3SLP-2
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $90,396 | ||
| 2 | Samron Midwest Contracting, Inc. | $111,625 | +23.5% | |
| 3 | Sierra Bravo Contractors, LLC | $120,359 | +33.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … | #3 Sierra Bravo Co… |
|---|---|---|---|---|---|---|---|---|
| 1 | Z0046304 | P UNDR FOR STRUCT 4 | 95 | FOOT | $4.70 | $25.00 | $12.94 | |
| 2 | 20200100 | EARTH EXCAVATION | 76 | CU YD | $23.93 | $30.00 | $37.45 | |
| 3 | 44004250 | PAVED SHLD REMOVAL | 70 | SQ YD | $33.37 | $25.00 | $40.66 | |
| 4 | 48203029 | HMA SHOULDERS 8 | 169 | SQ YD | $78.20 | $75.00 | $117.30 | |
| 5 | 52200015 | PERM SHT PILING | 1,500 | SQ FT | $19.81 | $33.00 | $32.25 | |
| 6 | 58600101 | GRANULAR BACKFILL STR | 25 | CU YD | $166.66 | $125.00 | $96.22 | |
| 7 | 63301210 | REM RE-E SPBGR TY A | 187 | FOOT | $60.50 | $60.00 | $61.60 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $8,619.83 | $10,000.00 | $6,812.76 | |
| 9 | 70100100 | TRAF CONT-PROT 701316 | 1 | EACH | $6,075.61 | $8,000.00 | $5,376.54 | |
| 10 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $6,511.49 | $5,000.00 | $7,243.59 | |
| 11 | 70106700 | TEMP RUMBLE STRIPS | 6 | EACH | $842.81 | $600.00 | $1,220.87 | |
| 12 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $40.00 | $75.00 | $162.70 |