22-00042-00-SW
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $283,773 | ||
| 2 | Gensini Excavating, Inc. | $307,198 | +8.3% | |
| 3 | Meade Inc. | $339,530 | +19.6% | |
| 4 | Gillan Construction LLC | $361,920 | +27.5% | |
| 5 | Knapp Concrete Contractors, Inc. | $436,056 | +53.7% | |
| 6 | Advanced Asphalt Company | $448,217 | +57.9% | |
| 7 | Davis Concrete Construction Co. | $599,685 | +111.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Gensini Excavat… | #3 Meade Inc. | #4 Gillan Construc… | #5 Knapp Concrete … | #6 Advanced Asphal… | #7 Davis Concrete … |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0327618 | LANDSCAPING, SPECIAL | 1 | L SUM | $20,700.00 | $20,000.00 | $28,000.00 | $21,780.00 | $8,640.00 | $19,800.00 | $20,000.00 | |
| 2 | 20200100 | EARTH EXCAVATION | 97 | CU YD | $40.00 | $50.00 | $62.00 | $110.00 | $64.80 | $195.00 | $125.00 | |
| 3 | 40600290 | BIT MATLS TACK CT | 3 | POUND | $0.0100 | $150.00 | $100.00 | $0.0100 | $32.40 | $1.00 | $1.00 | |
| 4 | 40800050 | INCIDENTAL HMA SURF | 1 | TON | $2,000.00 | $1,000.00 | $2,250.00 | $1,100.00 | $2,160.00 | $1,200.00 | $1,000.00 | |
| 5 | 42300200 | PCC DRIVEWAY PAVT 6 | 725 | SQ YD | $80.00 | $79.81 | $107.00 | $93.50 | $91.80 | $90.00 | $115.00 | |
| 6 | 42400100 | PC CONC SIDEWALK 4 | 16,561 | SQ FT | $7.25 | $9.09 | $9.15 | $10.50 | $14.69 | $12.00 | $21.00 | |
| 7 | 42400800 | DETECTABLE WARNINGS | 237 | SQ FT | $30.00 | $30.00 | $39.65 | $26.50 | $32.40 | $28.00 | $43.00 | |
| 8 | 44000200 | DRIVE PAVEMENT REM | 703 | SQ YD | $12.00 | $10.00 | $13.50 | $14.00 | $19.44 | $25.00 | $30.00 | |
| 9 | 44000500 | COMB CURB GUTTER REM | 254 | FOOT | $10.00 | $7.00 | $11.55 | $17.50 | $15.12 | $30.00 | $20.00 | |
| 10 | 44000600 | SIDEWALK REM | 3,160 | SQ FT | $2.50 | $2.00 | $3.20 | $1.95 | $2.70 | $9.00 | $6.00 | |
| 11 | 60255500 | MAN ADJUST | 3 | EACH | $1,000.00 | $450.00 | $375.00 | $475.00 | $864.00 | $1,775.00 | $500.00 | |
| 12 | 60255700 | MAN ADJ NEW T1F OL | 1 | EACH | $1,500.00 | $500.00 | $720.00 | $950.00 | $1,728.00 | $2,250.00 | $1,000.00 | |
| 13 | 60260300 | INLETS ADJ NEW T1F OL | 5 | EACH | $1,500.00 | $500.00 | $720.00 | $950.00 | $1,512.00 | $2,750.00 | $1,000.00 | |
| 14 | 60604400 | COMB CC&G TB6.18 | 254 | FOOT | $50.00 | $70.00 | $68.00 | $84.00 | $75.60 | $78.00 | $65.00 | |
| 15 | 67100100 | MOBILIZATION | 1 | L SUM | $16,700.00 | $10,000.00 | $14,000.00 | $19,500.00 | $21,600.00 | $25,000.00 | $40,000.00 | |
| 16 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $0.0100 | $8,750.00 | $1,350.00 | $4,500.00 | $15,120.00 | $8,750.00 | $100.00 | |
| 17 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $7,800.00 | $5,000.00 | $1,350.00 | $2,924.57 | $3,024.00 | $5,000.00 | $10,000.00 | |
| 18 | 78001130 | PAINT PVT MK LINE 6 | 398 | FOOT | $9.90 | $11.00 | $6.30 | $11.50 | $11.29 | $10.45 | $15.00 |