21-00198-00-BT
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illinois Civil Contractors, Inc. Low bidder | $573,961 | ||
| 2 | Otto Baum Company, Inc. | $598,800 | +4.3% | |
| 3 | R. A. Cullinan and Son, a div of UCM, Inc. | $645,480 | +12.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illinois Civil … | #2 Otto Baum Compa… | #3 R. A. Cullinan … |
|---|---|---|---|---|---|---|---|---|
| 1 | X0301339 | REM EX PARKING BLOCKS | 3 | EACH | $81.85 | $143.72 | $91.05 | |
| 2 | X1700066 | POTHOLING | 5 | EACH | $1,331.61 | $330.02 | $958.15 | |
| 3 | X4404000 | PARKING LOT PAVT REM | 403 | SQ YD | $20.33 | $19.41 | $14.96 | |
| 4 | X6024210 | DOUBLE INLET SPL | 2 | EACH | $7,616.31 | $8,892.57 | $11,489.57 | |
| 5 | X6024242 | INLETS SPL N1 | 1 | EACH | $4,521.35 | $4,242.48 | $10,994.91 | |
| 6 | X6060064 | COMB CC&G TB9.18 SPL | 202 | FOOT | $93.12 | $82.06 | $105.07 | |
| 7 | X6062400 | CONC GUTTER SPL | 315 | FOOT | $88.72 | $54.46 | $74.99 | |
| 8 | X6640300 | CH LK FENCE REMOV | 622 | FOOT | $5.92 | $19.85 | $10.34 | |
| 9 | X6640312 | CH LK GATES REM & RE | 1 | EACH | $1,936.09 | $1,022.01 | $1,423.16 | |
| 10 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $3,304.28 | $7,420.23 | $9,318.23 | |
| 11 | Z0022810 | FENCE REMOVAL SPECIAL | 40 | FOOT | $23.01 | $16.34 | $27.22 | |
| 12 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 13 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 14 | 20200100 | EARTH EXCAVATION | 607 | CU YD | $41.71 | $73.81 | $77.77 | |
| 15 | 25000210 | SEEDING CL 2A | 0.25 | ACRE | $8,515.68 | $8,176.00 | $8,064.00 | |
| 16 | 25000400 | NITROGEN FERT NUTR | 30 | POUND | $3.33 | $3.19 | $3.15 | |
| 17 | 25000500 | PHOSPHORUS FERT NUTR | 30 | POUND | $3.33 | $3.19 | $3.15 | |
| 18 | 25000600 | POTASSIUM FERT NUTR | 30 | POUND | $3.33 | $3.19 | $3.15 | |
| 19 | 25100125 | MULCH METHOD 3 | 0.25 | ACRE | $8,515.68 | $8,176.00 | $8,064.00 | |
| 20 | 28000250 | TEMP EROS CONTR SEED | 25 | POUND | $5.98 | $20.31 | $31.95 | |
| 21 | 28000400 | PERIMETER EROS BAR | 1,231 | FOOT | $4.41 | $5.60 | $5.83 | |
| 22 | 28000500 | INLET & PIPE PROTECT | 3 | EACH | $275.89 | $315.96 | $636.53 | |
| 23 | 31101180 | SUB GRAN MAT B 2 | 62 | SQ YD | $11.60 | $12.23 | $17.36 | |
| 24 | 31101200 | SUB GRAN MAT B 4 | 445 | SQ YD | $15.17 | $16.25 | $16.43 | |
| 25 | 35100100 | AGG BASE CSE A | 560 | TON | $60.28 | $63.74 | $91.64 | |
| 26 | 35300100 | PCC BSE CSE 6 | 128 | SQ YD | $73.15 | $44.27 | $83.66 | |
| 27 | 40201000 | AGGREGATE-TEMP ACCESS | 136 | TON | $53.08 | $71.12 | $95.65 | |
| 28 | 40600290 | BIT MATLS TACK CT | 58 | POUND | $1.39 | $1.33 | $25.96 | |
| 29 | 40800050 | INCIDENTAL HMA SURF | 14 | TON | $471.25 | $452.45 | $611.57 | |
| 30 | 42300200 | PCC DRIVEWAY PAVT 6 | 292 | SQ YD | $74.51 | $94.05 | $113.86 | |
| 31 | 42300400 | PCC DRIVEWAY PAVT 8 | 153 | SQ YD | $108.77 | $100.11 | $119.97 | |
| 32 | 42400200 | PC CONC SIDEWALK 5 | 19,746 | SQ FT | $8.01 | $7.36 | $8.92 | |
| 33 | 42400800 | DETECTABLE WARNINGS | 178 | SQ FT | $33.23 | $45.76 | $39.10 | |
| 34 | 44000100 | PAVEMENT REM | 106 | SQ YD | $19.58 | $56.03 | $33.04 | |
| 35 | 44000200 | DRIVE PAVEMENT REM | 379 | SQ YD | $21.95 | $19.54 | $15.44 | |
| 36 | 44000500 | COMB CURB GUTTER REM | 415 | FOOT | $13.30 | $12.72 | $6.91 | |
| 37 | 44000600 | SIDEWALK REM | 97 | SQ FT | $4.74 | $9.10 | $6.96 | |
| 38 | 550A0340 | STORM SEW CL A 2 12 | 109 | FOOT | $167.60 | $159.55 | $143.98 | |
| 39 | 59300100 | CONTR LOW-STRENG MATL | 23 | CU YD | $139.53 | $137.90 | $125.57 | |
| 40 | 60603800 | COMB CC&G TB6.12 | 428 | FOOT | $88.60 | $93.80 | $110.15 | |
| 41 | 66400305 | CH LK FENCE 6 | 620 | FOOT | $48.23 | $60.96 | $32.55 | |
| 42 | 67100100 | MOBILIZATION | 1 | L SUM | $34,437.64 | $45,160.26 | $22,389.95 | |
| 43 | 72000100 | SIGN PANEL T1 | 15 | SQ FT | $39.92 | $23.42 | $22.58 | |
| 44 | 72400500 | RELOC SIN PAN ASSY TA | 5 | EACH | $388.09 | $319.38 | $131.25 | |
| 45 | 72400600 | RELOC SIN PAN ASSY TB | 3 | EACH | $388.09 | $319.38 | $210.00 | |
| 46 | 72800100 | TELES STL SIN SUPPORT | 175 | FOOT | $31.05 | $31.94 | $27.30 | |
| 47 | 73100100 | BASE TEL STL SIN SUPP | 3 | EACH | $942.49 | $479.06 | $262.50 | |
| 48 | 78001110 | PAINT PVT MK LINE 4 | 1,705 | FOOT | $3.05 | $0.8000 | $0.7900 | |
| 49 | 78001150 | PAINT PVT MK LINE 12 | 258 | FOOT | $9.15 | $4.26 | $4.20 | |
| 50 | 78001180 | PAINT PVT MK LINE 24 | 209 | FOOT | $18.30 | $5.32 | $5.25 |