6R(RS-2)
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $1,930,021 | ||
| 2 | E. T. Simonds Construction Company | $2,076,114 | +7.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 E. T. Simonds C… |
|---|---|---|---|---|---|---|---|
| 1 | X4240430 | PC CONC SIDEWALK 5 SP | 949 | SQ FT | $33.50 | $13.75 | |
| 2 | X4401198 | HMA SURF REM VAR DP | 2,208 | SQ YD | $4.25 | $3.64 | |
| 3 | Z0034105 | MATL TRANSFER DEVICE | 10,216 | TON | $1.50 | $3.36 | |
| 4 | 40600290 | BIT MATLS TACK CT | 47,223 | POUND | $0.0100 | $0.0100 | |
| 5 | 40600370 | LONG JOINT SEALANT | 24,447 | FOOT | $3.25 | $2.96 | |
| 6 | 40600982 | HMA SURF REM BUTT JT | 1,412 | SQ YD | $2.25 | $6.81 | |
| 7 | 40600990 | TEMPORARY RAMP | 110 | SQ YD | $20.00 | $37.16 | |
| 8 | 40602970 | HMA BC IL-9.5FG N70 | 4,642 | TON | $86.00 | $104.58 | |
| 9 | 40604062 | HMA SC IL-9.5 D N70 | 5,574 | TON | $90.00 | $108.73 | |
| 10 | 40800050 | INCIDENTAL HMA SURF | 274 | TON | $200.00 | $169.80 | |
| 11 | 42001300 | PROTECTIVE COAT | 39 | SQ YD | $1.50 | $0.7100 | |
| 12 | 42300300 | PCC DRIVEWAY PAVT 7 | 8 | SQ YD | $85.00 | $375.97 | |
| 13 | 42400800 | DETECTABLE WARNINGS | 71 | SQ FT | $35.00 | $24.85 | |
| 14 | 44000100 | PAVEMENT REM | 9 | SQ YD | $50.00 | $266.55 | |
| 15 | 44000152 | HMA SURF REM 3/4 | 582 | SQ YD | $3.00 | $6.72 | |
| 16 | 44000155 | HMA SURF REM 1 1/2 | 63,277 | SQ YD | $2.35 | $2.05 | |
| 17 | 44000159 | HMA SURF REM 2 1/2 | 3,921 | SQ YD | $3.00 | $3.06 | |
| 18 | 44000160 | HMA SURF REM 2 3/4 | 1,133 | SQ YD | $6.00 | $4.79 | |
| 19 | 44000500 | COMB CURB GUTTER REM | 173 | FOOT | $15.00 | $27.73 | |
| 20 | 44000600 | SIDEWALK REM | 986 | SQ FT | $10.00 | $4.87 | |
| 21 | 44201389 | CL C PATCH T2 13 | 1,262 | SQ YD | $235.00 | $166.00 | |
| 22 | 44201394 | CL C PATCH T3 13 | 128 | SQ YD | $230.00 | $160.00 | |
| 23 | 44201396 | CL C PATCH T4 13 | 27 | SQ YD | $225.00 | $155.00 | |
| 24 | 48102100 | AGG WEDGE SHLD TYPE B | 696 | TON | $45.00 | $57.97 | |
| 25 | 48203100 | HMA SHOULDERS | 301 | TON | $120.00 | $128.79 | |
| 26 | 60255500 | MAN ADJUST | 3 | EACH | $450.00 | $259.72 | |
| 27 | 60603800 | COMB CC&G TB6.12 | 175 | FOOT | $77.00 | $65.32 | |
| 28 | 67100100 | MOBILIZATION | 1 | L SUM | $114,000.00 | $154,653.46 | |
| 29 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $8,000.00 | $0.0100 | |
| 30 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $15,345.00 | $43,287.56 | |
| 31 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $5,000.00 | $19,879.31 | |
| 32 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $0.0100 | $2,993.33 | |
| 33 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1,000.00 | $500.00 | |
| 34 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $150.00 | $84.95 | |
| 35 | 70300100 | SHORT TERM PAVT MKING | 7,410 | FOOT | $1.00 | $1.07 | |
| 36 | 70300150 | SHRT TRM PAVT MK REM | 2,470 | SQ FT | $1.50 | $0.0100 | |
| 37 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 128 | SQ FT | $0.0100 | $0.0100 | |
| 38 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 70,452 | FOOT | $0.0100 | $0.0100 | |
| 39 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 76 | FOOT | $0.0100 | $0.0100 | |
| 40 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 55 | FOOT | $0.0100 | $0.0100 | |
| 41 | 78000100 | THPL PVT MK LTR & SYM | 128 | SQ FT | $5.00 | $4.86 | |
| 42 | 78000200 | THPL PVT MK LINE 4 | 70,452 | FOOT | $0.8000 | $0.7800 | |
| 43 | 78000400 | THPL PVT MK LINE 6 | 76 | FOOT | $1.25 | $1.19 | |
| 44 | 78000600 | THPL PVT MK LINE 12 | 55 | FOOT | $2.50 | $2.43 | |
| 45 | 78100100 | RAISED REFL PAVT MKR | 309 | EACH | $40.00 | $39.23 | |
| 46 | 78300200 | RAISED REF PVT MK REM | 309 | EACH | $12.50 | $7.36 | |
| 47 | 78300201 | PAVMT MRKG REM GRIND | 23,705 | SQ FT | $0.0100 | $0.0100 |