(91-3)B-2
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $6,837,598 | ||
| 2 | Sierra Bravo Contractors, LLC | $7,842,150 | +14.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Sierra Bravo Co… |
|---|---|---|---|---|---|---|---|
| 1 | X0301993 | REM & REIN C HWL P DR | 3 | EACH | $199.16 | $376.84 | |
| 2 | X0320051 | CROS SONIC LOG A DUCT | 480 | FOOT | $47.17 | $12.47 | |
| 3 | X0320052 | CROS SONIC LOG TEST | 16 | EACH | $825.00 | $1,609.38 | |
| 4 | X0323265 | REMOVE EXIST RIPRAP | 54 | SQ YD | $9.10 | $16.66 | |
| 5 | X0325299 | INLET MODIFICATION | 1 | EACH | $1,695.09 | $981.61 | |
| 6 | X0327980 | PAVMT MRKG REM WTR BL | 13,320 | SQ FT | $1.38 | $2.58 | |
| 7 | X0484300 | MEDIAN INLET BOX REM | 2 | EACH | $349.41 | $678.57 | |
| 8 | X2503100 | MOWING | 16 | UNIT | $93.33 | $209.08 | |
| 9 | X2800500 | INLET PROTECTION SPL | 1 | EACH | $456.96 | $316.29 | |
| 10 | X5030250 | BR DECK GROOVING LONG | 1,998 | SQ YD | $10.35 | $10.01 | |
| 11 | X5420350 | END SECTIONS 18 SPL | 2 | EACH | $768.21 | $402.11 | |
| 12 | X5421550 | MET END SEC 15 SPL | 1 | EACH | $734.93 | $418.48 | |
| 13 | X6020073 | INLETS TA T8G TEMP | 3 | EACH | $1,466.02 | $1,744.62 | |
| 14 | X6024875 | TEMPORARY INLET | 1 | EACH | $1,751.78 | $1,511.84 | |
| 15 | X6330103 | R&R TRB TM T1 SPL TAN | 5 | EACH | $1,870.00 | $1,751.00 | |
| 16 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $282,668.04 | $400,493.66 | |
| 17 | X7030005 | TEMP PAVT MKING REMOV | 13,872 | SQ FT | $1.49 | $1.00 | |
| 18 | X7050169 | TEMP TRBT T1 SPL FLAR | 2 | EACH | $3,630.00 | $5,265.43 | |
| 19 | X7830050 | RAISD REF PM REFL REM | 151 | EACH | $11.56 | $9.01 | |
| 20 | Z0016001 | DECK SLAB REP (FD-T1) | 10 | SQ YD | $526.13 | $1,692.20 | |
| 21 | Z0016002 | DECK SLAB REP (FD-T2) | 40 | SQ YD | $379.89 | $1,061.49 | |
| 22 | Z0029090 | DIAMOND GRIND BR SEC | 2,732 | SQ YD | $8.55 | $16.04 | |
| 23 | Z0046304 | P UNDR FOR STRUCT 4 | 348 | FOOT | $14.90 | $31.91 | |
| 24 | Z0062456 | TEMP PAVEMENT | 3,081 | SQ YD | $64.65 | $70.72 | |
| 25 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | |
| 26 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | |
| 27 | 20100500 | TREE REMOV ACRES | 0.25 | ACRE | $24,402.40 | $25,339.75 | |
| 28 | 20200100 | EARTH EXCAVATION | 8,295 | CU YD | $14.35 | $14.48 | |
| 29 | 20800150 | TRENCH BACKFILL | 99 | CU YD | $70.58 | $47.48 | |
| 30 | 25000210 | SEEDING CL 2A | 4.5 | ACRE | $1,292.50 | $1,210.25 | |
