T-2BJR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Keeley & Sons, Inc. Low bidder | $1,048,120 | ||
| 2 | Keller Construction, Inc. | $1,156,651 | +10.4% | |
| 3 | The Kilian Corporation | $1,196,101 | +14.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Keeley & Sons, … | #2 Keller Construc… | #3 The Kilian Corp… |
|---|---|---|---|---|---|---|---|---|
| 1 | X7200201 | WIDTH RESTRICT SIGN | 1 | L SUM | $918.00 | $4,500.00 | $4,500.00 | |
| 2 | Z0001800 | APPROACH SL REP (PD) | 12.7 | SQ YD | $557.80 | $380.00 | $800.00 | |
| 3 | Z0001899 | JACK & REM EX BEARING | 36 | EACH | $2,880.00 | $2,000.00 | $2,600.00 | |
| 4 | Z0001903 | STRUCT STEEL REMOV | 9,810 | POUND | $3.55 | $5.60 | $2.65 | |
| 5 | Z0001905 | STRUCT STEEL REPAIR | 8,550 | POUND | $14.90 | $18.75 | $17.50 | |
| 6 | Z0016001 | DECK SLAB REP (FD-T1) | 21.9 | SQ YD | $2,980.00 | $2,600.00 | $3,200.00 | |
| 7 | Z0016200 | DECK SLAB REP (PART) | 5.4 | SQ YD | $787.80 | $2,400.00 | $800.00 | |
| 8 | Z0073200 | TEMP SHORING & CRIB | 1 | EACH | $18,945.00 | $13,000.00 | $27,000.00 | |
| 9 | 50102400 | CONC REM | 26.4 | CU YD | $1,690.10 | $2,440.00 | $3,600.00 | |
| 10 | 50300100 | FLOOR DRAINS | 60 | EACH | $497.80 | $550.00 | $500.00 | |
| 11 | 50300255 | CONC SUP-STR | 26.4 | CU YD | $2,998.50 | $3,500.00 | $5,500.00 | |
| 12 | 50300300 | PROTECTIVE COAT | 2,446 | SQ YD | $3.15 | $3.00 | $1.00 | |
| 13 | 50500405 | F & E STRUCT STEEL | 15,110 | POUND | $13.85 | $10.60 | $7.40 | |
| 14 | 50800205 | REINF BARS, EPOXY CTD | 4,090 | POUND | $3.65 | $3.20 | $2.70 | |
| 15 | 50800515 | BAR SPLICERS | 54 | EACH | $49.80 | $70.00 | $38.00 | |
| 16 | 52000110 | PREF JT STRIP SEAL | 166 | FOOT | $387.90 | $580.00 | $525.00 | |
| 17 | 52100010 | ELAST BEARING ASSY T1 | 36 | EACH | $797.80 | $2,450.00 | $1,800.00 | |
| 18 | 52100520 | ANCHOR BOLTS 1 | 72 | EACH | $123.70 | $190.00 | $225.00 | |
| 19 | 67000400 | ENGR FIELD OFFICE A | 5 | CAL MO | $2,765.00 | $2,900.00 | $2,400.00 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $62,890.00 | $73,500.00 | $119,975.00 | |
| 21 | 70100405 | TRAF CONT-PROT 701321 | 1 | EACH | $15,728.40 | $19,000.00 | $25,000.00 | |
| 22 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $20,145.00 | $19,905.20 | $25,000.00 | |
| 23 | 70106700 | TEMP RUMBLE STRIPS | 6 | EACH | $714.00 | $1,100.00 | $850.00 | |
| 24 | 70107005 | PAVT MK BLKOUT TAPE 5 | 1,565 | FOOT | $2.25 | $3.75 | $2.75 | |
| 25 | 70107025 | CHANGEABLE MESSAGE SN | 284 | CAL DA | $61.20 | $63.00 | $38.00 | |
| 26 | 70300150 | SHRT TRM PAVT MK REM | 651 | SQ FT | $0.3100 | $2.65 | $3.50 | |
| 27 | 70400100 | TEMP CONC BARRIER | 662.5 | FOOT | $49.80 | $30.00 | $32.00 | |
| 28 | 70400200 | REL TEMP CONC BARRIER | 662.5 | FOOT | $9.85 | $9.00 | $10.00 | |
| 29 | 70600235 | IMP ATTN TEMP FRD TL2 | 2 | EACH | $7,400.00 | $7,000.00 | $5,200.00 | |
| 30 | 70600320 | IMP ATTN REL FRD TL2 | 2 | EACH | $1,600.00 | $3,000.00 | $1,200.00 |