17-P4003-00-BT
Bidders 8
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stark Excavating, Inc. Low bidder | $442,510 | ||
| 2 | Mid-Illinois Concrete and Excavation, Inc. | $454,707 | +2.8% | |
| 3 | Feutz Contractors, Inc. | $479,727 | +8.4% | |
| 4 | Otto Baum Company, Inc. | $491,878 | +11.2% | |
| 5 | Duce Construction Company | $520,000 | +17.5% | |
| 6 | Beniach Construction Co., Inc. | $598,374 | +35.2% | |
| 7 | Cross Construction, Inc. | $628,767 | +42.1% | |
| 8 | Open Road Paving Company LLC | $654,449 | +47.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stark Excavatin… | #2 Mid-Illinois Co… | #3 Feutz Contracto… | #4 Otto Baum Compa… | #5 Duce Constructi… | #6 Beniach Constru… | #7 Cross Construct… | #8 Open Road Pavin… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | A2C02501 | T-CERCIS CANAD 1 CG | 2 | EACH | $375.00 | $525.00 | $550.00 | $523.16 | $498.00 | $594.00 | $491.15 | $446.50 | |
| 2 | A2C056G3 | T-QUERC MACR CG 3G | 1 | EACH | $375.00 | $545.00 | $700.00 | $523.16 | $498.00 | $725.00 | $511.83 | $465.30 | |
| 3 | A2002879 | T-CELTIS OCCID CL 2 | 2 | EACH | $375.00 | $910.00 | $820.00 | $523.16 | $498.00 | $667.00 | $853.05 | $775.50 | |
| 4 | A2005814 | T-PLATANUS OCC 1-3/4 | 2 | EACH | $375.00 | $875.00 | $650.00 | $523.16 | $498.00 | $667.00 | $822.03 | $747.30 | |
| 5 | A2006414 | T-QUERCUS ALBA 1-3/4 | 3 | EACH | $375.00 | $875.00 | $580.00 | $523.16 | $498.00 | $595.00 | $822.03 | $747.30 | |
| 6 | X0321461 | PILLAR REM | 1 | EACH | $1,200.00 | $875.00 | $920.00 | $1,503.60 | $2,000.00 | $631.00 | $6,792.11 | $2,000.00 | |
| 7 | X0327618 | LANDSCAPING, SPECIAL | 1 | L SUM | $50,000.00 | $67,255.00 | $50,000.00 | $63,915.74 | $60,799.75 | $141,612.00 | $63,250.00 | $57,500.00 | |
| 8 | X0327979 | PAVMT MRKG REM GRIND | 88 | SQ FT | $5.00 | $6.00 | $5.50 | $5.51 | $5.25 | $5.70 | $5.50 | $5.00 | |
| 9 | X2500910 | SEEDING CL 1 MOD | 0.25 | ACRE | $8,100.00 | $5,050.00 | $10,500.00 | $5,286.68 | $8,500.00 | $11,649.00 | $4,752.00 | $4,320.00 | |
| 10 | X2501820 | SEEDING CL 5 MOD | 0.25 | ACRE | $8,000.00 | $9,125.00 | $20,000.00 | $5,286.68 | $8,400.00 | $20,692.00 | $8,580.00 | $7,800.00 | |
| 11 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $4,000.00 | $3,920.00 | $12,000.00 | $20,155.39 | $14,000.00 | $17,800.00 | $32,015.09 | $20,000.00 | |
| 12 | X7240300 | SIGN REMOVAL | 1 | EACH | $300.00 | $245.00 | $310.00 | $376.97 | $322.00 | $113.00 | $2,648.72 | $750.00 | |
| 13 | Z0007124 | STEEL RAILING SPL | 103 | FOOT | $260.00 | $210.00 | $530.00 | $281.96 | $268.00 | $292.00 | $589.82 | $749.55 | |
| 14 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $6,000.00 | $6,265.00 | $3,800.00 | $5,506.94 | $6,000.00 | $7,994.00 | $9,625.00 | $3,300.00 | |
| 15 | 20100110 | TREE REMOV 6-15 | 31 | UNIT | $35.00 | $41.00 | $38.90 | $38.55 | $37.00 | $74.00 | $38.50 | $35.00 | |
| 16 | 20100210 | TREE REMOV OVER 15 | 210 | UNIT | $40.00 | $47.00 | $45.00 | $44.06 | $44.00 | $74.00 | $44.00 | $40.00 | |
