 20400800 | FURNISHED EXCAVATION | 77 | CU YD | $47.00 | $77.00 | $125.00 | |
| 18 | 21101505 | TOPSOIL EXC & PLAC | 168 | CU YD | $118.00 | $77.00 | $120.00 | |
| 19 | 25000400 | NITROGEN FERT NUTR | 45 | POUND | $1.60 | $5.00 | $1.60 | |
| 20 | 25000500 | PHOSPHORUS FERT NUTR | 45 | POUND | $1.60 | $5.00 | $1.60 | |
| 21 | 25000600 | POTASSIUM FERT NUTR | 45 | POUND | $1.60 | $5.00 | $1.60 | |
| 22 | 25100115 | MULCH METHOD 2 | 0.75 | ACRE | $3,025.00 | $5,000.00 | $3,025.00 | |
| 23 | 25100630 | EROSION CONTR BLANKET | 762 | SQ YD | $2.25 | $4.50 | $2.25 | |
| 24 | 28000250 | TEMP EROS CONTR SEED | 50 | POUND | $14.75 | $5.00 | $10.00 | |
| 25 | 28000400 | PERIMETER EROS BAR | 742 | FOOT | $3.50 | $3.50 | $3.00 | |
| 26 | 28000510 | INLET FILTERS | 2 | EACH | $340.00 | $228.00 | $350.00 | |
| 27 | 28100107 | STONE RIPRAP CL A4 | 360 | SQ YD | $83.05 | $105.00 | $200.00 | |
| 28 | 28200200 | FILTER FABRIC | 360 | SQ YD | $3.90 | $4.50 | $3.00 | |
| 29 | 30300112 | AGG SUBGRADE IMPR 12 | 350 | SQ YD | $36.70 | $50.00 | $37.00 | |
| 30 | 35101600 | AGG BASE CSE B 4 | 1,020 | SQ YD | $16.00 | $11.50 | $20.00 | |
| 31 | 42400300 | PC CONC SIDEWALK 6 | 7,158 | SQ FT | $9.20 | $10.25 | $13.00 | |
| 32 | 42400410 | PC CONC SIDEWALK 8 | 501 | SQ FT | $12.00 | $13.50 | $13.50 | |
| 33 | 42400800 | DETECTABLE WARNINGS | 30 | SQ FT | $23.25 | $45.00 | $36.00 | |
| 34 | 44000500 | COMB CURB GUTTER REM | 56 | FOOT | $30.25 | $22.25 | $26.00 | |
| 35 | 44000600 | SIDEWALK REM | 3,757 | SQ FT | $1.90 | $3.00 | $2.00 | |
| 36 | 50200100 | STRUCTURE EXCAVATION | 36 | CU YD | $94.20 | $77.00 | $100.00 | |
| 37 | 50300225 | CONC STRUCT | 14.6 | CU YD | $1,475.00 | $1,860.00 | $4,500.00 | |
| 38 | 50300255 | CONC SUP-STR | 15 | CU YD | $915.00 | $826.00 | $2,450.00 | |
| 39 | 50300300 | PROTECTIVE COAT | 90 | SQ YD | $6.60 | $0.9000 | $15.00 | |
| 40 | 50800205 | REINF BARS, EPOXY CTD | 3,800 | POUND | $3.10 | $3.85 | $5.00 | |
| 41 | 51200957 | FUR M S PILE 12X0.250 | 94 | FOOT | $121.00 | $85.00 | $225.00 | |
| 42 | 51202305 | DRIVING PILES | 94 | FOOT | $0.0100 | $1.00 | $1.00 | |
| 43 | 51203200 | TEST PILE MET SHELLS | 2 | EACH | $7,100.00 | $13,200.00 | $8,500.00 | |
| 44 | 51500100 | NAME PLATES | 1 | EACH | $730.00 | $1,000.00 | $500.00 | |
| 45 | 60300305 | FR & LIDS ADJUST | 2 | EACH | $720.00 | $650.00 | $600.00 | |
| 46 | 60604400 | COMB CC&G TB6.18 | 56 | FOOT | $116.50 | $101.00 | $75.00 | |
| 47 | 67100100 | MOBILIZATION | 1 | L SUM | $24,999.91 | $31,000.00 | $54,000.00 | |
| 48 | 72000100 | SIGN PANEL T1 | 60.5 | SQ FT | $39.00 | $48.00 | $39.00 | |
| 49 | 72900200 | METAL POST TY B | 55 | FOOT | $36.00 | $25.00 | $36.00 | |
| 50 | 73000100 | WOOD SIN SUPPORT | 50 | FOOT | $49.00 | $30.00 | $49.00 | |
| 51 | 78000600 | THPL PVT MK LINE 12 | 120 | FOOT | $37.04 | $58.00 | $37.04 |