9RS-4
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $2,299,898 | ||
| 2 | Samron Midwest Contracting, Inc. | $2,405,008 | +4.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | 40600290 | BIT MATLS TACK CT | 68,715 | POUND | $1.10 | $0.0100 | |
| 2 | 40600370 | LONG JOINT SEALANT | 30,169 | FOOT | $2.62 | $2.80 | |
| 3 | 40600405 | MATL TRANSFER DEVICE | 16,499 | TON | $4.05 | $1.75 | |
| 4 | 40600982 | HMA SURF REM BUTT JT | 1,851 | SQ YD | $8.99 | $9.00 | |
| 5 | 40600990 | TEMPORARY RAMP | 444 | SQ YD | $15.92 | $15.00 | |
| 6 | 40602970 | HMA BC IL-9.5FG N70 | 5,515 | TON | $84.26 | $89.00 | |
| 7 | 40604052 | HMA SC IL-9.5 C N70 | 6,617 | TON | $83.87 | $85.00 | |
| 8 | 40800050 | INCIDENTAL HMA SURF | 69 | TON | $263.96 | $525.00 | |
| 9 | 44000151 | HMA SURF REM 1/2 | 64,236 | SQ YD | $0.8000 | $1.15 | |
| 10 | 44000155 | HMA SURF REM 1 1/2 | 79,068 | SQ YD | $0.8600 | $1.50 | |
| 11 | 44201373 | CL C PATCH T1 12 | 4 | SQ YD | $185.00 | $215.00 | |
| 12 | 44201377 | CL C PATCH T2 12 | 823 | SQ YD | $178.00 | $210.00 | |
| 13 | 44201381 | CL C PATCH T3 12 | 16 | SQ YD | $175.00 | $205.00 | |
| 14 | 44201383 | CL C PATCH T4 12 | 32 | SQ YD | $172.00 | $200.00 | |
| 15 | 48102100 | AGG WEDGE SHLD TYPE B | 640 | TON | $34.37 | $55.00 | |
| 16 | 48203100 | HMA SHOULDERS | 6,235 | TON | $78.75 | $85.00 | |
| 17 | 67100100 | MOBILIZATION | 1 | L SUM | $112,128.79 | $145,000.00 | |
| 18 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $54,441.12 | $20,000.00 | |
| 19 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $23,468.28 | $11,500.00 | |
| 20 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $39.38 | $105.00 | |
| 21 | 70300100 | SHORT TERM PAVT MKING | 9,082 | FOOT | $1.40 | $2.30 | |
| 22 | 70300150 | SHRT TRM PAVT MK REM | 3,027 | SQ FT | $0.0100 | $3.25 | |
| 23 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 73 | SQ FT | $0.0100 | $0.0100 | |
| 24 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 67,530 | FOOT | $0.0100 | $0.0100 | |
| 25 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 400 | FOOT | $0.0100 | $0.0100 | |
| 26 | 78001100 | PT PVT MK LTRS & SYMB | 73 | SQ FT | $3.15 | $3.00 | |
| 27 | 78001110 | PAINT PVT MK LINE 4 | 67,530 | FOOT | $0.1300 | $0.1300 | |
| 28 | 78001150 | PAINT PVT MK LINE 12 | 400 | FOOT | $0.4700 | $0.4700 | |
| 29 | 78100100 | RAISED REFL PAVT MKR | 331 | EACH | $37.58 | $36.00 | |
| 30 | 78300200 | RAISED REF PVT MK REM | 331 | EACH | $7.60 | $15.00 | |
| 31 | 78300201 | PVT MKG REM GRINDING | 21,866 | SQ FT | $0.0100 | $0.0100 |