110RS-5
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $2,371,499 | ||
| 2 | Samron Midwest Contracting, Inc. | $2,595,923 | +9.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | X6420112 | CENTERLN RUM STRIP 8 | 4,622 | FOOT | $1.71 | $1.40 | |
| 2 | 40600290 | BIT MATLS TACK CT | 40,360 | POUND | $0.0100 | $0.0100 | |
| 3 | 40600370 | LONG JOINT SEALANT | 18,457 | FOOT | $2.84 | $3.00 | |
| 4 | 40600405 | MATL TRANSFER DEVICE | 9,603 | TON | $3.09 | $1.70 | |
| 5 | 40600982 | HMA SURF REM BUTT JT | 1,844 | SQ YD | $9.66 | $5.00 | |
| 6 | 40600990 | TEMPORARY RAMP | 790 | SQ YD | $17.41 | $15.00 | |
| 7 | 40603085 | HMA BC IL-19.0 N70 | 5,785 | TON | $85.37 | $97.00 | |
| 8 | 40604062 | HMA SC IL-9.5 D N70 | 3,818 | TON | $100.43 | $107.00 | |
| 9 | 40800050 | INCIDENTAL HMA SURF | 348 | TON | $172.35 | $265.00 | |
| 10 | 44000155 | HMA SURF REM 1 1/2 | 49,251 | SQ YD | $1.66 | $1.60 | |
| 11 | 44000156 | HMA SURF REM 1 3/4 | 101 | SQ YD | $13.55 | $2.00 | |
| 12 | 44000164 | HMA SURF REM 3 3/4 | 9,040 | SQ YD | $5.36 | $3.70 | |
| 13 | 44000200 | DRIVE PAVEMENT REM | 17 | SQ YD | $210.13 | $200.00 | |
| 14 | 44000400 | GUTTER REM | 45 | FOOT | $79.38 | $75.00 | |
| 15 | 44201427 | CL C PATCH T2 16 | 2,128 | SQ YD | $200.00 | $225.00 | |
| 16 | 44201431 | CL C PATCH T3 16 | 400 | SQ YD | $196.00 | $220.00 | |
| 17 | 44201433 | CL C PATCH T4 16 | 601 | SQ YD | $193.00 | $215.00 | |
| 18 | 44213202 | TIE BARS 1 | 12 | EACH | $0.0100 | $10.00 | |
| 19 | 48102100 | AGG WEDGE SHLD TYPE B | 646 | TON | $45.31 | $65.00 | |
| 20 | 48203100 | HMA SHOULDERS | 2,749 | TON | $89.62 | $115.00 | |
| 21 | 60600095 | CLASS SI CONC OUTLET | 7 | CU YD | $874.75 | $2,000.00 | |
| 22 | 64200108 | SHOULDER RUM STRIP 8 | 28,374 | FOOT | $0.2100 | $0.3500 | |
| 23 | 67000400 | ENGR FIELD OFFICE A | 4 | CAL MO | $2,200.00 | $1,750.00 | |
| 24 | 67100100 | MOBILIZATION | 1 | L SUM | $134,189.66 | $155,000.00 | |
| 25 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $48,583.39 | $17,500.00 | |
| 26 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $0.0100 | $5,000.00 | |
| 27 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $44,711.61 | $12,500.00 | |
| 28 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $40.50 | $110.00 | |
| 29 | 70300100 | SHORT TERM PAVT MKING | 5,034 | FOOT | $1.69 | $3.00 | |
| 30 | 70300150 | SHRT TRM PAVT MK REM | 2,517 | SQ FT | $0.0100 | $1.00 | |
| 31 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 47,649 | FOOT | $0.0100 | $0.0100 | |
| 32 | 78001110 | PAINT PVT MK LINE 4 | 47,649 | FOOT | $0.1500 | $0.1400 | |
| 33 | 78100100 | RAISED REFL PAVT MKR | 237 | EACH | $38.79 | $36.00 | |
| 34 | 78300200 | RAISED REF PVT MK REM | 237 | EACH | $12.18 | $14.50 | |
| 35 | 78300201 | PVT MKG REM GRINDING | 15,884 | SQ FT | $0.0100 | $0.0100 |