(13,13Z)RS-5
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $963,345 | ||
| 2 | Samron Midwest Contracting, Inc. | $988,006 | +2.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $16,717.80 | $9,000.00 | |
| 2 | 40600290 | BIT MATLS TACK CT | 4,616 | POUND | $4.56 | $0.0100 | |
| 3 | 40600370 | LONG JOINT SEALANT | 17,042 | FOOT | $3.03 | $4.20 | |
| 4 | 40600405 | MATL TRANSFER DEVICE | 4,221 | TON | $6.20 | $2.55 | |
| 5 | 40600990 | TEMPORARY RAMP | 312 | SQ YD | $36.82 | $35.00 | |
| 6 | 40602970 | HMA BC IL-9.5FG N70 | 1,919 | TON | $133.01 | $125.00 | |
| 7 | 40604062 | HMA SC IL-9.5 D N70 | 2,302 | TON | $124.43 | $120.00 | |
| 8 | 44000160 | HMA SURF REM 2 3/4 | 26,714 | SQ YD | $3.52 | $3.40 | |
| 9 | 44201389 | CL C PATCH T2 13 | 16 | SQ YD | $225.00 | $335.00 | |
| 10 | 44201394 | CL C PATCH T3 13 | 16 | SQ YD | $220.00 | $330.00 | |
| 11 | 44201396 | CL C PATCH T4 13 | 146.7 | SQ YD | $215.00 | $325.00 | |
| 12 | 67000400 | ENGR FIELD OFFICE A | 2 | CAL MO | $2,200.00 | $1,800.00 | |
| 13 | 67100100 | MOBILIZATION | 1 | L SUM | $57,570.05 | $58,500.00 | |
| 14 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $15,707.20 | $5,000.00 | |
| 15 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $25,068.46 | $35,000.00 | |
| 16 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $0.0100 | $0.0100 | |
| 17 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $41.25 | $115.00 | |
| 18 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $2,760.00 | $30,000.00 | |
| 19 | 70300100 | SHORT TERM PAVT MKING | 5,081 | FOOT | $2.81 | $2.25 | |
| 20 | 70300150 | SHRT TRM PAVT MK REM | 1,694 | SQ FT | $0.0100 | $9.00 | |
| 21 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 434.4 | SQ FT | $0.0100 | $0.0100 | |
| 22 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 12,391 | FOOT | $0.0100 | $0.0100 | |
| 23 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 75 | FOOT | $0.0100 | $0.0100 | |
| 24 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 134 | FOOT | $0.0100 | $0.0100 | |
| 25 | 78000100 | THPL PVT MK LTR & SYM | 434.4 | SQ FT | $11.55 | $8.00 | |
| 26 | 78000200 | THPL PVT MK LINE 4 | 12,391 | FOOT | $0.8700 | $1.55 | |
| 27 | 78000600 | THPL PVT MK LINE 12 | 75 | FOOT | $11.55 | $4.60 | |
| 28 | 78000650 | THPL PVT MK LINE 24 | 134 | FOOT | $16.50 | $9.30 | |
| 29 | 78100100 | RAISED REFL PAVT MKR | 309 | EACH | $62.70 | $94.00 | |
| 30 | 78300200 | RAISED REF PVT MK REM | 309 | EACH | $8.16 | $16.00 | |
| 31 | 78300201 | PVT MKG REM GRINDING | 4,914 | SQ FT | $0.0100 | $0.0100 |