23-00306-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Riber Construction, Inc. Low bidder | $1,225,921 | ||
| 2 | Dunnet Bay Construction Company | $1,365,431 | +11.4% | |
| 3 | Tobey's Construction & Cartage, Inc. | $1,429,353 | +16.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Riber Construct… | #2 Dunnet Bay Cons… | #3 Tobey's Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.3 | ACRE | $7,400.00 | $7,400.00 | $12,500.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $5,000.00 | $4,450.00 | $4,450.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $4,500.00 | $12,500.00 | $9,000.00 | |
| 4 | 20200100 | EARTH EXCAVATION | 55 | CU YD | $85.00 | $140.00 | $100.00 | |
| 5 | 20300100 | CHANNEL EXCAVATION | 280 | CU YD | $42.00 | $65.00 | $55.00 | |
| 6 | 20400800 | FURNISHED EXCAVATION | 100 | CU YD | $0.0100 | $70.00 | $85.00 | |
| 7 | 25100630 | EROSION CONTR BLANKET | 1,206 | SQ YD | $1.80 | $1.80 | $2.30 | |
| 8 | 28000305 | TEMP DITCH CHECKS | 34 | FOOT | $15.00 | $15.00 | $12.00 | |
| 9 | 28000500 | INLET & PIPE PROTECT | 1 | EACH | $150.00 | $150.00 | $150.00 | |
| 10 | 28100107 | STONE RIPRAP CL A4 | 602 | SQ YD | $72.00 | $135.00 | $117.00 | |
| 11 | 28200200 | FILTER FABRIC | 602 | SQ YD | $2.00 | $5.00 | $2.50 | |
| 12 | 35650300 | BASE CSE WIDENING 8 | 114 | SQ YD | $90.00 | $150.00 | $149.00 | |
| 13 | 40200100 | AGG SURF CSE A | 94 | TON | $42.00 | $65.00 | $60.00 | |
| 14 | 40600275 | BIT MATLS PR CT | 258 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 15 | 40600290 | BIT MATLS TACK CT | 197 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 16 | 40600982 | HMA SURF REM BUTT JT | 232 | SQ YD | $30.00 | $31.00 | $27.00 | |
| 17 | 40603080 | HMA BC IL-19.0 N50 | 42 | TON | $150.00 | $200.00 | $174.00 | |
| 18 | 40604050 | HMA SC IL-9.5 C N50 | 106 | TON | $175.00 | $210.00 | $194.00 | |
| 19 | 48101200 | AGGREGATE SHLDS B | 102 | TON | $83.50 | $70.00 | $57.75 | |
| 20 | 50100100 | REM EXIST STRUCT | 1 | EACH | $70,550.00 | $170,000.00 | $55,000.00 | |
| 21 | 50105220 | PIPE CULVERT REMOV | 111 | FOOT | $11.00 | $30.00 | $25.00 | |
| 22 | 50201101 | COFFERDAM TYP 1 LOC 1 | 1 | EACH | $0.0100 | $31,150.00 | $40,500.00 | |
| 23 | 50300225 | CONC STRUCT | 51.2 | CU YD | $1,400.00 | $2,000.00 | $1,745.00 | |
| 24 | 50300280 | CONCRETE ENCASEMENT | 7.1 | CU YD | $2,000.00 | $4,650.00 | $5,185.00 | |
| 25 | 50300300 | PROTECTIVE COAT | 22 | SQ YD | $2.00 | $15.00 | $17.00 | |
| 26 | 50400505 | P P CONC DK BM 27 DP | 3,660 | SQ FT | $148.00 | $125.00 | $159.75 | |
| 27 | 50800205 | REINF BARS, EPOXY CTD | 5,690 | POUND | $3.00 | $4.15 | $4.30 | |
| 28 | 50900209 | STEEL RAILING TY SMX | 244 | FOOT | $341.55 | $340.00 | $363.00 | |
| 29 | 51201400 | FUR STL PILE HP10X42 | 120 | FOOT | $80.00 | $125.00 | $76.00 | |
| 30 | 51201600 | FUR STL PILE HP12X53 | 60 | FOOT | $100.00 | $145.00 | $90.00 | |
| 31 | 51265002 | DRILL & SET PILES (IR) | 217 | CU FT | $660.00 | $300.00 | $715.00 | |
| 32 | 51500100 | NAME PLATES | 1 | EACH | $920.00 | $900.00 | $900.00 | |
| 33 | 542D0220 | P CUL CL D 1 15 | 70 | FOOT | $55.00 | $85.00 | $49.50 | |
| 34 | 542D0223 | P CUL CL D 1 18 | 74 | FOOT | $61.00 | $85.00 | $65.50 | |
| 35 | 58100200 | WATERPRF MEMBRANE SYS | 427 | SQ YD | $56.00 | $43.15 | $55.00 | |
| 36 | 58300100 | PC MORTAR FAIRING CSE | 275 | FOOT | $0.0100 | $15.00 | $3.00 | |
| 37 | 58600101 | GRANULAR BACKFILL STR | 97 | CU YD | $54.50 | $145.00 | $95.00 | |
| 38 | 59100100 | GEOCOMPOSITE WALL DR | 57 | SQ YD | $22.00 | $32.00 | $40.00 | |
| 39 | 60100060 | CONC HDWL FOR P DRAIN | 4 | EACH | $475.00 | $925.00 | $425.00 | |
| 40 | 60146304 | P UNDR FOR STRUCT 4 | 142 | FOOT | $0.0100 | $35.00 | $21.00 | |
| 41 | 63000001 | SPBGR TY A 6FT POSTS | 75 | FOOT | $39.50 | $44.00 | $27.00 | |
| 42 | 63100087 | TRAF BAR TERM T6A | 2 | EACH | $5,285.00 | $5,610.00 | $4,800.00 | |
| 43 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $4,145.00 | $3,925.00 | $3,000.00 | |
| 44 | 67100100 | MOBILIZATION | 1 | L SUM | $73,500.00 | $81,925.84 | $85,000.00 | |
| 45 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $50.00 | $50.00 | $50.00 | |
| 46 | 78200005 | GRDRAIL REF TYPE A | 8 | EACH | $10.00 | $25.00 | $12.00 |