124RS-3, 125RS-4
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $2,986,792 | ||
| 2 | Samron Midwest Contracting, Inc. | $3,164,991 | +6.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | Z0034105 | MATL TRANSFER DEVICE | 16,543 | TON | $2.68 | $1.40 | |
| 2 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | |
| 3 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 4 | 40600290 | BIT MATLS TACK CT | 73,133 | POUND | $0.0100 | $0.0100 | |
| 5 | 40600370 | LONG JOINT SEALANT | 37,143 | FOOT | $2.57 | $2.65 | |
| 6 | 40600982 | HMA SURF REM BUTT JT | 1,072 | SQ YD | $14.74 | $15.00 | |
| 7 | 40600990 | TEMPORARY RAMP | 426 | SQ YD | $70.17 | $25.00 | |
| 8 | 40602970 | HMA BC IL-9.5FG N70 | 7,535 | TON | $84.64 | $90.00 | |
| 9 | 40604062 | HMA SC IL-9.5 D N70 | 9,008 | TON | $92.16 | $92.00 | |
| 10 | 40800050 | INCIDENTAL HMA SURF | 171 | TON | $220.69 | $400.00 | |
| 11 | 44000155 | HMA SURF REM 1 1/2 | 84,481 | SQ YD | $1.22 | $1.25 | |
| 12 | 44000160 | HMA SURF REM 2 3/4 | 23,178 | SQ YD | $2.21 | $2.70 | |
| 13 | 44201403 | CL C PATCH T2 14 | 2,568 | SQ YD | $155.00 | $200.00 | |
| 14 | 44201407 | CL C PATCH T3 14 | 437 | SQ YD | $151.00 | $190.00 | |
| 15 | 44201409 | CL C PATCH T4 14 | 1,780 | SQ YD | $149.00 | $180.00 | |
| 16 | 48102100 | AGG WEDGE SHLD TYPE B | 1,376 | TON | $50.37 | $51.00 | |
| 17 | 48203100 | HMA SHOULDERS | 77 | TON | $120.95 | $92.00 | |
| 18 | 63500310 | REM & REIN DELINEATOR | 6 | EACH | $105.75 | $75.00 | |
| 19 | 67000400 | ENGR FIELD OFFICE A | 5 | CAL MO | $1,900.00 | $1,450.00 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $174,612.98 | $185,000.00 | |
| 21 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $44,455.41 | $5,000.00 | |
| 22 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $47,411.59 | $5,000.00 | |
| 23 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $0.0100 | $2,500.00 | |
| 24 | 70107025 | CHANGEABLE MESSAGE SN | 42 | CAL DA | $66.76 | $120.00 | |
| 25 | 70300100 | SHORT TERM PAVT MKING | 12,079 | FOOT | $0.4800 | $1.40 | |
| 26 | 70300150 | SHRT TRM PAVT MK REM | 1,342 | SQ FT | $3.27 | $3.25 | |
| 27 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 91,610 | FOOT | $0.0100 | $0.0100 | |
| 28 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 54 | FOOT | $0.0100 | $0.0100 | |
| 29 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 185 | FOOT | $0.0100 | $0.0100 | |
| 30 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 58 | FOOT | $0.0100 | $0.0100 | |
| 31 | 78001110 | PAINT PVT MK LINE 4 | 91,610 | FOOT | $0.1400 | $0.1400 | |
| 32 | 78001130 | PAINT PVT MK LINE 6 | 54 | FOOT | $0.2100 | $0.2100 | |
| 33 | 78001150 | PAINT PVT MK LINE 12 | 185 | FOOT | $0.4100 | $0.4400 | |
| 34 | 78001180 | PAINT PVT MK LINE 24 | 58 | FOOT | $3.16 | $3.15 | |
| 35 | 78100100 | RAISED REFL PAVT MKR | 484 | EACH | $39.57 | $39.00 | |
| 36 | 78300200 | RAISED REF PVT MK REM | 484 | EACH | $3.63 | $11.50 | |
| 37 | 78300201 | PVT MKG REM GRINDING | 30,865 | SQ FT | $0.0100 | $0.0100 |