(14-14,14-15)PP-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | DMS Contracting, Inc. Low bidder | $392,923 | ||
| 2 | G. M. Sipes Construction, Inc. | $442,595 | +12.6% | |
| 3 | Petroff Trucking Company, Inc. | $499,131 | +27.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 DMS Contracting… | #2 G. M. Sipes Con… | #3 Petroff Truckin… |
|---|---|---|---|---|---|---|---|---|
| 1 | X4406020 | PART DEP REM T1 2 | 80 | SQ YD | $49.90 | $100.00 | $105.00 | |
| 2 | X4406220 | PART DEP REM T2 2 | 84 | SQ YD | $35.65 | $90.00 | $105.00 | |
| 3 | X4406420 | PART DEP REM T3 2 | 83 | SQ YD | $24.00 | $90.00 | $105.00 | |
| 4 | X4421000 | PARTIAL DEPTH PATCH | 31 | TON | $290.35 | $950.00 | $330.00 | |
| 5 | 44200529 | CL A PATCH T2 8 | 748 | SQ YD | $204.35 | $215.00 | $190.00 | |
| 6 | 44200533 | CL A PATCH T3 8 | 176 | SQ YD | $200.05 | $215.00 | $190.00 | |
| 7 | 44200535 | CL A PATCH T4 8 | 484 | SQ YD | $109.00 | $210.00 | $190.00 | |
| 8 | 44213000 | PATCH REINFORCEMENT | 1,408 | SQ YD | $4.85 | $15.00 | $55.00 | |
| 9 | 44213200 | SAW CUTS | 5,829 | FOOT | $5.55 | $0.0100 | $5.50 | |
| 10 | 44213204 | TIE BARS 3/4 | 134 | EACH | $24.90 | $25.00 | $15.00 | |
| 11 | 67100100 | MOBILIZATION | 1 | L SUM | $26,100.00 | $22,000.00 | $25,000.00 | |
| 12 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $44,865.00 | $16,875.00 | $10,000.00 | |
| 13 | 70100420 | TRAF CONT-PROT 701411 | 1 | EACH | $1,500.00 | $4,550.00 | $10,000.00 | |
| 14 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $4,500.00 | $5,675.00 | $10,000.00 | |
| 15 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $0.0100 | $0.0100 | $7,600.00 | |
| 16 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $2,680.00 | $3,775.00 | $9,525.00 | |
| 17 | 78001110 | PAINT PVT MK LINE 4 | 2,686 | FOOT | $1.25 | $1.32 | $1.30 | |
| 18 | 78100100 | RAISED REFL PAVT MKR | 52 | EACH | $165.50 | $170.50 | $160.00 |