D9 TRAFFIC SIGNAL 2024-1
- Let date
- Friday, January 17, 2025
- Contract
- 78998 · job page
- District
- District 9
- County
- Jackson
- Highway
- Limits
- 16.5 miles of fiber optic cable installation and signal modification on IL 13 in Carbondale from Striegel Road west to IL 127/149 and on IL13/127/149 in Murphysboro from IL 13/127/149 north to Industrial Park Road.
- Classification
- ·
- Project number
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Gerstner Electric, Inc. Low bidder | $1,954,250 | ||
| 2 | Brown Electric, Inc. | $2,207,503 | +13.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Gerstner Electr… | #2 Brown Electric,… |
|---|---|---|---|---|---|---|---|
| 1 | XP000179 | GRUND ROD 8' COPPER | 50 | EACH | $205.00 | $212.00 | |
| 2 | X0322921 | INSTALL COMM CABINET | 1 | EACH | $2,885.00 | $13,125.00 | |
| 3 | X0328016 | TRAF CNT DATA COL SYS | 1 | EACH | $84,855.00 | $92,937.25 | |
| 4 | X1400102 | OUTDR RTD NTWRK CABLE | 120 | FOOT | $2.25 | $5.30 | |
| 5 | X1400307 | HQ FO CONNECTIVITY | 1 | L SUM | $5,705.00 | $598.75 | |
| 6 | X1400499 | SIG PERFORM MEAS SERV | 1 | EACH | $118,410.00 | $121,988.75 | |
| 7 | X1400500 | COMM VAULT 24X36 | 25 | EACH | $3,895.00 | $4,953.00 | |
| 8 | X1400501 | COMM VAULT 48X48 | 6 | EACH | $6,000.00 | $8,987.18 | |
| 9 | X1700066 | POTHOLING | 200 | EACH | $500.00 | $90.00 | |
| 10 | X7340100 | CONC FOUNDATION GR MT | 1.5 | CU YD | $3,780.00 | $650.00 | |
| 11 | X8100105 | CONDUIT SPLICE | 3 | EACH | $265.00 | $480.00 | |
| 12 | X8710010 | FIBER LAYOUT | 1 | L SUM | $9,655.00 | $22,260.00 | |
| 13 | X8710030 | FIB OPT CBL 48F SM | 38,525 | FOOT | $2.20 | $5.10 | |
| 14 | X8710036 | FIB OPT CBL 12F SM | 1,275 | FOOT | $2.65 | $3.05 | |
| 15 | X8710094 | FO INTERCT CENTER 48P | 3 | EACH | $3,765.00 | $2,873.85 | |
| 16 | X8710101 | ETHERNET MNG SWITCH | 1 | EACH | $9,855.00 | $7,726.80 | |
| 17 | X8710103 | ETHERNET SWITCH | 6 | EACH | $3,575.00 | $3,062.80 | |
| 18 | X8710304 | FOC SPLICE - LATERAL | 7 | EACH | $6,310.00 | $4,279.00 | |
| 19 | X8710306 | FOC SPLICE - MAINLINE | 4 | EACH | $6,985.00 | $6,875.00 | |
| 20 | X8710318 | FIB OPT UTILIT MARKER | 91 | EACH | $245.00 | $236.00 | |
| 21 | X8891301 | VID & RAD HYB DET SYS | 7 | EACH | $49,550.00 | $54,581.00 | |
| 22 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $5,000.00 | $2,000.00 | |
| 23 | 67100100 | MOBILIZATION | 1 | L SUM | $150,002.45 | $20,000.00 | |
| 24 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $5,470.00 | $7,200.00 | |
| 25 | 70100320 | TRAF CONT-PROT 701422 | 1 | L SUM | $5,470.00 | $100.00 | |
| 26 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $5,470.00 | $3,500.00 | |
| 27 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $5,470.00 | $8,800.00 | |
| 28 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $5,470.00 | $9,200.00 | |
| 29 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $5,470.00 | $1,500.00 | |
| 30 | 80300100 | LOCATE UNDERGR CABLE | 2,000 | FOOT | $1.45 | $3.96 | |
| 31 | 80500010 | SERV INSTALL GRND MT | 3 | EACH | $12,205.00 | $12,987.00 | |
| 32 | 81028350 | UNDRGRD C PVC 2 | 408 | FOOT | $19.30 | $41.76 | |
| 33 | 81028390 | UNDRGRD C PVC 4 | 23 | FOOT | $69.00 | $60.72 | |
| 34 | 81028740 | UNDRGRD C CNC 1 1/2 | 36,294 | FOOT | $8.00 | $14.97 | |
| 35 | 81702450 | EC C XLP USE 3-1C 10 | 166 | FOOT | $5.75 | $5.25 | |
| 36 | 85700300 | FAC T5 CAB | 7 | EACH | $30,350.00 | $32,130.00 | |
| 37 | 86200300 | UNINTER POWER SUP EXT | 5 | EACH | $14,045.00 | $10,076.25 | |
| 38 | 87301815 | ELCBL C SERV 6 3C | 166 | FOOT | $8.55 | $6.75 | |
| 39 | 87301900 | ELCBL C EGRDC 6 1C | 5,116 | FOOT | $2.60 | $5.48 | |
| 40 | 87800200 | CONC FDN TY D | 3 | FOOT | $2,470.00 | $1,265.00 | |
| 41 | 87900100 | DRILL EX FOUNDATION | 14 | EACH | $710.00 | $1,420.00 | |
| 42 | 89501250 | RELOC EX TS EQUIP | 4 | EACH | $1,045.00 | $1,850.00 | |
| 43 | 89502375 | REMOV EX TS EQUIP | 8 | EACH | $1,045.00 | $3,972.00 |