Bid tab 78B73

Let Aug 1, 2025 · District 9 · Johnson

‹ Aug 2025 results

115PP-1

Let date
Friday, August 1, 2025
Contract
78B73 · job page
District
District 9
County
Johnson
Highway
Limits
Patching on IL 37 from Hunter Street to Carter Street in Cypress.
Classification
·
Project number

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Samron Midwest Contracting, Inc. Low bidder $106,695
2 E. T. Simonds Construction Company $131,321 +23.1%
3 Kinney Contractors, Inc. $134,637 +26.2%
4 G. M. Sipes Construction, Inc. $177,977 +66.8%

Bid tab: unit prices 11 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Samron Midwest …#2 E. T. Simonds C…#3 Kinney Contract…#4 G. M. Sipes Con…
1X4421382 CL C PATCH T4 12 SPL295SQ YD $200.00 $220.00 $252.00 $300.00
244200050 WELDED WIRE REINF295SQ YD $10.00 $31.34 $19.00 $30.00
344201373 CL C PATCH T1 124SQ YD $150.00 $250.00 $300.00 $375.00
444201377 CL C PATCH T2 12110SQ YD $200.00 $239.10 $242.00 $325.00
544201381 CL C PATCH T3 1215SQ YD $200.00 $230.00 $240.00 $325.00
644213204 TIE BARS 3/4155EACH $19.00 $20.75 $18.00 $0.0100
767100100 MOBILIZATION1L SUM $6,400.00 $7,299.38 $8,000.00 $8,500.00
870100450 TRAF CONT-PROT 7012011L SUM $0.0100 $0.0100 $1.00 $0.0100
970100600 TRAF CONT-PROT 7013361L SUM $0.0100 $0.0100 $1.00 $0.0100
1070102620 TR CONT & PROT 7015011L SUM $7,000.00 $14,179.63 $8,000.00 $30,000.00
1170107025 CHANGEABLE MESSAGE SN28CAL DA $100.00 $61.78 $160.00 $0.0100