BRIDGE REPAIR 2022-2
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $3,085,776 | ||
| 2 | Samron Midwest Contracting, Inc. | $3,155,270 | +2.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | Z0034390 | MODULAR EXPAN JT 6 | 612 | FOOT | $2,189.30 | $1,650.00 | |
| 2 | 50102400 | CONC REM | 133.1 | CU YD | $3,089.97 | $4,000.00 | |
| 3 | 50300255 | CONC SUP-STR | 144.7 | CU YD | $3,605.04 | $3,500.00 | |
| 4 | 50300300 | PROTECTIVE COAT | 3,520 | SQ YD | $0.9600 | $2.00 | |
| 5 | 50800205 | REINF BARS, EPOXY CTD | 21,080 | POUND | $2.85 | $6.00 | |
| 6 | 50800515 | BAR SPLICERS | 280 | EACH | $36.32 | $50.00 | |
| 7 | 50800530 | MECHANICAL SPLICERS | 2,586 | EACH | $63.77 | $65.00 | |
| 8 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,200.00 | $1,500.00 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $150,503.09 | $188,000.00 | |
| 10 | 70100207 | TRAF CONT-PROT 701402 | 2 | EACH | $80,465.65 | $137,000.00 | |
| 11 | 70100420 | TRAF CONT-PROT 701411 | 1 | EACH | $9,515.82 | $5,000.00 | |
| 12 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $40,037.70 | $125,000.00 | |
| 13 | 70107025 | CHANGEABLE MESSAGE SN | 42 | CAL DA | $65.48 | $150.00 | |
| 14 | 70300150 | SHRT TRM PAVT MK REM | 5,012 | SQ FT | $0.0100 | $0.0100 | |
| 15 | 70307120 | TEMP PVT MK L4 T4 TAPE | 15,035 | FOOT | $0.0100 | $0.0100 | |
| 16 | 70400100 | TEMP CONC BARRIER | 2,025 | FOOT | $28.42 | $50.00 | |
| 17 | 70400200 | REL TEMP CONC BARRIER | 7,138 | FOOT | $11.31 | $5.00 | |
| 18 | 70600260 | IMP ATTN TEMP FRN TL3 | 2 | EACH | $9,764.89 | $4,250.00 | |
| 19 | 70600332 | IMP ATTN REL FRN TL3 | 10 | EACH | $1,194.93 | $850.00 | |
| 20 | 78009006 | MOD URETH PM LINE 6 | 15,035 | FOOT | $1.21 | $1.30 | |
| 21 | 78300201 | PAVMT MRKG REM GRIND | 5,012 | SQ FT | $1.87 | $2.00 |