(5,6,7)RS-5,SW-1,SR-1
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $2,709,114 | ||
| 2 | Samron Midwest Contracting, Inc. | $2,752,043 | +1.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | X4240420 | PC CONC SIDEWALK 4 SP | 25 | SQ FT | $79.32 | $120.00 | |
| 2 | X6420112 | CENTERLN RUM STRIP 8 | 7,467 | FOOT | $1.25 | $1.10 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $11,521.46 | $25,000.00 | |
| 4 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $5,401.20 | $10,000.00 | |
| 5 | 20200600 | EXC & GR EX SHOULDER | 194 | UNIT | $463.73 | $280.00 | |
| 6 | 40600290 | BIT MATLS TACK CT | 88,812 | POUND | $0.0100 | $0.0100 | |
| 7 | 40600370 | LONG JOINT SEALANT | 35,660 | FOOT | $2.61 | $2.40 | |
| 8 | 40600405 | MATL TRANSFER DEVICE | 14,862 | TON | $3.71 | $1.80 | |
| 9 | 40600982 | HMA SURF REM BUTT JT | 985 | SQ YD | $18.59 | $5.00 | |
| 10 | 40600990 | TEMPORARY RAMP | 814 | SQ YD | $23.67 | $15.00 | |
| 11 | 40602970 | HMA BC IL-9.5FG N70 | 6,452 | TON | $83.92 | $88.00 | |
| 12 | 40604052 | HMA SC IL-9.5 C N70 | 8,385 | TON | $82.82 | $91.00 | |
| 13 | 40800050 | INCIDENTAL HMA SURF | 69 | TON | $365.96 | $575.00 | |
| 14 | 42001300 | PROTECTIVE COAT | 2 | SQ YD | $0.0100 | $0.0100 | |
| 15 | 42400800 | DETECTABLE WARNINGS | 8 | SQ FT | $20.95 | $25.00 | |
| 16 | 44000155 | HMA SURF REM 1 1/2 | 104,420 | SQ YD | $1.42 | $1.75 | |
| 17 | 44000159 | HMA SURF REM 2 1/2 | 46,140 | SQ YD | $0.0100 | $0.0100 | |
| 18 | 44000400 | GUTTER REM | 1,271 | FOOT | $17.79 | $5.00 | |
| 19 | 44000500 | COMB CURB GUTTER REM | 4 | FOOT | $207.10 | $20.00 | |
| 20 | 44000600 | SIDEWALK REM | 25 | SQ FT | $33.14 | $15.00 | |
| 21 | 48102100 | AGG WEDGE SHLD TYPE B | 732 | TON | $57.29 | $65.00 | |
| 22 | 48203029 | HMA SHOULDERS 8 | 8,591 | SQ YD | $37.60 | $45.00 | |
| 23 | 48203100 | HMA SHOULDERS | 2,752 | TON | $86.84 | $90.00 | |
| 24 | 60603800 | COMB CC&G TB6.12 | 4 | FOOT | $439.13 | $30.00 | |
| 25 | 64200108 | SHOULDER RUM STRIP 8 | 59,415 | FOOT | $0.1900 | $0.1900 | |
| 26 | 67000400 | ENGR FIELD OFFICE A | 5 | CAL MO | $2,100.00 | $1,600.00 | |
| 27 | 67100100 | MOBILIZATION | 1 | L SUM | $212,753.19 | $164,000.00 | |
| 28 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $60,373.85 | $25,000.00 | |
| 29 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $15,093.88 | $5,500.00 | |
| 30 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $0.0100 | $0.0100 | |
| 31 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $0.0100 | $2,500.00 | |
| 32 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $0.0100 | $0.0100 | |
| 33 | 70103815 | TR CONT SURVEILLANCE | 5 | CAL DA | $0.0100 | $0.0100 | |
| 34 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $39.28 | $100.00 | |
| 35 | 70300100 | SHORT TERM PAVT MKING | 9,439 | FOOT | $1.38 | $1.65 | |
| 36 | 70300150 | SHRT TRM PAVT MK REM | 3,147 | SQ FT | $0.0100 | $1.20 | |
| 37 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 124 | SQ FT | $0.0100 | $0.0100 | |
| 38 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 71,208 | FOOT | $0.0100 | $0.0100 | |
| 39 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 90 | FOOT | $0.0100 | $0.0100 | |
| 40 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 216 | FOOT | $0.0100 | $0.0100 | |
| 41 | 78000100 | THPL PVT MK LTR & SYM | 124 | SQ FT | $27.04 | $26.25 | |
| 42 | 78000400 | THPL PVT MK LINE 6 | 90 | FOOT | $6.73 | $6.50 | |
| 43 | 78000650 | THPL PVT MK LINE 24 | 216 | FOOT | $27.56 | $26.50 | |
| 44 | 78001110 | PAINT PVT MK LINE 4 | 71,208 | FOOT | $0.1200 | $0.1300 | |
| 45 | 78100100 | RAISED REFL PAVT MKR | 427 | EACH | $38.48 | $37.50 | |
| 46 | 78300200 | RAISED REF PVT MK REM | 425 | EACH | $9.88 | $10.00 | |
| 47 | 78300201 | PVT MKG REM GRINDING | 24,337 | SQ FT | $0.0100 | $0.0100 |