22SLP-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sierra Bravo Contractors, LLC Low bidder | $3,033,362 | ||
| 2 | E. T. Simonds Construction Company | $3,378,526 | +11.4% | |
| 3 | Samron Midwest Contracting, Inc. | $3,889,902 | +28.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sierra Bravo Co… | #2 E. T. Simonds C… | #3 Samron Midwest … |
|---|---|---|---|---|---|---|---|---|
| 1 | X0321809 | PERMANENT GRND ANCHOR | 60 | EACH | $12,898.95 | $9,713.82 | $14,600.00 | |
| 2 | X0800003 | COARSE AGR BACKFIL SP | 2,535 | CU YD | $3.83 | $11.55 | $15.00 | |
| 3 | X1200235 | REMOVE EXIST RIPRAP | 127 | CU YD | $7.58 | $16.56 | $25.00 | |
| 4 | X6063000 | CONC GUTTER TB SPL | 550 | FOOT | $32.18 | $27.67 | $25.00 | |
| 5 | X7010202 | TC-PROT 701321 SPL | 1 | EACH | $26,713.85 | $12,524.67 | $6,000.00 | |
| 6 | Z0046304 | P UNDR FOR STRUCT 4 | 775 | FOOT | $6.28 | $19.28 | $25.00 | |
| 7 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 8 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 9 | 20200100 | EARTH EXCAVATION | 3,831 | CU YD | $5.63 | $16.49 | $22.00 | |
| 10 | 20400800 | FURNISHED EXCAVATION | 850 | CU YD | $19.43 | $23.26 | $10.00 | |
| 11 | 25000210 | SEEDING CL 2A | 0.75 | ACRE | $2,750.00 | $2,750.00 | $2,800.00 | |
| 12 | 25000400 | NITROGEN FERT NUTR | 68 | POUND | $3.30 | $3.30 | $3.15 | |
| 13 | 25000500 | PHOSPHORUS FERT NUTR | 68 | POUND | $3.30 | $3.30 | $3.15 | |
| 14 | 25000600 | POTASSIUM FERT NUTR | 68 | POUND | $3.30 | $3.30 | $3.15 | |
| 15 | 25100115 | MULCH METHOD 2 | 0.75 | ACRE | $1,100.00 | $1,100.00 | $1,100.00 | |
| 16 | 25100630 | EROSION CONTR BLANKET | 1,545 | SQ YD | $2.04 | $2.04 | $2.00 | |
| 17 | 28000250 | TEMP EROS CONTR SEED | 350 | POUND | $2.37 | $2.00 | $2.00 | |
| 18 | 28000400 | PERIMETER EROS BAR | 590 | FOOT | $3.48 | $9.09 | $4.50 | |
| 19 | 28000500 | INLET & PIPE PROTECT | 1 | EACH | $168.89 | $189.04 | $95.00 | |
| 20 | 31100910 | SUB GRAN MAT A 12 | 2,308 | SQ YD | $12.19 | $16.99 | $14.00 | |
| 21 | 31102000 | SUB GRAN MAT C | 53 | CU YD | $99.78 | $99.85 | $65.00 | |
| 22 | 31200100 | STAB SUBBASE 4 | 1,650 | SQ YD | $35.40 | $27.03 | $23.00 | |
| 23 | 40200500 | AGG SURF CSE A 6 | 119 | SQ YD | $25.59 | $20.72 | $14.00 | |
| 24 | 42000411 | PCC PVT 9 1/2 JOINTD | 1,467 | SQ YD | $84.98 | $76.58 | $65.00 | |
| 25 | 44000100 | PAVEMENT REM | 1,778 | SQ YD | $6.83 | $9.98 | $15.00 | |
| 26 | 44000200 | DRIVE PAVEMENT REM | 17 | SQ YD | $20.30 | $25.93 | $8.00 | |