| 17 | 20100500 | TREE REMOV ACRES | 0.5 | ACRE | $10,000.00 | $11,700.00 | $11,000.00 | $11,013.88 | $11,000.00 | $18,723.00 | $11,000.00 | $10,000.00 | |
| 18 | 20101000 | TEMPORARY FENCE | 1,422 | FOOT | $5.50 | $8.50 | $6.50 | $6.61 | $3.75 | $1.60 | $9.44 | $6.18 | |
| 19 | 20101200 | TREE ROOT PRUNING | 5 | EACH | $250.00 | $88.00 | $83.00 | $82.60 | $80.00 | $293.00 | $82.50 | $225.00 | |
| 20 | 20101300 | TREE PRUN 1-10 | 5 | EACH | $25.00 | $30.00 | $28.00 | $27.54 | $28.00 | $28.00 | $27.50 | $25.00 | |
| 21 | 20101350 | TREE PRUN OVER 10 | 5 | EACH | $50.00 | $59.00 | $56.00 | $55.07 | $53.00 | $57.00 | $55.00 | $50.00 | |
| 22 | 20101400 | NITROGEN FERT NUTR | 10 | POUND | $3.00 | $6.00 | $9.00 | $4.79 | $3.00 | $10.00 | $5.28 | $4.80 | |
| 23 | 20101500 | PHOSPHORUS FERT NUTR | 10 | POUND | $3.00 | $6.00 | $9.00 | $4.79 | $3.00 | $10.00 | $5.28 | $4.80 | |
| 24 | 20101600 | POTASSIUM FERT NUTR | 10 | POUND | $3.00 | $6.00 | $9.00 | $4.79 | $3.00 | $10.00 | $5.28 | $4.80 | |
| 25 | 20101700 | SUPPLE WATERING | 1 | UNIT | $100.00 | $210.00 | $700.00 | $2,065.10 | $100.00 | $784.00 | $198.00 | $180.00 | |
| 26 | 20200100 | EARTH EXCAVATION | 7 | CU YD | $60.00 | $55.00 | $44.00 | $53.78 | $75.00 | $36.00 | $58.48 | $45.00 | |
| 27 | 20201200 | REM & DISP UNS MATL | 1,150 | CU YD | $16.50 | $22.00 | $20.00 | $16.91 | $35.20 | $18.00 | $26.78 | $30.00 | |
| 28 | 20400800 | FURNISHED EXCAVATION | 597 | CU YD | $18.25 | $22.00 | $50.00 | $58.31 | $28.00 | $61.00 | $45.94 | $55.00 | |
| 29 | 21101505 | TOPSOIL EXC & PLAC | 771 | CU YD | $29.00 | $28.00 | $19.00 | $41.53 | $42.40 | $30.00 | $43.28 | $60.00 | |
| 30 | 25000305 | SEEDING CL 3A | 0.25 | ACRE | $8,000.00 | $3,650.00 | $14,500.00 | $5,286.68 | $8,400.00 | $16,213.00 | $3,432.00 | $3,120.00 | |
| 31 | 25000400 | NITROGEN FERT NUTR | 21 | POUND | $3.00 | $6.00 | $5.00 | $4.79 | $3.00 | $4.70 | $5.28 | $4.80 | |
| 32 | 25000500 | PHOSPHORUS FERT NUTR | 21 | POUND | $3.00 | $6.00 | $5.00 | $4.79 | $3.00 | $4.70 | $5.28 | $4.80 | |
| 33 | 25000600 | POTASSIUM FERT NUTR | 21 | POUND | $3.00 | $6.00 | $5.00 | $4.79 | $3.00 | $4.70 | $5.28 | $4.80 | |
| 34 | 25100125 | MULCH METHOD 3 | 0.25 | ACRE | $8,600.00 | $5,615.00 | $11,500.00 | $5,286.68 | $9,030.00 | $12,650.00 | $5,280.00 | $4,800.00 | |
| 35 | 25100630 | EROSION CONTR BLANKET | 1,345 | SQ YD | $2.00 | $5.70 | $3.85 | $2.31 | $2.20 | $2.40 | $5.28 | $4.80 | |
| 36 | 25200200 | SUPPLE WATERING | 5 | UNIT | $100.00 | $210.00 | $200.00 | $413.02 | $100.00 | $952.00 | $198.00 | $180.00 | |
| 37 | 28000250 | TEMP EROS CONTR SEED | 23 | POUND | $1.00 | $6.00 | $29.00 | $9.91 | $1.00 | $11.50 | $5.28 | $20.83 | |
| 38 | 28000400 | PERIMETER EROS BAR | 1,660 | FOOT | $3.00 | $3.70 | $2.40 | $3.81 | $3.34 | $3.00 | $5.77 | $4.83 | |
| 39 | 28000510 | INLET FILTERS | 32 | EACH | $150.00 | $160.00 | $248.00 | $222.58 | $142.00 | $182.00 | $241.86 | $225.00 | |