| 31 | 25000350 | SEEDING CL 7 | 4.5 | ACRE | $346.50 | $324.45 | |
| 32 | 25000400 | NITROGEN FERT NUTR | 405 | POUND | $1.27 | $1.18 | |
| 33 | 25000500 | PHOSPHORUS FERT NUTR | 405 | POUND | $1.27 | $1.18 | |
| 34 | 25000600 | POTASSIUM FERT NUTR | 405 | POUND | $1.27 | $1.18 | |
| 35 | 25000700 | AGR GROUND LIMESTONE | 9 | TON | $231.00 | $216.30 | |
| 36 | 25100115 | MULCH METHOD 2 | 9 | ACRE | $907.50 | $849.75 | |
| 37 | 25100630 | EROSION CONTR BLANKET | 463 | SQ YD | $1.54 | $1.44 | |
| 38 | 28000250 | TEMP EROS CONTR SEED | 900 | POUND | $3.48 | $1.94 | |
| 39 | 28000305 | TEMP DITCH CHECKS | 1,015 | FOOT | $19.63 | $15.86 | |
| 40 | 28000400 | PERIMETER EROS BAR | 478 | FOOT | $5.55 | $2.54 | |
| 41 | 28000500 | INLET & PIPE PROTECT | 9 | EACH | $161.13 | $152.02 | |
| 42 | 28100109 | STONE RIPRAP CL A5 | 5,353 | SQ YD | $41.79 | $29.44 | |
| 43 | 28200200 | FILTER FABRIC | 5,387 | SQ YD | $2.16 | $1.49 | |
| 44 | 31100100 | SUB GRAN MAT A | 70 | TON | $37.28 | $21.37 | |
| 45 | 31100300 | SUB GRAN MAT A 4 | 370 | SQ YD | $8.43 | $4.82 | |
| 46 | 31100700 | SUB GRAN MAT A 8 | 3,655 | SQ YD | $12.47 | $8.91 | |
| 47 | 31100910 | SUB GRAN MAT A 12 | 1,803 | SQ YD | $20.90 | $12.51 | |
| 48 | 31200100 | STAB SUBBASE 4 | 1,803 | SQ YD | $39.42 | $40.60 | |
| 49 | 40600290 | BIT MATLS TACK CT | 1,008 | POUND | $0.00 | $0.00 | |
| 50 | 42000080 | PVT CON PCC BR APP SL | 694 | SQ YD | $135.20 | $151.73 | |
| 51 | 42000516 | PCC PVT 10 3/4 JOINTD | 842 | SQ YD | $86.25 | $84.19 | |
| 52 | 42001300 | PROTECTIVE COAT | 2,503 | SQ YD | $0.00 | $1.93 | |
| 53 | 44000100 | PAVEMENT REM | 7,087 | SQ YD | $11.58 | $6.63 | |
| 54 | 44004250 | PAVED SHLD REMOVAL | 1,452 | SQ YD | $11.49 | $13.71 | |
| 55 | 44200050 | WELDED WIRE REINF | 110 | SQ YD | $27.32 | $5.62 | |
| 56 | 44200978 | CL B PATCH T1 11 | 10 | SQ YD | $245.00 | $335.11 | |
| 57 | 44200982 | CL B PATCH T2 11 | 10 | SQ YD | $230.00 | $335.11 | |
| 58 | 44200986 | CL B PATCH T3 11 | 60 | SQ YD | $205.00 | $242.10 | |
| 59 | 44200988 | CL B PATCH T4 11 | 50 | SQ YD | $195.00 | $280.24 | |
| 60 | 44201299 | DOWEL BARS 1 1/2 | 20 | EACH | $33.04 | $20.60 | |
| 61 | 44213200 | SAW CUTS | 150 | FOOT | $12.57 | $8.62 | |
| 62 | 44213204 | TIE BARS 3/4 | 30 | EACH | $18.35 | $5.15 | |
| 63 | 48101500 | AGGREGATE SHLDS B 6 | 1,965 | SQ YD | $15.32 | $10.75 | |
| 64 | 48203029 | HMA SHOULDERS 8 | 374 | SQ YD | $66.17 | $111.01 | |