| 27 | 44000400 | GUTTER REM | 589 | FOOT | $4.04 | $4.49 | $3.00 | |
| 28 | 48300410 | PCC SHOULDERS 9 1/2 | 658 | SQ YD | $79.94 | $66.54 | $80.00 | |
| 29 | 50105220 | PIPE CULVERT REMOV | 212 | FOOT | $11.21 | $8.32 | $10.00 | |
| 30 | 50300225 | CONC STRUCT | 61.2 | CU YD | $1,987.25 | $718.17 | $1,835.00 | |
| 31 | 50500405 | F & E STRUCT STEEL | 63,156 | POUND | $1.76 | $5.50 | $3.45 | |
| 32 | 50800205 | REINF BARS, EPOXY CTD | 7,830 | POUND | $1.53 | $1.77 | $2.00 | |
| 33 | 52200105 | FUR SOLDIER PILES WS | 2,651 | FOOT | $74.42 | $135.94 | $105.00 | |
| 34 | 52200200 | DRILL SET SLD PI SOIL | 10,430 | CU FT | $39.91 | $15.40 | $16.00 | |
| 35 | 52200205 | DRILL SET SLD PI ROCK | 2,584 | CU FT | $199.91 | $192.23 | $200.00 | |
| 36 | 52200255 | TREATED TIMBER LAG | 7,772 | SQ FT | $16.08 | $62.86 | $30.00 | |
| 37 | 542D1063 | P CUL CL D 2 18 | 53 | FOOT | $43.43 | $52.50 | $55.00 | |
| 38 | 54262718 | METAL FL END SEC 18" | 2 | EACH | $429.44 | $976.83 | $350.00 | |
| 39 | 54390210 | INSERT CUL LIN 30 | 58 | FOOT | $326.56 | $430.53 | $250.00 | |
| 40 | 59100100 | GEOCOMPOSITE WALL DR | 567 | SQ YD | $22.44 | $83.16 | $35.00 | |
| 41 | 63000001 | SPBGR TY A 6FT POSTS | 725 | FOOT | $24.75 | $33.39 | $25.00 | |
| 42 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $3,685.00 | $4,471.50 | $3,700.00 | |
| 43 | 63200310 | GUARDRAIL REMOV | 152 | FOOT | $15.89 | $16.63 | $5.00 | |
| 44 | 67000400 | ENGR FIELD OFFICE A | 20 | CAL MO | $1,971.06 | $2,000.00 | $1,200.00 | |
| 45 | 67100100 | MOBILIZATION | 1 | L SUM | $171,699.73 | $209,963.74 | $864,000.00 | |
| 46 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $17,325.00 | $18,462.28 | $17,000.00 | |
| 47 | 70106700 | TEMP RUMBLE STRIPS | 6 | EACH | $852.50 | $664.93 | $750.00 | |
| 48 | 70107025 | CHANGEABLE MESSAGE SN | 70 | CAL DA | $78.10 | $43.06 | $70.00 | |
| 49 | 70400100 | TEMP CONC BARRIER | 300 | FOOT | $38.20 | $25.24 | $45.00 | |
| 50 | 70600260 | IMP ATTN TEMP FRN TL3 | 4 | EACH | $8,627.90 | $8,601.24 | $7,500.00 | |
| 51 | 72501000 | TERMINAL MARKER - DA | 2 | EACH | $33.00 | $55.00 | $34.00 | |
| 52 | 78001110 | PAINT PVT MK LINE 4 | 2,200 | FOOT | $2.37 | $2.15 | $2.00 | |
| 53 | 78100100 | RAISED REFL PAVT MKR | 7 | EACH | $127.60 | $116.88 | $120.00 | |
| 54 | 78200005 | GRDRAIL REF TYPE A | 12 | EACH | $11.00 | $11.00 | $11.00 | |
| 55 | 78200011 | BARR WALL REF TYPE C | 48 | EACH | $13.20 | $7.47 | $2.00 |