| 40 | 35101600 | AGG BASE CSE B 4 | 1,891 | SQ YD | $13.00 | $7.50 | $8.60 | $11.83 | $7.90 | $10.00 | $11.10 | $10.25 | |
| 41 | 42000200 | PCC PVT 7 | 151 | SQ YD | $100.00 | $54.00 | $84.00 | $75.70 | $101.00 | $101.00 | $115.11 | $155.00 | |
| 42 | 42400300 | PC CONC SIDEWALK 6 | 17,153 | SQ FT | $7.50 | $7.60 | $5.70 | $5.71 | $7.83 | $6.90 | $8.40 | $8.20 | |
| 43 | 42400800 | DETECTABLE WARNINGS | 252 | SQ FT | $22.00 | $25.00 | $20.00 | $27.37 | $27.75 | $19.00 | $22.32 | $25.00 | |
| 44 | 44000100 | PAVEMENT REM | 151 | SQ YD | $26.00 | $12.50 | $24.00 | $28.03 | $17.00 | $21.00 | $23.05 | $50.00 | |
| 45 | 44000500 | COMB CURB GUTTER REM | 338 | FOOT | $15.00 | $13.00 | $12.00 | $8.01 | $9.60 | $9.00 | $10.58 | $36.59 | |
| 46 | 44000600 | SIDEWALK REM | 1,823 | SQ FT | $2.00 | $1.50 | $2.00 | $2.29 | $1.75 | $1.70 | $2.46 | $3.75 | |
| 47 | 550A0050 | STORM SEW CL A 1 12 | 82 | FOOT | $52.00 | $50.00 | $50.00 | $54.23 | $38.25 | $52.00 | $79.40 | $135.00 | |
| 48 | 60219000 | MAN TA 4 DIA T8G | 1 | EACH | $2,300.00 | $1,900.00 | $2,600.00 | $2,147.26 | $2,792.00 | $1,387.00 | $3,159.41 | $2,800.00 | |
| 49 | 60236200 | INLETS TA T8G | 2 | EACH | $880.00 | $1,200.00 | $1,480.00 | $1,112.58 | $1,390.00 | $1,081.00 | $1,546.24 | $2,500.00 | |
| 50 | 60500040 | REMOV MANHOLES | 1 | EACH | $460.00 | $645.00 | $645.00 | $284.89 | $603.00 | $185.00 | $530.91 | $940.00 | |
| 51 | 60604400 | COMB CC&G TB6.18 | 304 | FOOT | $58.00 | $45.00 | $57.00 | $49.74 | $65.62 | $44.00 | $91.26 | $110.00 | |
| 52 | 67100100 | MOBILIZATION | 1 | L SUM | $12,500.00 | $2,800.00 | $23,000.00 | $20,432.83 | $31,000.00 | $30,000.00 | $17,121.32 | $22,500.00 | |
| 53 | 72000100 | SIGN PANEL T1 | 70 | SQ FT | $30.00 | $35.00 | $40.00 | $31.39 | $29.00 | $42.00 | $48.18 | $36.15 | |
| 54 | 72900200 | METAL POST TY B | 46 | FOOT | $16.50 | $27.00 | $19.00 | $21.75 | $21.65 | $3.00 | $53.40 | $17.45 | |
| 55 | 73000100 | WOOD SIN SUPPORT | 93 | FOOT | $19.00 | $56.00 | $21.00 | $48.46 | $23.00 | $2.00 | $46.52 | $19.40 | |
| 56 | 78009006 | MOD URETH PM LINE 6 | 77 | FOOT | $18.75 | $22.00 | $20.00 | $20.65 | $19.69 | $21.00 | $20.63 | $18.75 | |
| 57 | 78009024 | MOD URETH PM LINE 24 | 21 | FOOT | $50.00 | $60.00 | $55.00 | $55.07 | $52.50 | $57.00 | $55.00 | $50.00 | |
| 58 | 81028340 | UNDRGRD C PVC 1 1/2 | 530 | FOOT | $13.00 | $25.00 | $14.00 | $14.32 | $13.65 | $14.00 | $14.30 | $13.00 | |
| 59 | 81400730 | HANDHOLE C CONC | 6 | EACH | $800.00 | $670.00 | $850.00 | $881.11 | $840.00 | $913.00 | $880.00 | $800.00 | |
| 60 | 81702130 | EC C XLP USE 1C 6 | 1,590 | FOOT | $3.00 | $2.00 | $3.30 | $3.30 | $3.15 | $3.40 | $3.30 | $3.00 | |
| 61 | 84200500 | REM LT UNIT SALV | 2 | EACH | $550.00 | $295.00 | $610.00 | $605.77 | $577.50 | $628.00 | $605.00 | $550.00 | |
| 62 | 84400105 | RELOC EX LT UNIT | 2 | EACH | $900.00 | $1,325.00 | $950.00 | $991.25 | $945.00 | $1,027.00 | $990.00 | $900.00 |