(101,12-1)RS-6
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $1,219,324 | ||
| 2 | Samron Midwest Contracting, Inc. | $1,249,325 | +2.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | X7030005 | TEMP PAVT MKING REMOV | 7,027 | SQ FT | $0.00 | $0.00 | |
| 2 | Z0033700 | LONG JOINT SEALANT | 5,260 | FOOT | $3.32 | $3.00 | |
| 3 | Z0034105 | MATL TRANSFER DEVICE | 3,406.3 | TON | $3.09 | $3.00 | |
| 4 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | |
| 5 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 6 | 40600290 | BIT MATLS TACK CT | 14,930 | POUND | $0.00 | $0.0100 | |
| 7 | 40600990 | TEMPORARY RAMP | 90 | SQ YD | $241.43 | $25.00 | |
| 8 | 40603219 | P HMA BC IL-9.5FG N90 | 1,549 | TON | $90.61 | $106.00 | |
| 9 | 40604164 | P HMA SC IL-9.5 D N90 | 1,858 | TON | $91.74 | $106.00 | |
| 10 | 42001300 | PROTECTIVE COAT | 192 | SQ YD | $0.00 | $0.0100 | |
| 11 | 42400200 | PC CONC SIDEWALK 5 | 8,029 | SQ FT | $10.17 | $8.00 | |
| 12 | 42400800 | DETECTABLE WARNINGS | 1,148 | SQ FT | $17.77 | $25.00 | |
| 13 | 44000100 | PAVEMENT REM | 27 | SQ YD | $17.33 | $50.00 | |
| 14 | 44000160 | HMA SURF REM 2 3/4 | 22,119 | SQ YD | $3.24 | $3.00 | |
| 15 | 44000500 | COMB CURB GUTTER REM | 1,089 | FOOT | $5.61 | $10.00 | |
| 16 | 44000600 | SIDEWALK REM | 8,029 | SQ FT | $4.53 | $2.50 | |
| 17 | 44200050 | WELDED WIRE REINF | 2,803 | SQ YD | $9.58 | $6.00 | |
| 18 | 44201373 | CL C PATCH T1 12 | 79 | SQ YD | $170.00 | $160.00 | |
| 19 | 44201377 | CL C PATCH T2 12 | 548 | SQ YD | $115.00 | $150.00 | |
| 20 | 44201381 | CL C PATCH T3 12 | 556 | SQ YD | $112.00 | $140.00 | |
| 21 | 44201383 | CL C PATCH T4 12 | 2,247 | SQ YD | $110.00 | $130.00 | |
| 22 | 44213204 | TIE BARS 3/4 | 2,059 | EACH | $20.33 | $0.0100 | |
| 23 | 60600605 | CONC CURB TB | 64 | FOOT | $21.63 | $40.00 | |
| 24 | 60603800 | COMB CC&G TB6.12 | 1,089 | FOOT | $22.45 | $40.00 | |
| 25 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $1,800.00 | $500.00 | |
| 26 | 67100100 | MOBILIZATION | 1 | L SUM | $53,068.46 | $63,500.00 | |
| 27 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $61,160.00 | $5,000.00 | |
| 28 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $0.00 | $25,000.00 | |
| 29 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $2,095.80 | $2,500.00 | |
| 30 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $52.50 | $80.00 | |
| 31 | 70300100 | SHORT TERM PAVT MKING | 1,670 | FOOT | $1.25 | $1.00 | |
| 32 | 70300150 | SHRT TRM PAVT MK REM | 557 | SQ FT | $0.00 | $1.00 | |
| 33 | 70300210 | TEMP PVT MK LTR & SYM | 413.6 | SQ FT | $0.00 | $0.00 | |
| 34 | 70300220 | TEMP PVT MK LINE 4 | 11,228 | FOOT | $0.00 | $0.00 | |
| 35 | 70300260 | TEMP PVT MK LINE 12 | 2,562 | FOOT | $0.00 | $0.00 | |
| 36 | 70300280 | TEMP PVT MK LINE 24 | 154 | FOOT | $0.00 | $0.00 | |
| 37 | 78000100 | THPL PVT MK LTR & SYM | 413.6 | SQ FT | $4.64 | $5.00 | |
| 38 | 78000200 | THPL PVT MK LINE 4 | 11,228 | FOOT | $1.03 | $1.00 | |
| 39 | 78000600 | THPL PVT MK LINE 12 | 2,562 | FOOT | $3.18 | $3.25 | |
| 40 | 78000650 | THPL PVT MK LINE 24 | 154 | FOOT | $4.38 | $4.50 | |
| 41 | 78100100 | RAISED REFL PAVT MKR | 150 | EACH | $36.87 | $40.00 | |
| 42 | 78300200 | RAISED REF PVT MK REM | 150 | EACH | $4.50 | $15.00 |