129RS-5
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Charles E. Mahoney Co. Low bidder | $1,138,537 | ||
| 2 | Christ Bros. Asphalt, Inc. | $1,246,814 | +9.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Charles E. Maho… | #2 Christ Bros. As… |
|---|---|---|---|---|---|---|---|
| 1 | X7030005 | TEMP PAVT MKING REMOV | 17,592 | SQ FT | $0.00 | $0.00 | |
| 2 | Z0033700 | LONG JOINT SEALANT | 23,610 | FOOT | $2.54 | $2.15 | |
| 3 | Z0034105 | MATL TRANSFER DEVICE | 4,653 | TON | $7.95 | $4.23 | |
| 4 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $2,266.95 | $15,185.00 | |
| 5 | Z0070100 | SURV MONUMENT COV ASY | 4 | EACH | $397.35 | $895.00 | |
| 6 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | |
| 7 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | |
| 8 | 40600290 | BIT MATLS TACK CT | 29,389 | POUND | $1.15 | $1.41 | |
| 9 | 40600990 | TEMPORARY RAMP | 248 | SQ YD | $30.00 | $0.00 | |
| 10 | 40604064 | HMA SC IL-9.5 D N90 | 4,653 | TON | $107.81 | $103.23 | |
| 11 | 40800029 | BIT MATLS TACK CT | 38 | POUND | $1.07 | $1.41 | |
| 12 | 40800050 | INCIDENTAL HMA SURF | 14 | TON | $159.18 | $250.00 | |
| 13 | 44000155 | HMA SURF REM 1 1/2 | 65,310 | SQ YD | $2.60 | $2.68 | |
| 14 | 44200144 | PAVT PATCH T2 12 | 48 | SQ YD | $196.57 | $253.00 | |
| 15 | 48203100 | HMA SHOULDERS | 819 | TON | $106.68 | $121.56 | |
| 16 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $2,557.12 | $2,500.00 | |
| 17 | 67100100 | MOBILIZATION | 1 | L SUM | $91,540.99 | $139,512.00 | |
| 18 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $5,500.00 | $0.00 | |
| 19 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $6,335.91 | $45,462.00 | |
| 20 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $0.00 | $45,462.00 | |
| 21 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $2,469.11 | $0.00 | |
| 22 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $9,078.66 | $0.00 | |
| 23 | 70102634 | TR CONT & PROT 701611 | 1 | L SUM | $3,358.11 | $0.00 | |
| 24 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $3,883.11 | $0.00 | |
| 25 | 70107025 | CHANGEABLE MESSAGE SN | 56 | CAL DA | $80.75 | $65.00 | |
| 26 | 70300100 | SHORT TERM PAVT MKING | 11,986 | FOOT | $0.00 | $1.76 | |
| 27 | 70300150 | SHRT TRM PAVT MK REM | 1,998 | SQ FT | $0.00 | $0.00 | |
| 28 | 70300210 | TEMP PVT MK LTR & SYM | 590 | SQ FT | $0.00 | $0.00 | |
| 29 | 70300220 | TEMP PVT MK LINE 4 | 50,934 | FOOT | $0.00 | $0.00 | |
| 30 | 70300250 | TEMP PVT MK LINE 8 | 981 | FOOT | $0.00 | $0.00 | |
| 31 | 70300260 | TEMP PVT MK LINE 12 | 572 | FOOT | $0.00 | $0.00 | |
| 32 | 70300280 | TEMP PVT MK LINE 24 | 288 | FOOT | $0.00 | $0.00 | |
| 33 | 78000100 | THPL PVT MK LTR & SYM | 590 | SQ FT | $8.00 | $8.00 | |
| 34 | 78000200 | THPL PVT MK LINE 4 | 50,934 | FOOT | $0.6400 | $0.6400 | |
| 35 | 78000500 | THPL PVT MK LINE 8 | 981 | FOOT | $1.00 | $1.00 | |
| 36 | 78000600 | THPL PVT MK LINE 12 | 572 | FOOT | $8.00 | $8.00 | |
| 37 | 78000650 | THPL PVT MK LINE 24 | 288 | FOOT | $12.00 | $12.00 | |
| 38 | 78100100 | RAISED REFL PAVT MKR | 517 | EACH | $28.78 | $29.07 | |
| 39 | 78300200 | RAISED REF PVT MK REM | 517 | EACH | $17.16 | $0.00 | |
| 40 | 88600600 | DET LOOP REPL | 1,430 | FOOT | $4.00 | $4.00 |