15-00045-00-BR
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Riber Construction, Inc. Low bidder | $1,162,974 | ||
| 2 | D. Construction, Inc. | $1,210,257 | +4.1% | |
| 3 | Herlihy Mid-Continent Company | $1,579,183 | +35.8% | |
| 4 | Alliance Contractors, Inc. | $1,626,141 | +39.8% | |
| 5 | Rausch Infrastructure LLC_DO NOT USE | $1,771,234 | +52.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Riber Construct… | #2 D. Construction… | #3 Herlihy Mid-Con… | #4 Alliance Contra… | #5 Rausch Infrastr… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | XX006199 | STEEL BR RAIL SM SPL | 256 | FOOT | $168.85 | $162.00 | $147.27 | $147.27 | $175.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $5,300.00 | $20,000.00 | $8,500.00 | $5,300.00 | $15,000.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $6,500.00 | $8,000.00 | $15,000.00 | $5,500.00 | $30,000.00 | |
| 4 | Z0022800 | FENCE REMOVAL | 1,272 | FOOT | $3.65 | $3.00 | $3.92 | $3.92 | $5.00 | |
| 5 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $18.00 | $25.00 | $18.00 | $18.00 | $20.00 | |
| 6 | 20100110 | TREE REMOV 6-15 | 241 | UNIT | $10.00 | $11.00 | $10.00 | $10.00 | $28.00 | |
| 7 | 20100210 | TREE REMOV OVER 15 | 181 | UNIT | $16.00 | $17.60 | $16.00 | $16.00 | $35.00 | |
| 8 | 20200100 | EARTH EXCAVATION | 263 | CU YD | $42.00 | $25.00 | $75.00 | $20.00 | $45.00 | |
| 9 | 20300100 | CHANNEL EXCAVATION | 690 | CU YD | $21.00 | $30.00 | $67.00 | $40.00 | $64.00 | |
| 10 | 20400800 | FURNISHED EXCAVATION | 1,237 | CU YD | $28.50 | $25.00 | $30.00 | $10.00 | $20.00 | |
| 11 | 21101615 | TOPSOIL F & P 4 | 3,388 | SQ YD | $3.40 | $5.00 | $4.00 | $5.30 | $6.00 | |
| 12 | 25000210 | SEEDING CL 2A | 0.7 | ACRE | $2,000.00 | $2,200.00 | $1,210.00 | $2,217.14 | $2,640.00 | |
| 13 | 25000400 | NITROGEN FERT NUTR | 63 | POUND | $2.00 | $2.20 | $2.00 | $5.44 | $6.00 | |
| 14 | 25000500 | PHOSPHORUS FERT NUTR | 63 | POUND | $2.00 | $2.20 | $2.00 | $5.44 | $6.00 | |
| 15 | 25000600 | POTASSIUM FERT NUTR | 63 | POUND | $2.00 | $2.20 | $2.00 | $5.44 | $6.00 | |
| 16 | 25100115 | MULCH METHOD 2 | 1.9 | ACRE | $1,000.00 | $1,100.00 | $2,420.00 | $2,154.77 | $2,500.00 | |
| 17 | 25100630 | EROSION CONTR BLANKET | 3,388 | SQ YD | $1.25 | $1.38 | $1.75 | $1.11 | $1.25 | |
| 18 | 28000250 | TEMP EROS CONTR SEED | 200 | POUND | $3.50 | $3.85 | $4.00 | $6.99 | $8.00 | |
| 19 | 28000305 | TEMP DITCH CHECKS | 20 | FOOT | $11.00 | $12.10 | $20.00 | $32.89 | $40.00 | |
| 20 | 28000400 | PERIMETER EROS BAR | 1,800 | FOOT | $3.00 | $2.20 | $2.50 | $1.78 | $2.50 | |
| 21 | 28000500 | INLET & PIPE PROTECT | 1 | EACH | $175.00 | $192.50 | $300.00 | $250.00 | $800.00 | |
