82-1-I
- Let date
- Friday, June 14, 2024
- Contract
- 76T47 · job page
- District
- District 8
- County
- St Clair
- Highway
- Limits
- Adding a new precast concrete vault that will contain two new flow meters installed on 12-inch piping that is the discharge from the 25th Street Pump Station-s deep groundwater wells in East St. Louis.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Hank's Excavating & Landscaping, Inc. Low bidder | $124,250 | ||
| 2 | Haier Plumbing and Heating, Inc. | $179,455 | +44.4% | |
| 3 | Korte and Luitjohan Contractors, Inc. | $191,967 | +54.5% | |
| 4 | CSD Environmental Services, Inc. | $380,600 | +206.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Hank's Excavati… | #2 Haier Plumbing … | #3 Korte and Luitj… | #4 CSD Environment… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X5610018 | FLOW METER | 2 | EACH | $42,500.00 | $50,500.00 | $67,388.00 | $94,880.00 | |
| 2 | X6026629 | FORCEMAIN CLNOUT VLT | 1 | EACH | $25,000.00 | $60,100.00 | $35,285.00 | $99,437.00 | |
| 3 | 20200100 | EARTH EXCAVATION | 50 | CU YD | $16.00 | $69.00 | $101.00 | $345.00 | |
| 4 | 20800150 | TRENCH BACKFILL | 10 | CU YD | $45.00 | $59.00 | $279.00 | $155.00 | |
| 5 | 28000400 | PERIMETER EROS BAR | 750 | FOOT | $4.00 | $0.0200 | $8.00 | $9.75 | |
| 6 | 67100100 | MOBILIZATION | 1 | L SUM | $5,000.00 | $10,700.00 | $4,001.00 | $42,790.00 | |
| 7 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $5,000.00 | $3,600.00 | $4,065.00 | $22,500.00 |