D9 PATCH 2021-1
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kinney Contractors, Inc. Low bidder | $118,436 | ||
| 2 | E. T. Simonds Construction Company | $128,637 | +8.6% | |
| 3 | Samron Midwest Contracting, Inc. | $129,702 | +9.5% | |
| 4 | G. M. Sipes Construction, Inc. | $150,011 | +26.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kinney Contract… | #2 E. T. Simonds C… | #3 Samron Midwest … | #4 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 44200525 | CL A PATCH T1 8 | 8 | SQ YD | $200.00 | $210.00 | $200.00 | $300.00 | |
| 2 | 44200529 | CL A PATCH T2 8 | 22 | SQ YD | $175.00 | $180.00 | $185.00 | $250.00 | |
| 3 | 44200533 | CL A PATCH T3 8 | 17 | SQ YD | $165.00 | $160.00 | $175.00 | $250.00 | |
| 4 | 44200535 | CL A PATCH T4 8 | 399 | SQ YD | $148.00 | $150.00 | $160.00 | $200.00 | |
| 5 | 44213000 | PATCH REINFORCEMENT | 446 | SQ YD | $45.00 | $53.46 | $55.00 | $40.00 | |
| 6 | 44213200 | SAW CUTS | 1,372 | FOOT | $1.00 | $6.85 | $9.50 | $7.95 | |
| 7 | 44213204 | TIE BARS 3/4 | 379 | EACH | $13.00 | $17.24 | $18.00 | $3.50 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $10,000.00 | $6,600.58 | $3,200.00 | $7,000.00 | |
| 9 | 70100320 | TRAF CONT-PROT 701422 | 1 | L SUM | $8,300.00 | $10,874.66 | $5,500.00 | $14,000.00 | |
| 10 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1,000.00 | $0.00 | $1.00 | $5,000.00 | |
| 11 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $125.00 | $35.71 | $85.00 | $1.00 | |
| 12 | 88600100 | DET LOOP T1 | 70 | FOOT | $28.00 | $31.09 | $25.00 | $27.98 |