(5,6,7)PP-1
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $521,745 | ||
| 2 | Kinney Contractors, Inc. | $583,938 | +11.9% | |
| 3 | G. M. Sipes Construction, Inc. | $651,100 | +24.8% | |
| 4 | Samron Midwest Contracting, Inc. | $687,535 | +31.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Kinney Contract… | #3 G. M. Sipes Con… | #4 Samron Midwest … |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $7,199.50 | $5,000.00 | $15,000.00 | $14,000.00 | |
| 2 | 44201373 | CL C PATCH T1 12 | 16 | SQ YD | $206.00 | $280.00 | $305.00 | $275.00 | |
| 3 | 44201377 | CL C PATCH T2 12 | 1,379 | SQ YD | $200.00 | $230.00 | $230.00 | $270.00 | |
| 4 | 44201381 | CL C PATCH T3 12 | 365 | SQ YD | $195.00 | $227.00 | $225.00 | $265.00 | |
| 5 | 44201383 | CL C PATCH T4 12 | 303 | SQ YD | $189.00 | $224.00 | $225.00 | $260.00 | |
| 6 | 44201423 | CL C PATCH T1 16 | 16 | SQ YD | $208.00 | $350.00 | $330.00 | $295.00 | |
| 7 | 44201427 | CL C PATCH T2 16 | 54 | SQ YD | $202.00 | $298.00 | $255.00 | $290.00 | |
| 8 | 44201431 | CL C PATCH T3 16 | 20 | SQ YD | $197.00 | $295.00 | $250.00 | $285.00 | |
| 9 | 44201433 | CL C PATCH T4 16 | 54 | SQ YD | $190.00 | $292.00 | $250.00 | $280.00 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $28,517.00 | $24,000.00 | $32,000.00 | $40,000.00 | |
| 11 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $0.0100 | $20,000.00 | $30,000.00 | $0.0100 | |
| 12 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $48,794.94 | $1.00 | $30,000.00 | $19,000.00 | |
| 13 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $0.0100 | $15,000.00 | $30,000.00 | $19,000.00 | |
| 14 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $45.00 | $150.00 | $150.00 | $75.00 |