| 65 | 48300515 | PCC SHOULDERS 10 3/4 | 961 | SQ YD | $72.29 | $80.03 | |
| 66 | 50100300 | REM EXIST STRUCT N1 | 1 | EACH | $82,585.14 | $163,832.13 | |
| 67 | 50100400 | REM EXIST STRUCT N2 | 1 | EACH | $81,350.90 | $163,832.13 | |
| 68 | 50104400 | CONC HDWL REM | 5 | EACH | $215.33 | $171.93 | |
| 69 | 50105220 | PIPE CULVERT REMOV | 1,006 | FOOT | $7.75 | $10.06 | |
| 70 | 50200100 | STRUCTURE EXCAVATION | 894 | CU YD | $25.57 | $12.26 | |
| 71 | 50300100 | FLOOR DRAINS | 22 | EACH | $338.68 | $519.18 | |
| 72 | 50300225 | CONC STRUCT | 605.4 | CU YD | $998.45 | $1,205.28 | |
| 73 | 50300255 | CONC SUP-STR | 678.3 | CU YD | $1,125.37 | $1,294.38 | |
| 74 | 50300300 | PROTECTIVE COAT | 2,783 | SQ YD | $1.24 | $1.79 | |
| 75 | 50301350 | CONC SUPSTR APP SLAB | 249 | CU YD | $362.12 | $447.58 | |
| 76 | 50500105 | F & E STRUCT STEEL | 1 | L SUM | $791,801.75 | $779,652.02 | |
| 77 | 50500505 | STUD SHEAR CONNECTORS | 14,094 | EACH | $2.46 | $2.28 | |
| 78 | 50800105 | REINFORCEMENT BARS | 59,610 | POUND | $1.32 | $1.25 | |
| 79 | 50800205 | REINF BARS, EPOXY CTD | 396,050 | POUND | $1.28 | $1.15 | |
| 80 | 50800515 | BAR SPLICERS | 444 | EACH | $35.10 | $35.18 | |
| 81 | 50800530 | MECHANICAL SPLICERS | 128 | EACH | $114.21 | $111.32 | |
| 82 | 51202100 | FUR STL PILE HP14X117 | 1,885 | FOOT | $103.79 | $119.33 | |
| 83 | 51202305 | DRIVING PILES | 1,885 | FOOT | $1.00 | $1.00 | |
| 84 | 51204650 | PILE SHOES | 52 | EACH | $165.00 | $162.42 | |
| 85 | 51500100 | NAME PLATES | 2 | EACH | $536.31 | $487.16 | |
| 86 | 51603000 | DRILLED SHAFT IN SOIL | 312.5 | CU YD | $691.94 | $1,359.58 | |
| 87 | 51604000 | DRILLED SHAFT IN ROCK | 130.5 | CU YD | $2,802.60 | $2,333.76 | |
| 88 | 52100520 | ANCHOR BOLTS 1 | 96 | EACH | $87.46 | $50.63 | |
| 89 | 5421D015 | P CUL CL D 1 15 TEMP | 334 | FOOT | $40.51 | $41.82 | |
| 90 | 5421D018 | P CUL CL D 1 18 TEMP | 176 | FOOT | $31.64 | $43.95 | |
| 91 | 54213663 | PRC FLAR END SEC 18 | 2 | EACH | $993.64 | $1,134.34 | |
| 92 | 54244405 | FL INLT BX MED 542546 | 2 | EACH | $2,627.73 | $2,605.49 | |
| 93 | 54248510 | CONCRETE COLLAR | 0.3 | CU YD | $1,264.67 | $5,273.27 | |
| 94 | 54262712 | METAL FL END SEC 12" | 4 | EACH | $386.39 | $386.41 | |
| 95 | 550A0090 | STORM SEW CL A 1 18 | 155 | FOOT | $56.13 | $49.42 | |
| 96 | 58600101 | GRANULAR BACKFILL STR | 432 | CU YD | $56.84 | $46.02 | |
| 97 | 59100100 | GEOCOMPOSITE WALL DR | 226 | SQ YD | $18.15 | $28.49 | |