| 22 | 28100109 | STONE RIPRAP CL A5 | 830 | SQ YD | $78.00 | $55.00 | $91.00 | $170.00 | $75.00 | |
| 23 | 28200200 | FILTER FABRIC | 650 | SQ YD | $3.25 | $3.00 | $2.50 | $1.00 | $4.00 | |
| 24 | 30300112 | AGG SUBGRADE IMPR 12 | 3,632 | SQ YD | $17.00 | $16.00 | $20.45 | $14.25 | $14.00 | |
| 25 | 35101800 | AGG BASE CSE B 6 | 56 | SQ YD | $12.00 | $10.00 | $1.00 | $6.00 | $30.00 | |
| 26 | 40200100 | AGG SURF CSE A | 29 | TON | $37.00 | $30.00 | $75.00 | $64.00 | $64.00 | |
| 27 | 40201000 | AGGREGATE-TEMP ACCESS | 57 | TON | $20.00 | $30.00 | $40.00 | $1.00 | $40.00 | |
| 28 | 40600290 | BIT MATLS TACK CT | 553 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 29 | 40603080 | HMA BC IL-19.0 N50 | 843 | TON | $65.00 | $76.00 | $65.00 | $65.00 | $77.00 | |
| 30 | 40603310 | HMA SC "C" N50 | 278 | TON | $73.00 | $80.00 | $73.00 | $73.00 | $88.00 | |
| 31 | 40800050 | INCIDENTAL HMA SURF | 7 | TON | $375.00 | $180.00 | $375.00 | $375.00 | $500.00 | |
| 32 | 42001300 | PROTECTIVE COAT | 59 | SQ YD | $4.00 | $2.00 | $3.50 | $0.0100 | $8.00 | |
| 33 | 44000100 | PAVEMENT REM | 2,525 | SQ YD | $7.50 | $10.00 | $11.00 | $30.00 | $12.00 | |
| 34 | 44000200 | DRIVE PAVEMENT REM | 34 | SQ YD | $7.50 | $10.00 | $12.00 | $20.00 | $33.00 | |
| 35 | 48101200 | AGGREGATE SHLDS B | 272 | TON | $30.00 | $30.00 | $38.00 | $38.00 | $45.00 | |
| 36 | 48203027 | HMA SHOULDERS 7 1/2 | 367 | SQ YD | $37.00 | $36.00 | $37.00 | $37.00 | $44.00 | |
| 37 | 50100100 | REM EXIST STRUCT | 1 | EACH | $46,100.00 | $150,000.00 | $241,000.00 | $205,293.00 | $355,000.00 | |
| 38 | 50200100 | STRUCTURE EXCAVATION | 45 | CU YD | $35.00 | $30.00 | $52.00 | $40.00 | $52.00 | |
| 39 | 50200300 | COFFERDAM EXCAVATION | 160 | CU YD | $39.00 | $35.00 | $0.0100 | $40.00 | $98.00 | |
| 40 | 50201101 | COFFERDAM TYP 1 LOC 1 | 1 | EACH | $36,000.00 | $0.0100 | $1.00 | $1.00 | $25,000.00 | |
| 41 | 50201102 | COFFERDAM TYP 1 LOC 2 | 1 | EACH | $36,000.00 | $0.0100 | $1.00 | $1.00 | $25,000.00 | |
| 42 | 50300225 | CONC STRUCT | 140.2 | CU YD | $700.00 | $800.00 | $950.00 | $1,395.00 | $950.00 | |
| 43 | 50300280 | CONCRETE ENCASEMENT | 3.4 | CU YD | $1,160.00 | $500.00 | $2,517.43 | $2,475.00 | $1,000.00 | |
| 44 | 50400305 | P P CONC DK BM 17 DP | 1,931 | SQ FT | $58.20 | $57.50 | $82.00 | $75.00 | $70.00 | |
| 45 | 50400505 | P P CONC DK BM 27 DP | 2,096 | SQ FT | $67.00 | $69.00 | $95.00 | $82.00 | $72.00 | |
| 46 | 50800105 | REINFORCEMENT BARS | 10,750 | POUND | $1.70 | $1.80 | $2.50 | $1.90 | $2.15 | |
| 47 | 51201400 | FUR STL PILE HP10X42 | 520 | FOOT | $37.80 | $58.00 | $41.00 | $1.00 | $48.00 | |
