D9 PATCH 2020-4
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $608,452 | ||
| 2 | DMS Contracting, Inc. | $625,846 | +2.9% | |
| 3 | E. T. Simonds Construction Company | $670,842 | +10.3% | |
| 4 | Sierra Bravo Contractors, LLC | $780,514 | +28.3% | |
| 5 | Southern Illinois Asphalt Co., Inc. | $804,144 | +32.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 DMS Contracting… | #3 E. T. Simonds C… | #4 Sierra Bravo Co… | #5 Southern Illino… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X7030005 | TEMP PAVT MKING REMOV | 4,517 | SQ FT | $1.95 | $0.0100 | $0.00 | $0.0100 | $0.00 | |
| 2 | 31100910 | SUB GRAN MAT A 12 | 4,217 | SQ YD | $19.00 | $16.90 | $18.04 | $27.54 | $31.11 | |
| 3 | 31102100 | SUB GRAN MAT C 4 | 1,080 | SQ YD | $5.00 | $8.40 | $11.62 | $15.69 | $26.70 | |
| 4 | 31200100 | STAB SUBBASE 4 | 3,117 | SQ YD | $23.00 | $31.85 | $30.47 | $33.31 | $26.50 | |
| 5 | 42000401 | PCC PVT 9 JOINTED | 2,934 | SQ YD | $47.50 | $49.60 | $57.46 | $66.94 | $60.30 | |
| 6 | 42001300 | PROTECTIVE COAT | 4,156 | SQ YD | $0.7500 | $0.0100 | $0.00 | $0.9400 | $1.69 | |
| 7 | 44000100 | PAVEMENT REM | 2,934 | SQ YD | $8.00 | $10.05 | $16.54 | $19.81 | $24.27 | |
| 8 | 44000500 | COMB CURB GUTTER REM | 1,100 | FOOT | $5.00 | $3.40 | $7.67 | $10.03 | $13.92 | |
| 9 | 44004250 | PAVED SHLD REMOVAL | 1,223 | SQ YD | $8.00 | $3.75 | $17.47 | $22.93 | $13.54 | |
| 10 | 44201297 | DOWEL BARS 1 | 146 | EACH | $15.00 | $14.15 | $19.49 | $11.44 | $64.92 | |
| 11 | 44213204 | TIE BARS 3/4 | 110 | EACH | $15.00 | $15.35 | $23.54 | $10.40 | $57.77 | |
| 12 | 48300400 | PCC SHOULDERS 9 | 1,223 | SQ YD | $46.00 | $52.50 | $68.53 | $69.19 | $70.72 | |
| 13 | 60605000 | COMB CC&G TB6.24 | 1,100 | FOOT | $28.00 | $9.00 | $38.32 | $38.69 | $39.54 | |
| 14 | 67100100 | MOBILIZATION | 1 | L SUM | $42,334.00 | $54,000.00 | $33,487.53 | $46,277.00 | $51,225.69 | |
| 15 | 70100400 | TRAF CONT-PROT 701431 | 1 | EACH | $67,000.00 | $73,000.00 | $43,644.93 | $38,616.85 | $47,475.13 | |
| 16 | 70107025 | CHANGEABLE MESSAGE SN | 56 | CAL DA | $100.00 | $110.00 | $75.78 | $104.00 | $106.30 | |
| 17 | 70300100 | SHORT TERM PAVT MKING | 798 | FOOT | $1.00 | $11.10 | $1.05 | $2.64 | $2.79 | |
| 18 | 70300150 | SHRT TRM PAVT MK REM | 266 | SQ FT | $2.50 | $0.0100 | $6.14 | $6.94 | $0.00 | |
| 19 | 70300210 | TEMP PVT MK LTR & SYM | 36 | SQ FT | $20.00 | $0.0100 | $0.00 | $0.0100 | $0.00 | |
| 20 | 70300220 | TEMP PVT MK LINE 4 | 13,128 | FOOT | $0.8000 | $0.0100 | $0.00 | $0.0100 | $0.00 | |
| 21 | 70300260 | TEMP PVT MK LINE 12 | 98 | FOOT | $6.50 | $0.0100 | $0.00 | $0.0100 | $0.00 | |
| 22 | 78009000 | MOD URETH PM LTR-SYM | 36 | SQ FT | $39.00 | $40.00 | $20.60 | $5.20 | $5.32 | |
| 23 | 78009004 | MOD URETH PM LINE 4 | 13,128 | FOOT | $3.00 | $3.05 | $1.70 | $1.57 | $1.61 | |
| 24 | 78009012 | MOD URETH PM LINE 12 | 98 | FOOT | $12.75 | $13.35 | $20.60 | $4.68 | $4.78 |