(267-1212.2-15D) BDR,BJR 25
- Let date
- Friday, June 12, 2026
- Contract
- 80B47 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- Bridge Painting project consists of reconstruction of the expansion joints with strip seals, slope wall repair and substructure repair. Project is located on FAI 90/94 (Kennedy Expressway) under Ainslie Street in the City of Chicago. (SN 016-1105)
- Classification
- Reconstruction of the expansion joints with strip seals, slope wall repair and substructure repair ·
- Project number
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Areatha Construction Co., Inc. Low bidder | $641,982 | ||
| 2 | Lorig Construction Company | $643,436 | +0.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Areatha Constru… | #2 Lorig Construct… |
|---|---|---|---|---|---|---|---|
| 1 | X0326766 | CLEAN RESEAL RLF JNT | 96 | FOOT | $84.80 | $100.00 | |
| 2 | X6700407 | ENGRS FLD OFC TY A D1 | 6 | CAL MO | $3,000.00 | $3,300.00 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $15,000.00 | $58,000.00 | |
| 4 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $67,200.00 | $100,000.00 | |
| 5 | X7200061 | TEMP INFO SIGNING | 219 | SQ FT | $18.00 | $22.00 | |
| 6 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $24,496.15 | $8,000.00 | |
| 7 | Z0073200 | TEMP SHORING & CRIB | 3 | EACH | $17,386.40 | $5,000.00 | |
| 8 | 20700220 | POROUS GRAN EMBANK | 16 | CU YD | $189.55 | $500.00 | |
| 9 | 50102400 | CONC REM | 11.6 | CU YD | $2,133.40 | $2,900.00 | |
| 10 | 50104650 | SLOPE WALL REMOV | 94 | SQ YD | $93.30 | $250.00 | |
| 11 | 50300255 | CONC SUP-STR | 11.7 | CU YD | $4,197.95 | $3,300.00 | |
| 12 | 50300300 | PROTECTIVE COAT | 32 | SQ YD | $13.10 | $5.00 | |
| 13 | 50800205 | REINF BARS, EPOXY CTD | 2,340 | POUND | $5.90 | $4.00 | |
| 14 | 51100100 | SLOPE WALL 4 | 94 | SQ YD | $285.85 | $325.00 | |
| 15 | 52000110 | PREF JT STRIP SEAL | 141.5 | FOOT | $460.05 | $340.00 | |
| 16 | 53212754 | STR REP CON DP = < 5 | 794 | SQ FT | $223.75 | $200.00 | |
| 17 | 53212755 | STR REP CON DP OVER 5 | 92 | SQ FT | $220.65 | $225.00 | |
| 18 | 67100100 | MOBILIZATION | 1 | L SUM | $38,505.00 | $30,000.00 | |
| 19 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $1,124.65 | $100.00 | |
| 20 | 70400100 | TEMP CONC BARRIER | 175 | FOOT | $65.00 | $70.00 | |
| 21 | 70600250 | IMP ATTN TEMP NRD TL3 | 1 | EACH | $4,600.00 | $5,000.00 | |
| 22 | 78004620 | PREF PL PM TD STD L4 | 726 | FOOT | $7.25 | $8.00 | |
| 23 | 78011025 | GRV RCSD PVT MRKG 5 | 726 | FOOT | $3.25 | $5.00 |