| 98 | 60100060 | CONC HDWL FOR P DRAIN | 5 | EACH | $166.28 | $743.21 | |
| 99 | 60100945 | PIPE DRAINS 12 | 143 | FOOT | $45.24 | $45.85 | |
| 100 | 60108100 | PIPE UNDERDRAIN 4 SP | 122 | FOOT | $24.21 | $21.07 | |
| 101 | 60260100 | INLETS ADJUST | 1 | EACH | $3,376.75 | $1,589.85 | |
| 102 | 61000050 | CONC THRUST BLOCKS | 2 | EACH | $524.15 | $1,260.83 | |
| 103 | 61000225 | TY F INLET BOX 610001 | 2 | EACH | $4,508.48 | $3,442.88 | |
| 104 | 61000335 | TY G INLET BOX 610001 | 2 | EACH | $2,534.53 | $2,366.53 | |
| 105 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $4,180.00 | $3,914.00 | |
| 106 | 63200310 | GUARDRAIL REMOV | 312 | FOOT | $8.80 | $8.24 | |
| 107 | 63301210 | REM RE-E SPBGR TY A | 1,025 | FOOT | $16.50 | $15.45 | |
| 108 | 63500105 | DELINEATORS | 8 | EACH | $110.00 | $103.00 | |
| 109 | 64200116 | SHOULDER RUM STRIP 16 | 1,233 | FOOT | $12.30 | $20.31 | |
| 110 | 67000400 | ENGR FIELD OFFICE A | 29 | CAL MO | $2,000.00 | $1,678.56 | |
| 111 | 67100100 | MOBILIZATION | 1 | L SUM | $258,164.15 | $443,895.29 | |
| 112 | 70100420 | TRAF CONT-PROT 701411 | 1 | EACH | $1,742.88 | $20,729.16 | |
| 113 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $28,526.54 | $184,268.65 | |
| 114 | 70103815 | TR CONT SURVEILLANCE | 25 | CAL DA | $0.00 | $426.58 | |
| 115 | 70107025 | CHANGEABLE MESSAGE SN | 112 | CAL DA | $64.40 | $43.22 | |
| 116 | 70300100 | SHORT TERM PAVT MKING | 3,084 | FOOT | $0.6900 | $0.7200 | |
| 117 | 70300150 | SHRT TRM PAVT MK REM | 1,028 | SQ FT | $1.52 | $3.63 | |
| 118 | 70300220 | TEMP PVT MK LINE 4 | 41,615 | FOOT | $0.3500 | $0.3300 | |
| 119 | 70400100 | TEMP CONC BARRIER | 19,675 | FOOT | $20.63 | $25.09 | |
| 120 | 70400500 | TEMP CON BAR ST OWN | 14,600 | FOOT | $16.99 | $10.10 | |
| 121 | 70500665 | TEMP TR BAR TERM T6 | 2 | EACH | $4,730.00 | $3,811.00 | |
| 122 | 72400600 | RELOC SIN PAN ASSY TB | 1 | EACH | $316.15 | $1,130.53 | |
| 123 | 72501000 | TERMINAL MARKER - DA | 5 | EACH | $55.00 | $51.50 | |
| 124 | 78009004 | MOD URETH PM LINE 4 | 39,960 | FOOT | $0.9900 | $0.9300 | |
| 125 | 78100100 | RAISED REFL PAVT MKR | 13 | EACH | $397.14 | $391.40 | |
| 126 | 78100200 | TEMP RAIS REF PVT MKR | 1,198 | EACH | $6.60 | $7.24 | |
| 127 | 78100300 | REPLACEMENT REFLECTOR | 151 | EACH | $3.30 | $39.10 | |
| 128 | 78200005 | GRDRAIL REF TYPE A | 14 | EACH | $11.00 | $10.30 | |
| 129 | 78200006 | GRDRAIL REF TYPE B | 4,132 | EACH | $6.24 | $10.30 |