| 48 | 51201610 | FUR STL PILE HP12X63 | 820 | FOOT | $48.50 | $60.00 | $61.00 | $1.00 | $52.00 | |
| 49 | 51202305 | DRIVING PILES | 1,340 | FOOT | $0.1000 | $0.0100 | $1.00 | $103.00 | $1.00 | |
| 50 | 51203400 | TEST PILE ST HP10X42 | 2 | EACH | $11,000.00 | $3,500.00 | $5,567.72 | $5,000.00 | $20,000.00 | |
| 51 | 51203610 | TEST PILE ST HP12X63 | 2 | EACH | $14,000.00 | $4,500.00 | $7,461.57 | $5,000.00 | $20,000.00 | |
| 52 | 51500100 | NAME PLATES | 1 | EACH | $400.00 | $500.00 | $550.00 | $500.00 | $535.00 | |
| 53 | 58100200 | WATERPRF MEMBRANE SYS | 455 | SQ YD | $36.50 | $31.13 | $48.00 | $42.30 | $64.00 | |
| 54 | 58300100 | PC MORTAR FAIRING CSE | 220 | FOOT | $0.0100 | $2.50 | $9.00 | $1.00 | $15.00 | |
| 55 | 59300100 | CONTR LOW-STRENG MATL | 13.9 | CU YD | $150.00 | $200.00 | $500.00 | $200.00 | $300.00 | |
| 56 | 60100060 | CONC HDWL FOR P DRAIN | 4 | EACH | $311.00 | $300.00 | $425.00 | $350.00 | $245.00 | |
| 57 | 60108100 | PIPE UNDERDRAIN 4 SP | 160 | FOOT | $20.00 | $24.00 | $30.00 | $17.50 | $23.00 | |
| 58 | 60108501 | PIPE UNDERDR T 3 | 1,465 | FOOT | $20.00 | $13.00 | $23.15 | $17.50 | $34.00 | |
| 59 | 60600095 | CLASS SI CONC OUTLET | 3.9 | CU YD | $660.00 | $400.00 | $500.00 | $450.00 | $575.00 | |
| 60 | 60602800 | CONC GUTTER TB | 180 | FOOT | $32.00 | $23.00 | $22.00 | $40.00 | $30.00 | |
| 61 | 63100087 | TRAF BAR TERM T6A | 2 | EACH | $4,075.00 | $4,164.60 | $3,786.00 | $3,786.00 | $4,500.00 | |
| 62 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $3,460.00 | $3,206.50 | $2,915.00 | $2,915.00 | $3,500.00 | |
| 63 | 63200310 | GUARDRAIL REMOV | 346 | FOOT | $6.00 | $5.89 | $5.35 | $5.35 | $6.00 | |
| 64 | 66500105 | WOV W FENCE 4 | 1,275 | FOOT | $14.00 | $13.46 | $12.24 | $12.24 | $15.00 | |
| 65 | 67100100 | MOBILIZATION | 1 | L SUM | $46,840.00 | $68,000.00 | $94,000.00 | $98,728.00 | $100,000.00 | |
| 66 | 72000100 | SIGN PANEL T1 | 5 | SQ FT | $40.00 | $25.00 | $40.00 | $40.00 | $90.00 | |
| 67 | 72400100 | REMOV SIN PAN ASSY TA | 3 | EACH | $50.00 | $50.00 | $50.00 | $50.00 | $175.00 | |
| 68 | 72400200 | REMOV SIN PAN ASSY TB | 2 | EACH | $75.00 | $50.00 | $75.00 | $75.00 | $260.00 | |
| 69 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $40.00 | $49.50 | $45.00 | $45.00 | $54.00 | |
| 70 | 72800100 | TELES STL SIN SUPPORT | 13 | FOOT | $15.00 | $20.00 | $15.00 | $15.00 | $30.00 | |
| 71 | 78009004 | MOD URETH PM LINE 4 | 9,348 | FOOT | $0.8100 | $0.6100 | $1.60 | $0.8100 | $1.00 | |
| 72 | 78200005 | GRDRAIL REF TYPE A | 8 | EACH | $9.00 | $13.20 | $12.00 | $12.00 | $14.00 |